Resolved
RESOLVED that - 1) The Internal Audit Plan for 2014/15 be agreed. 2) The performance indicators as set out in paragraph 4 of the report be agreed.
North East Museums Finance, Audit and Risk Committee agreed this item on Monday 3 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that - 1) The Internal Audit Plan for 2014/15 be agreed. 2) The performance indicators as set out in paragraph 4 of the report be agreed.
Tyne & Wear Archives & Museums Audit Committee
3 March 2014
Internal Audit Plan 2014/15
Report by: Head of Internal Audit For Information
1. Introduction The Public Sector Internal Audit Standards (PSIAS) require the Head of Internal Audit to: • Establish risk-based plans to determine the priorities of the internal audit activity, which are consistent with the organisation’s goals • Take into account the requirement to produce an annual internal audit opinion and assurance framework. • Base the activity plan of engagement on a documented risk assessment undertaken at least annually. The input of senior management and the Audit Committee must be considered. • Ensure that internal audit resources are appropriate, sufficient and effectively deployed to achieve the approved plan.
Audit Committee agreed a Strategic Audit Plan 2013/14-2015/16 at its meeting in May 2013. In line with PSIAS the Head of Internal Audit has undertaken an annual review of the plan and prepared an Internal Audit Plan for 2014/15 which is attached at Appendix I.
2. Report Priority Level Medium (For Decision)
3 Background 3.1 Priorities and Key Considerations
The 2014/15 audit plan includes allocated time to cover each of Internal Audit’s roles as follows: • Providing assurance to Management and the Audit Committee on the effectiveness of TWAM’s internal control environment. This feeds into the Annual Governance Statement process. • To make recommendations to improve their controls and achieve greater value for money. • Provide advice and guidance on day to day activity and issues.
Time is not included within the plan for the following but can be undertaken as additional work if required: • Fraud investigations • Grant certification • Consultancy In formulating the plan, the following have been taken into account: • The indicative Internal Audit Plan for 2014/15 contained within the Strategic Audit Plan 2013/14-2015/16 (attached at Appendix II) • Consultations with the Director and Head of Finance, Governance and Resources around changes to the organisation, key risks and the day to day operating environment. • Changes in the structure of TWAM with Sunderland City Council no longer being part of the Joint Committee. • Consideration of disclosures in the Annual Governance Statement • Outcomes of audits in previous years and ongoing work (attached at Appendix III).
Additionally, to provide assurances to Committee: • Internal Audit work will examine controls relating to TWAM financial and IT transactions processed through NCC financial systems. • Each audit will consider the effectiveness of controls and the efficiency of systems under review. They will make recommendations to improve value for money and control, where appropriate. This will also include identifying opportunities to generate additional income for TWAM.
In accordance with PSIAS the plan will be kept under review during the year and revised if appropriate. 3.2 Resources
The 2014/15 audit plan provides for 25 days of audit resources delivered through the service level agreement at a cost of £7,625. Internal Audit will not directly follow up on the implementation of audit recommendations. Reliance will be placed upon follow up by TWAM officers feeding into the production of the TWAM Action Plan Update presented to each Audit Committee by the Head of Finance, Governance and Resources. 3.3 Proposed Internal Audit Plan 2014/15
Following the review of relevant information the Head of Internal Audit has prepared an Internal Audit Plan for 2014/15 which is attached at Appendix I. There are some changes from the indicative plan for 2014/15 and these are summarised below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Plan 2014-15Report | 181 KB | DownloadRead as text |
Follow North East Museums Finance, Audit and Risk Committee at Newcastle and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Mar 2014 | Minutes of the Meeting held on 18 November 2013RESOLVED – That the minutes of the meeting held on 18 November 2013 were agreed as a correct record and signed by the... | Agreed | Open |
| 3 Mar 2014 | Annual Governance Statement 2013/14RESOLVED that - a) The draft roles & responsibilities, timescales and terms of reference are adopted as the basis for... | Approved | Open |
| 3 Mar 2014 | TWAM Strategic Risk Register Review and FrameworkRESOLVED that - 1) The Risk Management Framework be submitted to the Joint Committee for their approval. 2) The Treas... | Approved | Open |
| 3 Mar 2014 | TWAM Value for Money StrategyRESOLVED that - 1) The Value for Money Strategy (Appendix A) be approved. 2) The Value for Money Strategy be submitte... | Approved | Open |
| 3 Mar 2014 | TWAM Action Plan UpdateRESOLVED – That the report be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.