Newcastle City Council
Cabinet, Monday 21 March 2022 at 5.30pm

Tyne Bridge and Central Motorway Maintenance

Agreed Executive 1 paper

Cabinet agreed this item on Monday 21 March 2022. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

Cabinet agreed to: i. Note the progress to secure the funding of the proposed maintenance works to the Tyne Bridge and the Central Motorway and the progress with the procurement of the construction contracts to deliver the works. ii. Authorise the allocation of the local funding contribution to the proposed works and add the funding to the capital programme. iii. Authorise the procurement of a range of contracts for the delivery of the proposed works, and delegate authority to finalise and implement the contract documentation and any relevant Grant Funding Agreements to the Director of Place in consultation with the Cabinet Member for Development, Neighbourhoods and Transport, Director of Resources and the Assistant Director of Legal Services, subject to funding being secured.
Word for word from the decision Newcastle published for this meeting. Source: democracy.newcastle.gov.uk

Follow this further

Built from Newcastle's papers

What the report saysPro

Report to Cabinet

CABINET 21 March 2022 Tyne Bridge and Central Motorway Maintenance

Name of Cabinet Member: Councillor Ged Bell

Director presenting this report: Michelle Percy, Director of Place

Report Author: Graham Grant, Assistant Director of Transport

Confidential / Not for Publication Key Decision No

Report summary: With support from the North East Joint Transport Committee and Transport for the North, Newcastle City Council has submitted bids for essential maintenance funding of the Tyne Bridge and Central Motorway to government. This paper will update on the process to secure funding and seek the necessary approvals to appoint contractors to work with the City Council to deliver these improvements.

Summary of decision being asked: Note the update on the process for funding the proposed maintenance works to the Tyne Bridge and the Central Motorway and the progress with the procurement of the construction contracts to deliver the works. Delegated authority to enter into the various funding, contractual and legal agreements to the Director of Place and the Assistant Director of Legal Services, in consultation with the Cabinet Member for Development, Neighbourhoods and Transport. Cabinet report 21 March 2022

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Tyne Bridge and Central Motorway MaintenanceReport 445 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Newcastle

Search all
  1. Tyne Bridge and Central Motorway MaintenanceThis decision
  2. Application for a New Premises Licence: Greggs, Unit 5, Pilgrims Quarter, New Bridge Street West, Newcastle upon Tyne, NE1 8BF (Monument ward)Noted
  3. Application 2019/0666/01/OUT - Land to the West of Brunton Lane, North of Brunton Bridge and East of Sunniside, Newcastle upon Tyne - Callerton and Throckley WardAgreed
  4. Application for New Premises Licence: Tyne Bridge, North Buttress, Newcastle upon Tyne, NE1 3AFDecided
  5. Review of Premises Licence - YOLO Townhouse, 14 High Bridge Street, Newcastle upon Tyne, NE1 1EN (Westgate Ward)Decided

More from Newcastle Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Property Team Response to the Corporate Scrutiny Committee Commercial Property Development Spotlight ReviewSummary Consideration was given to a report which outlined the response to recommendations received by Cabinet in Jun... Agreed Open
21 Sep 2026 Council PlanSummary Consideration was given to the 2026-2029, which set out six priority outcomes that will drive activity to ach... Agreed Open
21 Sep 2026 Scrutiny Response to the Draft Council PlanSummary Consideration was given to a report which outlined the findings and recommendations of the Corporate Scrutiny... Agreed Open
21 Sep 2026 Council Tax SupportSummary Consideration was given to a report which set out possible options for amendments to the working age scheme a... Refused Open
21 Sep 2026 Quarter 1 Projected OutturnSummary Consideration was given to a report which set out the outturn position for Quarter One, for all council servi... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies