Cabinet agreed to: (i) Note the latest level of 2011-12 capital programme and approve the inclusion of the new schemes and changes to the existing schemes into the capital programme as outlined in section 3 and Annex 2 of this report; (ii) Approval re-phasing of the Byker Trust budget of £1.495 million, funded through corporate prudential borrowing as outlined in section 4.1 of this report; (iii) Approve re-phasing of £1.822 million for Central Walker C of E Primary School new build, funded through Primary Strategy Grant as outlined in section 4.2 of this report; (iv) Approve the inclusion in the capital programme of £1.117 million for Pottery Bank Phase 2 capital works, to be funded from New Homes Bonus and YHN resources as outlined in section 4.3 of this report; (v) Approve re-phasing of £1.591 million and a reduction of £1.367 million in the Civic Centre capital programme, as outlined in section 4.4 of this report; (vi) Approve removal of Strategic Sites budget of £1.955 million, as outlined in section 4.5 of this report; (vii) Approve inclusion in the capital programme of the Riverside Dene Demolitions £2.252 million, to be funded from HRA resources as outlined in section 4.6 of this report; (viii) Approve inclusion in the capital report Public Space CCTV £0.110 million, to be funded the corporate resource pool as outlined in section 4.7 of this report; (ix) Approve inclusion in the capital programme £0.084 million of increased costs for infrastructure works at Barrack Road / Strawberry Place, to be funded from as outlined in section 5.1 of this report; and (x) Approve inclusion in the capital programme increased costs of £0.177 million for work at Virginia House Hostel, to be funded from a mixture of re-aligned corporate resource pool, New Homes Bonus and, Adult Services capital grant as outlined in section 5.2 of this report.
Word for word from the decision Newcastle published for this meeting.Source: democracy.newcastle.gov.uk
1.1This report sets out new capital schemes and changes to the 2011-12 capital programme, which have been identified since the start of the financial year. A full listing of changes to the capital programme and an analysis by directorate/division/ward is available on the City Council’s internet site on Your Council / Budget and Annual Report / Capital Programme Updates Reports 1.2 The current programme is £173.334 million for direct capital expenditure in 2011-2012, with a further £17.812 million of capital investment funded through Building Schools for the Future (BSF) schemes, giving total estimated investment level of £191.146 million in the year. 2. Recommendations
2.1Cabinet is recommended to :
2.1.1 Note the latest level of 2011-12 capital programme and approve the inclusion of the new schemes and changes to the existing schemes into the capital programme as outlined in section 3 and Annex 2 of this report;
2.1.2 Approval re-phasing of the Byker Trust budget of £1.495 million, funded through corporate prudential borrowing as outlined in section 4.1 of this report;
2.1.3 Approve re-phasing of £1.822 million for Central Walker C of E Primary School new build, funded through Primary Strategy Grant as outlined in section 4.2 of this report;
2.1.4 Approve the inclusion in the capital programme of £1.117 million for Pottery Bank Phase 2 capital works, to be funded from New Homes Bonus and YHN resources as outlined in section 4.3 of this report;
2.1.5 Approve re-phasing of £1.591 million and a reduction of £1.367 million in the Civic Centre capital programme, as outlined in section 4.4 of this report; 2.1.6 Approve removal of Strategic Sites budget of £1.955 million, as outlined in section 4.5 of this report;
2.1.7 Approve inclusion in the capital programme of the Riverside Dene Demolitions £2.252 million, to be funded from HRA resources as outlined in section 4.6 of this report;
2.1.8 Approve inclusion in the capital report Public Space CCTV £0.110 million, to be funded the corporate resource pool as outlined in section 4.7 of this report;
2.1.9 Approve inclusion in the capital programme £0.084 million of increased costs for infrastructure works at Barrack Road / Strawberry Place, to be funded from as outlined in section 5.1 of this report;
2.1.10 Approve inclusion in the capital programme increased costs of £0.177 million for work at Virginia House Hostel, to be funded from a mixture of re-aligned corporate resource pool, New Homes Bonus and, Adult Services capital grant as outlined in section 5.2 of this report, and;
3. Financial Issues
3.1Capital Programme Variations
3.1.1 The movement in the programme since Oct is analysed by funding source in Table 1 and by directorate and reason for variation in Annex 2. Significant changes to the programme are highlighted in section 4. 3.1.2 Capital investment is funded from the following sources in 2011-12. Table 1 : Capital Funding Oct 11 Jan 12 Change £’000 £000’s £’000 Balance Sheet Provisions 14,487 19,088 4,601 Supported Borrowing 673 728 55 Unsupported Borrowing 63,954 57,154 (6,800) Capital Contributions 5,181 5,242 61 Capital Receipts 1,932 831 (1,101) Corporate Resource Pool 9,037 5,908 (3,129) Grants 45,551 44,445 (1,106) Revenue Contributions 4,455 4,505 50 Major Repairs Allowance 35,944 35,433 (511) TOTAL FUNDING 181,214 173,334 (7,880) Over-programming 20,668 12,551 (8,117) Total Programme 201,882 185,885 (15,997)
Note 1: October figures reflect programme approvals taken at October Cabinet and specific Project Approvals taken at November and December Cabinet. 4. Reasons For Significant Movements In The Capital Programme
4.1Byker Trust (-£1.495 million)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.