Resolved
Decision The Committee agreed the reasons for approval and granted planning permission subject to conditions: The relevant conditions are summarised as follows: 1. Three years to implement permission, Reason – To comply with Section 91 of TCP Act 1990. 2. Approval applies only to drawings submitted, Reason – To ensure development is completed in accordance with the approved plans. 3. Restricted timeframe for temporary classrooms of 1 year, after which date, the buildings are to be removed offsite. Reason – To maintain residential amenity. 4. External materials to match existing, Reason – To maintain visual amenity. Informatives: Air pollution and noise from demolition or construction sites informative - relating to smoke and burning of materials, dust containment, and noise avoidance and reduction.