Newcastle City Council
Planning and Transport Strategy Committee, Thursday 26 February 2009 at 4.30pm

Heart of Walker: Supplementary Planning Document ( SDP)

Noted Planning 3 papers

Planning and Transport Strategy Committee noted this item on Thursday 26 February 2009. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED – That:- (i) the issues raised as part of the consultation process and the ongoing work to address the issues be noted where appropriate; (ii) the Supplementary Planning Document for the Heart of Walker be adopted, subject to the following amendments and additions:- (a) paragraph 7.5 – Risk – reference be added to the need for revenue funding for maintenance (this reference also to be included in paragraph 5.4.1 reference to open space, paragraph 5.4.4 reference to hard landscaping and paragraph 5.9 reference to management and maintenance); (b) a further report with information on retail and residential issues be submitted; (c) in paragraph 5.6.3 – Parking – the wording be amended to reflect the fact that although drop off parking for primary school element had been relaxed it was important to ensure that parking solution was safe and accessible to local residents and others; (d) in paragraph 7.1 – Kkey Enquiry Themes – reference be added to the type and tenure of housing, community facilities and bus services.
Word for word from the decision Newcastle published for this meeting. Source: democracy.newcastle.gov.uk

Follow this further

Built from Newcastle's papers

What the report saysPro

Report to Planning and Transport Strategy Committee

1 C:\moderngov\data\published\Intranet\C00000139\M00001087\AI00007121\HoWapp10.doc

HEART OF WALKER FINAL DRAFT SUPPLEMENTARY PLANNING DOCUMENT FEBRUARY 2009

Harvey Emms, Director Strategic Housing, Planning and Transportation

Service / Document Location Version: Issued By: Classification: Directorate: and Title: ABR/E&R HoW SPD v.13 C Wood Draft 2 C:\moderngov\data\published\Intranet\C00000139\M00001087\AI00007121\HoWapp10.doc

Heart of Walker Supplementary Planning Document

Contents

1.0Purpose of this document 1.1 Roles and responsibilities 1.2 Status and version 1.3 Relevant plans and policies 1.4 List of (WRAAP) planning policies to be delivered by the HOW SPD 1.5 Minor departures from the WRAAP 1.6 Planning framework

2.0Background 2.1 Site details

3.0Vision and objectives 3.1 Creating this vision and objectives 3.2 Vision 3.3 Objectives 3.4 Timescales for delivering this vision

4.0Feasibility 4.1 Site constraints

5.0Planning and design 5.1 Design concept 5.2 Preferred uses 5.3 Development form 5.4 Landscape 5.5 Public realm art 5.6 Proposed movement 5.7 Safety and security 5.8 Energy, waste and water 5.9 Management and maintenance

6.0Development phasing 6.1 Outline phasing approach

7.0Further engagement 7.1 Key engagement themes

8.0Planning applications 8.1 Outline planning application 8.2 Planning submission requirements

Appendices X1 Glossary X2 Sport England exemption policies X3 Historical morphology X4 Underlying morphology X5 Regeneration responses Service / Document Location Version: Issued By: Classification: Directorate: and Title: ABR/E&R HoW SPD v.13 C Wood Draft 3 C:\moderngov\data\published\Intranet\C00000139\M00001087\AI00007121\HoWapp10.doc

Map 1 – Heart of Walker in relation to Newcastle City Centre

Map 2 – Aerial photograph of the Heart of Walker area

Service / Document Location Version: Issued By: Classification: Directorate: and Title: ABR/E&R HoW SPD v.13 C Wood Draft 4 C:\moderngov\data\published\Intranet\C00000139\M00001087\AI00007121\HoWapp10.doc

1.0Purpose of this document

This document is intended to be a clear statement of the development which is sought, including a spatial masterplan and policies addressing key principles to be followed in developing the site. The guidance in this document will be an important material consideration for any Planning Application relating to this site. This function will help to ensure that the shared vision is embodied in the development which is delivered in this area.

Diagram 1: relationship between this document and other documents

1.1Roles, responsibilities, monitoring

This document has been produced by Newcastle City Council, with contributions drawn from collaboration between several internal teams and from many external partners and community representatives. Any revision of this document will be considered by the Council Executive sub committee responsible for Planning and Transportation guidance. This document will be ‘monitored’ on an annual basis within the management process already in place to monitoring the Walker Riverside Area Action Plan (WRAAP). It is the responsibility of potential developers to ensure they are referring to up-to-date planning guidance, including this document and any other relevant policy or plan in operation at the time of making planning applications. Any queries should be addressed to the Project Manager for the Heart of Walker - refer to the back cover for details.

1.2Status and version

This is a Supplementary Planning Document [SPD] applicable to a specific site area identified under the adopted Walker Riverside Area Action Plan Development Planning Document [DPD], which itself is part of Newcastle’s Local Development Framework [LDF]. This is the final version as adopted by Newcastle City Council on 26th February 2009.

1.3Relevant plans and policies

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Heart of Walker: Supplementary Planning Document ( SDP)Supplementary 93 KB Download
PDF
HoW app1Report 14 MB DownloadRead as text
PDF
HoW app2Report 27 KB Download

At this meeting

Whole meeting
3The East Pilgrim Street Regeneration Opportunity Area: Interim Planning GuidanceAgreed
4Heart of Walker: Supplementary Planning Document ( SDP)This decision

On this subject at Newcastle

Search all
  1. Heart of Walker: Supplementary Planning Document ( SDP)This decision
  2. Investment in the Heart of WalkerAgreed

More from Newcastle Planning and Transport Strategy Committee

All decisions
MeetingDecisionOutcome
26 Feb 2009 The East Pilgrim Street Regeneration Opportunity Area: Interim Planning GuidanceThe Committee agreed to endorse the draft IPG for publication and further consultation, subject to:- ( i ) clarificat... Agreed Open
22 Jan 2009 Draft Gosforth Conservation Area Management Plan-Supplementary Planning DocumentResolved that a) the draft Conservation Area Management Plan Supplementary Planning Document in relation to the Gosfo... Approved Open
22 Jan 2009 Draft Brandling Village and South Jesmond Conservation Area Management Plans, Development Guidance Notes (DNGs)Resolved that:- a) the draft Conservation Area Management Plan Development Guidance Note (CAMP DGN) in relation to th... Approved Open
25 Sep 2008 Minutesa) The minutes of the meeting held on 24 July 2008 were agreed as a correct record. b) The minutes of the meeting hel... Agreed Open
25 Sep 2008 The Former Scottish and Newcastle Brewery (Science Central) MasterplanThe Committee agreed: a) to note the preliminary findings of the latest consultation exercise undertaken on 8 July 20... Agreed Open