Decision The Mayor in consultation with the Cabinet Member for Children and Young People’s Service, the Mayoral Advisors for Performance and Inspection; Early Years and Business Partnership and Skills agreed: to approve the tender from Lakehouse Ltd. in the sum of £1,650.018 for refurbishment of Ellen Wilkinson Primary School and the construction of a new Early Learning Centre subject to the funding for the Early Learning Centre being first approved by the DfES. Reason for Decision There is a very limited supply of good quality childcare places in the Docklands Early Start area. Children's Centre capital, at Ellen Wilkinson will be developed to offer 50 childcare places and support facilities. These facilities will provide a comprehensive range of family support, health, jobs and training information service, all of which will be promoted as Early Start, as outlined in the Early Years Strategy approved by the Council on 21 June 2004. This decision is subject to the call-in process as the decision was based on a partly exempt report The call-in period ends at 5pm on 9 th March 2006
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
To obtain approval to accept the lowest tender for the refurbishment of Ellen Wilkinson Primary School and the construction of the new Early Learning Centre.
To approve the tender from Lakehouse Ltd. in the sum of £1,650.018 for refurbishment of Ellen Wilkinson Primary School and the construction of a new Early Learning Centre subject to the funding for the Early Learning Centre being first approved by the DfES Pauline Maddison Executive Director Children and Young People
Originator of report: Tazeem Aziz, Early Start Capital Programme Manager, Education Asset Management and Planning Unit. Tel no: (0208-42359) E-mail address: [email protected]
Local Government (Access to Information) Act 1985 Background papers used in preparing this report:
Cleared by Legal (officer’s initials) CB Cleared by Finance (officer’s initials) NM Cleared by Risk (officer’s initials) KM
List of enclosures: The quantity surveyor’s report Appendix A. Table containing Exempt Information - Appendix B 1 Executive Summary
1.1This is a joint capital project involving the refurbishment of the Primary School and creation of an Early Learning Centre. The Early Leaning Centre is in accordance with Newham’s Early Years Strategy approved by the Council on 21st June 2004 . 1.2 The project is to be funded through Sure Start Local Programme Capital, Children’s Centre Capital 2004-2006, and the Local Authority’s Education Capital Programme. The refurbishment of Ellen Wilkinson Primary School is to be funded from the Local Authority’s Education Capital Programme 2005/06 approved by the Mayor on 31 March 2005.
1.3Tenders were invited from 7 contractors on Newham’s Approved Tender List. Tenders were received from 5 contractors and opened on 6 February 2006. The lowest tender was from Lakehouse Ltd for the sum of £1,650.018 and is acceptable. The Council’s Corporate Contracts Unit has confirmed Lakehouse Ltd as acceptable, subject to no final qualifications.
Details of the tender returns are set out below
1 LAKEHOUSE LTD £1,650,018 2 A £1,876,323 3 B £1,916,615 4 C £2,022,85 5 D £2,095,880
1.4The new build and refurbishment programme will enable Ellen Wilkinson Primary School to offer many additional services to children and families in their immediate neighbourhood. These will include full day childcare, family support, health services and information on training and jobs. These services will be delivered by a variety of partners from the maintained, private and voluntary sectors, and will be co-ordinated by the Council as outlined in its Early Years Strategy.
1.5The tender is a competitive fixed-price based on an outline design and specification provided by the Council and which are to be further developed and built by the contractor, using the JCT Standard Form of Building Contract with Contractor’s Design. This form of contract is tried and tested and its use is recommended if certainty of price and programme are desirable, provided that variations during the construction stage are kept to minimum. A start on site is expected in April 2006 and completion is expected in February 2007.
2 Outline of Proposals
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.