Resolved
Cabinet agreed to receive the report.
Cabinet agreed this item on Wednesday 25 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Cabinet agreed to receive the report.
Portfolio: Quality of Life
Cabinet 25 January 2012
Public Space CCTV Update
Report by: Executive Director of Environment and Regeneration
Ward Implications: All For Information
1. Purpose of the report 1.1 This report is to update cabinet on the progress being made to address the functionality of Public Space CCTV cameras across the city.
2. Recommendations 2.1 Cabinet is recommended to receive the report.
3. Introduction and background 3.1 In July of 2011, the CCTV Delivery Group commissioned an independent assessment of 31 cameras that were identified as either: • not having funding towards running costs, • not operational, or • presenting potential risks to the Council’s reputation in its use of CCTV to effectively tackle crime and disorder.
The CCTV Delivery Group considered the findings and recommendations that arose from the report. Operational Requirements for each of identified cameras were established together with an indicative cost to carry out remedial work that would enable the cameras to operate to a standard acceptable to the criminal justice system.
Following detailed discussions of the report’s recommendations, and subsequent publicity surrounding CCTV across the city in October and November 2011, a business case seeking capital investment of £110,000 to carry out essential works was submitted and approved through the delegated decision making process. This was approved on 1 December 2011.
1 4. Proposals 4.1 The proposal is to:
• Reinstate the operational functionality of 13 cameras, as agreed through member and partner consultation. • Decommission the use of 6 cameras that are no longer operationally required as agreed through member and partner consultation. • To make additional refurbished Re-deployable CCTV cameras available within neighbourhoods where cameras are decommissioned. • To expand the wireless network infrastructure for CCTV use, providing the opportunity to reduce the use and future cost of lease line transmission services.
5. Resource and legal implications
5.1Financial 5.1.1 The capital costs of restoring all necessary CCTV cameras to use are set out in the delegated decision report. The capital expenditure is to be met from the Environment & Regeneration capital programme.
5.1.2 As a consequence of returning a number of cameras back to operationally functional levels, there will be ongoing revenue implications. These are estimated at £10,500.00 pa for preventative maintenance, and £10,500.00 pa for energy supplies, it has been agreed that these cost will be met through corporate contingencies.
5.1.3 Safe Newcastle are to invest a further £10,000 in equipment that will build growth and contingency into the CCTV wireless network, providing a link that will allow a greater number of cameras to become wireless and reduce future revenue demands.
5.1.4 The next step is to discuss the proposed funding arrangements with the wards where cameras are located or planned. The costs required for the upgrade of or new purchase of re-deployable cameras will remain the responsibility of ward budgets. 5.2 Any additional comments from the Director of Finance and Resources There are no further comments 5.3 Legal There are no legal implications. 5.4 Other implications There are no implications for cabinet to note.
6 Progress to date 6.1 Since the issue of none operational cameras was escalated work has been ongoing to ensure all cameras that are required, are functional and those that may not be required are identified and plans put in place to remove them.
Work progressed to date includes:
2 • Welbeck Road camera reinstated • Operational Requirements established for indentified cameras • Surveys of the key cameras carried out to establish the level of remedial work required. • Agreement with ward members and portfolio lead for decommissioning of cameras • Installation of 10 new re-deployable cameras in the east of the city. • Planning with Outer West wards for up to 10 camera re-deployment replacement. Funding yet to be confirmed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Public Space CCTV UpdateReport | 227 KB | DownloadRead as text |
Follow Cabinet at Newcastle and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Property Team Response to the Corporate Scrutiny Committee Commercial Property Development Spotlight ReviewSummary Consideration was given to a report which outlined the response to recommendations received by Cabinet in Jun... | Agreed | Open |
| 21 Sep 2026 | Council PlanSummary Consideration was given to the 2026-2029, which set out six priority outcomes that will drive activity to ach... | Agreed | Open |
| 21 Sep 2026 | Scrutiny Response to the Draft Council PlanSummary Consideration was given to a report which outlined the findings and recommendations of the Corporate Scrutiny... | Agreed | Open |
| 21 Sep 2026 | Council Tax SupportSummary Consideration was given to a report which set out possible options for amendments to the working age scheme a... | Refused | Open |
| 21 Sep 2026 | Quarter 1 Projected OutturnSummary Consideration was given to a report which set out the outturn position for Quarter One, for all council servi... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.