The Procurement Committee:- (i) noted the progress made to date by the Corporate Procurement and Efficiency Team in developing the Corporate Efficiency Programme and contributing to the preliminary work of the Corporate Transformation Programme; (ii) requested that a further report is provided to Procurement Committee in September 2009.
Word for word from the decision Newcastle published for this meeting.Source: democracy.newcastle.gov.uk
• Note the progress made to date by the Corporate Procurement & Efficiency Team in developing the Corporate Efficiency Programme and contributing to the preliminary work of the Corporate Transformation Programme;
• Request that a further report is provided to Procurement Committee in September 2009.
Background
3.1Efficiency is defined as achieving the same outputs for less resource or additional outputs for the same resource. An action that fully or partially alleviates a cost pressure is countable as a cash releasing efficiency, but an action that frees up cash at the expense of the overall effectiveness of service delivery is not an efficiency gain. 3.2 The Government has ruled out providing additional money to help local councils meet rising transport, energy, fuel and food costs. In the context of tight financial settlements for the Council, these rising cost pressures mean that the council has had to radically increase the pace of its efficiency programme and achieve more efficiency savings to avoid cutting key services to the public and protect local taxpayers from having to pay more to meet the rising costs.
3.3In June 2007 the Council employed a Strategic Development Officer (Efficiency) to support the Head of Efficiency in the delivery of a number of Corporate Efficiency Projects as a preliminary phase to the Corporate Transformation Programme.
This report presents a summary of progress to date: • Corporate Postage • Printer Rationalisation • Corporate Travel • Corporate Telephony • Agency Staff
4. Corporate Postage
4.1Spend on Post in the last financial year was approximately £1.25m. A recent review identified significant opportunities for improvements and efficiencies with savings estimated at £125k in 2009/10.
4.2The Council’s existing postal arrangements are ineffective and inefficient compared to what is achievable both in the short and long term. Work is being undertaken to improve and streamline the management of post across the Council that will deliver cashable efficiency savings for all directorates.
4.3The introduction and compliance with agreed postage standards will bring immediate financial benefits. These will be delivered through; • Moving away from franking machines to and “clean mail” (Royal Mail Product attracting 12.5% saving) for day to day mail • Ensuring all bulk mailing maximises those tariff discounts available through Royal Mail (Mailsort and Walksort) • Standardisation of envelopes for outgoing post, • Standardisation of class of post • Reducing in postage licenses.
4.4Activity in the medium to long term will include activity to undertake soft market testing and/or a procurement exercise to explore more innovative and radical arrangements around postage, printing and new technology. 5 Printer Rationalisation
5.1The current annual cost of ownership for printing in the Council is £2.04m. A project is underway which is anticipated to deliver savings of £515k over a five year period.
5.2Printers in the Council have suffered from a legacy of little strategic overview and limited controls. This has resulted in the Council being in a position of having 1 printer to every 3 people, whereas the industry standard is nearer to 1 printer to every 15 people.
5.3The project will focus on; • Reducing the council’s laser / desktop device estate and see a migration to fewer, more cost effective multi function devices (MFD). • Pushing high volume print jobs to more cost effective solutions (Digital Print)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Playgroup and Nursery ProvisionRESOLVED – That Procurement agreed to: ( i ) Authorise the commencement of retrospective contract negotiations with i...
Regional Legal Services Framework PanelRESOLVED – That Procurement agreed to: ( i ) Approve a collaborative procurement exercise to put in place a 4 year Fr...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.