Executive agreed to:- a) Agree the capital programme for 2010-11 to 2013-14 analysed at scheme level by portfolio in Appendix A; b) Note the total capital resources available for 2010-11 as detailed in Appendix B; c) Approve the schemes listed at section 5.3.5, to be funded by part of the £8.3m Prudential Borrowing allocation, subject to the approval of the revenue budget to fund the borrowing costs, and; d) Approve refurbishment of Gosforth Pool, total scheme cost of £1.2m including prudential borrowing of £0.250m; e) Approve increased Prudential Borrowing for Your Homes Newcastle Furniture Service of £1.831m in 2010/11 (£0.706m 09/10), and agree funding swap for the Heat Metering system (£0.655m) from Major Repairs Allowance to Prudential Borrowing (09/10).
Word for word from the decision Newcastle published for this meeting.Source: democracy.newcastle.gov.uk
1.1This report gives details of the Capital Programme for 2010-11. It also sets out the capital programme prospects for 2011-12 to 2013-14. At this stage the figures for 2010-11 are known in more detail, whereas the resource position for 2011-12 to 2013-14 is less certain, which means that the programme that we are aware of for those three years is at a lower level than in 2010-11, but is likely to increase as additional resources and projects are confirmed. 1.2 The capital programme has been prepared against the background of an economic recession, where land and property prices have fallen; loan finance has been less accessible to individuals and businesses, construction related employee cost pressures have eased and the Council is able to access cheaper loan finance. This has impacted on the capital programme in several ways; - 1. The level of capital receipts that the Council is able to generate at this time has reduced significantly, putting pressure on the Corporate Resource Pool. In response to this it is proposed that the Council undertakes more Prudential Borrowing to fund new schemes which would maintain the high level of the capital programme. 2. The decline in property prices is now presenting opportunities for strategic property acquisitions to help the Council meet its regeneration and capital strategy objectives, working with our public and private sector partners. 3. The pressure on national public finances will result in a significant reduction in Government support for capital investment from 2011/12 onwards. As the majority of our capital funding has come from Government the level of our capital programme will be significantly lower than it has been in recent years. 1.3 The key elements of the Capital Programme, include :- • A capital programme for 2010-11 of £219,816m (excluding PFI funded investment), this includes over-programming and outturn expenditure is likely to be lower than this and closer to £200million; • PFI funded investment of £43m in 2010-11 and £26m from 2011- 2014; • Anticipated grant funding of at least £79m in 2010-11 (plus whatever private sector leverage this may also help to secure). • A potential 4-year capital programme of at least £500m excluding PFI investment of £69m, which may increase further as additional resources are identified.
1.4The overall 2010-11 to 2013-14 programme includes investment in the following areas: • Building Schools for the Future investment of £29m during the next two years; • Social housing investment under the Decent Homes programme of £73.845m in 2010-11 and £49.726m in 2011-12; • Anticipated £8.3m infrastructure and regeneration investment to address the impact of the current economic downturn, funded by Prudential Borrowing, subject to the agreement of a revenue budget contribution to finance the borrowing costs; • Investment in area based regeneration schemes of £21.026m in 2010- 11 and anticipated future expenditure of £24.501m in 2011-12, £23.624m in 2012-13 and £23.624m in 2013-14 • Investment in highways and transport infrastructure of £12.428m in 2010-11 and anticipated future expenditure of £11.086m in 2011-12, £8.710m in 2012-13 and £8.840m in 2013-14.
Recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.