The Procurement Committee:- ( i ) noted the content of this report; (ii) noted that client officers are being advised to consult with their appropriate Executive Member, after obtaining the written approval of the City Treasurer, on all Negotiated Procurements that have a value of over £100k.
Word for word from the decision Newcastle published for this meeting.Source: democracy.newcastle.gov.uk
2. Note that client officers are being advised to consult with their appropriate Executive Member, after obtaining the written approval of the City Treasurer, on all Negotiated Procurements that have a value of over £100K. 3. Introduction
3.1Generally, the Procurement Procedure Rules (PPR) require competitive quotations or tenders for any contract over £5,000. However, section 3E of the Rules allows for contracts to be negotiated with one firm only, without competition, in exceptional circumstances. The conditions which must be satisfied if this option is to be used are as follows:
1. Delegated Officer must certify in writing, using a proforma Authorisation to Negotiate Form, that it is in the Council’s best interests to negotiate the contract rather than invite competitive bids. In cases of real urgency, where prior authorisation is impractical, retrospective authorisation is allowed;
2. If the contract is estimated over £100K, the City Treasurer’s written approval to the negotiation must also be obtained;
3. Where the estimated value of the contract is over £100,000, the relevant Executive Member must be consulted before authorisation to negotiate is given. If that Member so requests, the authorisation shall not be given without the matter being reported to Procurement Committee (or in a case of urgency to a delegated sub-committee of that Committee) and the approval of that Committee (or sub- committee) being obtained. For these purposes, ‘the relevant Executive Member’ is that member of Executive within whose portfolio the proposed contract falls or in the absence of such member his or her Executive Support Member (if any) or in the absence of any such person any other member of Executive.
4. Negotiation must be allowed under EU Procurement Regulations if the contract value is above the EU threshold;
5. The Authorisation to Negotiate Form must be lodged (immediately after it has been signed) with the City Treasurer and Corporate Procurement Team, who must also be advised in writing of the details of any contract resulting from the negotiation;
6. The Delegated Officer shall only award any resultant contract if satisfied the negotiated price and other terms and conditions represent best value for money and will be in the best interests of the Council
7. A full written record of the negotiation process must be kept.
3.2PPR. 3.26 requires the Assistant General Manager (Procurement) in collaboration with the Head of Legal Services to report to this Committee each Contract with a total estimated value of £5,000 or more that has been let without formal competition. Every such report shall highlight any case where a retrospective authorisation has been given under PPR 3.22.1. 4. Current Position
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Playgroup and Nursery ProvisionRESOLVED – That Procurement agreed to: ( i ) Authorise the commencement of retrospective contract negotiations with i...
Regional Legal Services Framework PanelRESOLVED – That Procurement agreed to: ( i ) Approve a collaborative procurement exercise to put in place a 4 year Fr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.