Resolved
That the work undertaken by Internal Audit since the last committee meeting in November 2011 be noted.
North East Museums Finance, Audit and Risk Committee noted this item on Monday 20 February 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
That the work undertaken by Internal Audit since the last committee meeting in November 2011 be noted.
Tyne & Wear Archives & Museums Audit Committee
20 February 2012
Internal Audit Progress Report
Report by: Head of Audit and Strategic Risk For Information
1. Introduction This report shows Internal Audit activity since the last Audit Committee meeting in November 2011.
2. Report Priority Level Medium (For Information)
3. Executive Summary The following table summarises the key areas of Internal Audit activity since the last Audit Committee meeting:
Assessment Comments Progress against the Annual Good 2 final reports issued and Audit Plan 2011/12 (see Counter Fraud Training section 4) delivered. Draft reports issued for remaining 3 audits. Management implementation Satisfactory Progress towards of recommendations (see implementing all section 6) recommendations has been made but there are delays in some areas. Internal Audit Performance Satisfactory On target for delivery Indicators 2011/12 (see section 7)
4. Progress against the Annual Audit Plan 2011/12 The table below provides a summary of progress against the audit plan for 2011/12 agreed by Committee in February 2011. Planned Audit Status Comments Counter Fraud Training Complete Training delivered to middle management in May 2011. Design and Exhibition Final report issued Services Tyne and Wear Archives Final report issued Financial Control Draft report issued. Unannounced income Draft report issued. audit – Laing Art Gallery Unannounced income Draft report issued. audit – South Shields Museum Procurement (See Note Audit removed from 1) plan and replaced by Unannounced Income Audits.
Note 1 The Senior Manager, TWAM, contacted Internal Audit in December 2011 regarding a loss of £20 from petty cash at the Laing Art Gallery. As a result of this discussion it was agreed that Internal Audit would undertake unannounced visits to 2 sites, Laing Art Gallery and South Shields Museum, to review the income collection and management arrangements.
Given the limited resources available within the Internal Audit plan it was necessary to free up resource to undertake this work. The 2011/12 Annual Internal Audit Plan included a Procurement audit and the scope of this was to review the proposed implementation of the electronic procurement system. However, implementation is now planned for April 2012 and therefore it was felt appropriate to defer this work and reallocate the resources to the unannounced visits.
This proposed approach was discussed with the Chair of the Audit Committee who confirmed it was acceptable to revise the plan accordingly.
5. Update on fraud work Internal Audit have no fraud investigations ongoing with TWAM. The loss of money form the Laing Art Gallery mentioned in Section 4 was investigated internally by TWAM management.
6. Recommendations Follow Up 6.1 Management is responsible for implementing all audit recommendations. Internal Audit follows up all high and medium priority recommendations to verify implementation. This provides assurance that those recommendations which are both fundamental and important to the organisation’s system of control are addressed. As low priority recommendations are not vital to Tyne & Wear Archives & Museum’s system of internal control these are not followed up by Internal Audit.
6.2Table 1 below provides a summary of the current status of all Internal Audit recommendations issued in respect of audits completed as part of the 2010/11 and 2011/12 audit plans.
Table 1 - Summary of implementation of Internal Audit recommendations
2011/12 2010/11 High Med Total High Med Total Recommendations n/a 3 3 n/a 11 11 Issued Implementation not yet n/a 0 0 n/a 1 1 due Recommendations due n/a 3 3 0 10 10 for implementation Implementation confirmed n/a 3 3 0 7 7 by management and verified by Internal Audit Implementation delayed n/a n/a n/a 0 3 3 (see Table 2) Percentage of n/a 100% 100% n/a 70% 70% recommendations due implemented Target 100% 100% 100% 100% 100% 100%
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Monitoring reportReport | 135 KB | DownloadRead as text |
Follow North East Museums Finance, Audit and Risk Committee at Newcastle and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Mar 2014 | Minutes of the Meeting held on 18 November 2013RESOLVED – That the minutes of the meeting held on 18 November 2013 were agreed as a correct record and signed by the... | Agreed | Open |
| 3 Mar 2014 | Annual Governance Statement 2013/14RESOLVED that - a) The draft roles & responsibilities, timescales and terms of reference are adopted as the basis for... | Approved | Open |
| 3 Mar 2014 | Internal Audit Plan 2014-15RESOLVED that - 1) The Internal Audit Plan for 2014/15 be agreed. 2) The performance indicators as set out in paragra... | Agreed | Open |
| 3 Mar 2014 | TWAM Strategic Risk Register Review and FrameworkRESOLVED that - 1) The Risk Management Framework be submitted to the Joint Committee for their approval. 2) The Treas... | Approved | Open |
| 3 Mar 2014 | TWAM Value for Money StrategyRESOLVED that - 1) The Value for Money Strategy (Appendix A) be approved. 2) The Value for Money Strategy be submitte... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.