Resolved
Decision The Board noted the current assessment and action plan.
Audit Board noted this item on Wednesday 17 January 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Board noted the current assessment and action plan.
AUDIT BOARD REPORT 17th January 2007 Date of meeting Agenda Item Subject Heading Risk Management Survey and Action Plan
Is this Item for: Information and Discussion Information or Discussion Summary of The Corporate Risk Management Team undertook a CIPFA self assessment survey to determine the extent of risk issues/key points management embeddedness in Newham. From the results of for discussion the survey, the risk team have devised an action plan of work to be completed to increase the level of compliance.
Members are asked to note the current assessment scores and action plan.
Officer preparing report Ashley Easen Contact 020 8430 4795 Number and e- [email protected] mail address Manager’s name Marianne Manager’s Title Chief Internal Auditor Wood
Internal Audit Section, Resources 1 3. Report
The role of the Corporate Risk Management Team in Newham is to facilitate the management of the Council’s significant business risks and embed risk management in all of the Council’s services. As part of this, the team measure the risk management performance of services on how well they integrate risk management into their work. However, the team were concerned about their own levels of performance regarding their ability to support services in risk management and help with the embedding process.
To this end, in October 2006, the Risk Management Team decided to undertake a self assessment exercise using a risk management survey tool designed by CIPFA. The purpose of the assessment was to establish how well the risk management team are delivering the risk management service across the Council and to highlight areas where improvement in the team’s performance is needed.
The survey asks a series of questions which require only ‘yes’ or ‘no’ answers. The difficulty with this direct questioning is that many of the team’s responses fell somewhere between yes and no - where aspects of risk were implemented in part for example. In these circumstances, the answer provided by the team was ‘not fully’ to ensure that actions could then be developed to fully embed these areas of work and provide evidence if needed. The scoring mechanism was 1 point for yes, ½ point for not fully and 0 points for no.
The overall result from the survey was that risk management is embedded in the Council to a level of 70%. There were aspects of our work and scores which were weaker than others such as projects and partnerships and the corporate risk management group. As our partnership work project is now nearing the end of wave one, it should not take long for this score to increase and it was comforting to know that the team were headed in the right direction with this project. For the Corporate Risk Management Group, the structure of meetings needs to be clarified and the items discussed on the agenda widened to incorporate more subject areas such as training for staff in risk management and reviewing the risks held on the Councils Corporate Risk Register. This has been discussed with the Chief Executive and changes will be made to the meetings format to increase compliance and good practice.
The summary of scores and areas where further work is needed under each section is shown on page 3 this report. If a member would like a detailed breakdown of the questions asked within the survey and the respective responses given by the team from either a specific section or the entire survey, please contact Ashley Easen who can provide you with this.
All outstanding tasks which need to be completed to enable the team to achieve full compliance of the survey have been used to create an action plan of work. The plan outlines the outstanding tasks and the recommended work needed to achieve them. The team have used the results of the survey and recommendations within the plan to produce their project plan for 2007-08. The action plan is attached to this report as Appendix A.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management Survey and Action PlanReport | 62 KB | DownloadRead as text |
Follow Audit Board at Newham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Feb 2019 | Minutes, Decision Sheet and Action PlanRESOLVED that: 1. The minutes of the last meeting of the Board, held on 7 November 2018, be approved as a correct rec... | Approved | Open |
| 12 Feb 2019 | Risk Management Policy and StrategyRESOLVED that the , be noted. | Noted | Open |
| 12 Feb 2019 | Annual Treasury Management Strategy StatementRESOLVED that the Annual Treasury Management Strategy Statement, be noted, subject to the reference on Page 50 being ... | Noted | Open |
| 12 Feb 2019 | Duration of MeetingRESOLVED that the meeting be extended until 9.30pm, if required, to enable the remainder of the business to be transa... | Decided | Open |
| 12 Feb 2019 | Exclusion of Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following items of busine... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.