Decision The Mayor agreed the proposal to tender the works contract to deliver the second phase of the development of improved facilities at Ellen Wilkinson Primary School. Reason for Decision Approval for the contract for the delivery of the first phase of the refurbishment of Ellen Wilkinson Primary School and the construction of a new Early Learning Centre was agreed at Mayoral Proceedings on 15 February 2006. Approval is now being sought for tenders for the works to deliver the second phase of the development of the facilities at the school. This decision is subject to the call-in process as the decision was based on part exempt information. The call-in period will expire at 5pm on 17 April 2008.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
This pre-tender report requests approval to begin the procurement process to deliver the second phase of a project to improve facilities at the Ellen Wilkinson Primary School. This project is the second phase of the development of the school’s facilities. The first phase was approved at a meeting of Mayoral Proceedings on 23 February 2006. The aggregate figure for the tender for Phase 1 and the construction estimate for Phase 2 as set out in the exempt Appendix result in a figure below the EU Threshold figure.
Recommendations
The Mayor is asked to agree the proposal to tender the works contract to deliver the second phase of the development of improved facilities at Ellen Wilkinson Primary School.
Reason for recommendation
Approval for the contract for the delivery of the first phase of the refurbishment of Ellen Wilkinson Primary School and the construction of a new Early Learning Centre was agreed at Mayoral Proceedings on 15 February 2006. Approval is now being sought for tenders for the works to deliver the second phase of the development of the facilities at the school.
Consultation
• Councillor Alec Kellaway, in the absence of the Lead Member for Children and Young People, Councillor Rev. Quintin Peppiatt. • Local Ward Councillors via the Influential Councillor Scheme.
NAME OF LEAD OFFICER: Angela Drizi POSITION: Head of Children and Young People
Originator of report: John Cochrane, Principal Officer Asset Management and Planning Tel no: 020 8430 4985 E-mail address: [email protected]
Local Government (Access to Information) Act 1985 Background papers used in preparing this report: • Mayoral Proceedings Report, 15 February 2006 – “Ellen Wilkinson Children's Centre Tender Acceptance Report”. • Cabinet Report, 20 March 2008 – “Schools Capital Allocations and Programmes for 2008/09”.
List of enclosures: • Appendix A (Exempt). Proposal to tender works contract to develop Phase 2 of the Ellen Wilkinson Primary School.
1. Introduction and Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.