Newcastle City Council
Cabinet, Monday 21 March 2022 at 5.30pm

West Denton Community Site - New Facilities

Agreed Executive 1 paper

Cabinet agreed this item on Monday 21 March 2022. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Cabinet agreed to: i. Approve the design, construction, and operation of new community facilities in the Outer West. ii. Approve the financial package as follows:- a) An estimated scheme cost of £22.3m, part funded by £19.8m Levelling Up Funds b) Prudential borrowing for the remaining £2.5m funded by a combination of net operating income and a contribution of £1m from earmarked reserves iii. Authorise the Assistant Director of City Futures, in consultation with the Director of Place and Cabinet Member for Community Services and Public Engagement to:- a) approve designs to be submitted by the Design Team in stages following engagement and consultation with the community and stakeholders; b) procure a building contractor using the appropriate NEPO Framework; c) appoint specialist advisors if required to support the project development, and d) negotiate amendments to the Concession Agreement with GLL to continue to operate at the site and run the new facilities. iv. Authorise the Head of Property to negotiate and complete any Agreements needed with adjacent landowners (licences, access agreements). v. Authorise the Assistant Director Legal Services to complete the necessary documentation pursuant to the above recommendations.
Word for word from the decision Newcastle published for this meeting. Source: democracy.newcastle.gov.uk

Follow this further

Built from Newcastle's papers

What the report saysPro

Report to Cabinet

CABINET 21 March 2022

West Denton Community Site – New Facilities

Name of Cabinet Member: Councillor Irim Ali

Director presenting this report: Matt Wilton, Interim Assistant Director, City Futures

Report Author: Sean Trott, Senior Specialist Advisor, Major Projects

Confidential / Not for Publication Key Decision No

Report summary: This new state of the art development including a swimming pool and other community facilities replaces the former West Denton Swimming Pool which was closed following the outbreak of COVID-19 after 63 years of operation. The report seeks approvals for the design, construction, and operation of these new community facilities in the Outer West.

Summary of decision being asked: In October 2021 Government announced the award of £19.8m Levelling Up Funds for the replacement of the Outer West Swimming Pool facilities. The funding is to be fully expended by March 2024. To deliver the project at the required pace, this report seeks approval to delegate authority to the Interim Assistant Director, City Futures to progress the scheme in consultation with the Cabinet Member. Cabinet report 21 March 2022

1 What is the report about? 1.1 This report seeks approval for the design, construction, and operation of new community facilities in the Outer West. 1.2 When it opens in 2024, the building will offer space and modern facilities for a broad range of community users in addition to the replacement swimming pool. 1.3 The report provides an update on progress made to date and sets out the decisions to be delegated in order to achieve the funding deadline.

2 What decisions are being asked for? 2.1 Approve the design, construction, and operation of new community facilities in the Outer West. 2.2 Approve the financial package as follows:-

a) An estimated scheme cost of £22.3m, part funded by £19.8m Levelling Up Funds b) Prudential borrowing for the remaining £2.5m funded by a combination of net operating income and a contribution of £1m from earmarked reserves 2.3 Authorise the Assistant Director of City Futures, in consultation with the Director of Place and Cabinet Member for Community Services and Public Engagement to:-

a) approve designs to be submitted by the Design Team in stages following engagement and consultation with the community and stakeholders b) procure a building contractor using the appropriate NEPO Framework c) appoint specialist advisors if required to support the project development, and d) negotiate amendments to the Concession Agreement with GLL to continue to operate at the site and run the new facilities. 2.4 Authorise the Head of Property to negotiate and complete any Agreements needed with adjacent landowners (licences, access agreements). 2.5 Author the Assistant Director Legal Services to complete the necessary documentation pursuant to the above recommendations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
West Denton Community Site: New FacilitiesReport 245 KB DownloadRead as text

More from Newcastle Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Property Team Response to the Corporate Scrutiny Committee Commercial Property Development Spotlight ReviewSummary Consideration was given to a report which outlined the response to recommendations received by Cabinet in Jun... Agreed Open
21 Sep 2026 Council PlanSummary Consideration was given to the 2026-2029, which set out six priority outcomes that will drive activity to ach... Agreed Open
21 Sep 2026 Scrutiny Response to the Draft Council PlanSummary Consideration was given to a report which outlined the findings and recommendations of the Corporate Scrutiny... Agreed Open
21 Sep 2026 Council Tax SupportSummary Consideration was given to a report which set out possible options for amendments to the working age scheme a... Refused Open
21 Sep 2026 Quarter 1 Projected OutturnSummary Consideration was given to a report which set out the outturn position for Quarter One, for all council servi... Agreed Open