Resolved
Decision The Committee agreed to defer consideration of this application to the next meeting.
Development Control Committee agreed this item on Wednesday 13 February 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee agreed to defer consideration of this application to the next meeting.
1.1The committee is asked to grant consent subject to the following conditions.
1. The development hereby permitted shall be removed and the use hereby permitted shall be discontinued and the land/area restored to its former condition on or before 13th February 2011 in accordance with a scheme of works submitted to and approved by the Local Planning Authority
Reasons: To ensure that the development is carried out in accordance with the principles of the approved proposal and the London Borough of Newham Unitary Development Plan (adopted June 2001 and saved from the 27th of September 2007 in accordance with the direction from the Secretary of State) and The London Plan (adopted February 2004).
2. The following materials will be used in the implementation of the changes to hard landscaping as outlined in the proposal as approved: • Concrete block dished channels Marshalls keychannel 200 x 200 x 65 Charcoal to define vehicular route. • Block paving adjacent to keychannel one row each side of 200 x 100 x 80 chamfered edge Marshall Keyblock Charcoal. • Block paving to NE corner of RVS 200 x 100 x 80 chamfered edge Marshalls keyblock Burnt Ochre/bracken mix to match existing paths in herringbone pattern. • Stone slab granite paving Marshalls GRA 917 silver with fine picked top 700, 500 and 300mm widths as existing. • Stone setts 100 x 100 x 100 GRA 917 silver granite cropped all sides to match existing. • Tactile paving Marshalls blister 400 x 400 x 65 colour Natural stack bond hotel entrance. • Paving in front of Hotel Foyer Marshalls Traffica Saxon 400 x 400 x 65 colour Marigold stack bond. • Paving at disabled parking spaces Marshalls Regula 160 x 240 x 80 & 160 x 160 x 80 harvest buff and burnt ochre 50% mix to match existing (if existing quantities are insufficient.)
3. Prior to the commencement of the Hotel use operations, details of the elevational design and materials to be used in the doors and access to the proposed refuse storage, shall be submitted to and approved by the Local Planning Authority.
Reasons: To ensure a satisfactory standard of external appearance of the development and with regard to Policy EQ15 of the London Borough of Newham Unitary Development Plan (adopted June 2001 and saved from 27th September in accordance with the directive of the Secretary of State).
4. No use of the hotel shall commence until all persons interested in the site have entered into an agreement of agreements made pursuant to Section 106 of the Town and Country Planning Act 1990 securing planning obligations in respect of the items referred to in Section 8 of the officers report put before Development Control Committee on the 13/02/2008, and agreed in writing by the agent.
2. SYNOPSIS
2.1The planning application relates to the relocation of the Sunborn Yacht, a 5 no. decked boat used as a floating hotel with 102 no. rooms. At current the Yacht is moored to the east of the Excel Exhibition Centre, the proposal would allow for its relocation to the west side of the centre adjacent to the Royal Victoria Square amenity area. This relocation is required in order to accommodate the ‘Phase 2’ expansion of the Excel Centre eastwards, permission for which was granted in February 2007. 2.2 The proposal does not include any expansion of Hotel facilities, however it does require changes to the associated hard landscaping to accommodate revision to traffic routes to and from the yacht and the creation of 4 disabled parking spaces.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Sunbourn Yacht Floating Hotel, western Gateway, E16Report | 43 KB | DownloadRead as text |
Follow Development Control Committee at Newham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Mar 2010 | 370 Romford Road, Forest Gate, London E7 8BSDecision The Committee agreed the reasons for approval as outlined in the report and granted planning permission subj... | Agreed | Open |
| 3 Mar 2010 | 120 High Street, E6Decision The Committee agreed to defer consideration to a later meeting. | Agreed | Open |
| 3 Mar 2010 | Dersingham Infant School, Lawrence Avenue, Manor Park E12Decision The Committee agreed the reasons for approval as outlined in the report and granted outline planning permiss... | Agreed | Open |
| 3 Mar 2010 | Eastlea Community Comprehensive School, Exing Road E16Decision The Committee agreed the reasons for approval as outlined in the report and granted full planning permission... | Agreed | Open |
| 3 Mar 2010 | 44 The Broadway, E15Decision The Committee agreed the reasons for approval as outlined in the report and granted planning permission subj... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.