Cabinet, Thursday 20 March 2008

Newham Development Vehicle - Submission of Outline Business Case

Agreed Executive 1 paper

Cabinet agreed this item on Thursday 20 March 2008. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Decision The Mayor in consultation with Cabinet agreed to receive a further report in May which will recommend whether or not to proceed with the establishment of a Newham Development Vehicle and if so recommended to procure a partner for the Vehicle. Reasons for the Recommendations Following the establishment of the Newham Development Vehicle project board and initial discussions with the Mayor, Members of Land Panel and the Executive Member for Housing, officers are requesting that the Mayor agrees that a further report should be received by Cabinet in May containing all relevant information and implications to enable the Mayor in consultation with Cabinet to decide whether or not to proceed with the establishment of a Newham Development Vehicle and if so to procure a partner through a tendering process throughout the EU. This decision is subject to the call-in process as the decision was based on exempt information. The call-in period will expire at 5pm on 11 April 2008.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report provides a summary of the detailed Newham Development Vehicle “Outline Business Case” considered by the Project Board and Newham Executive Board and asks that the Mayor in consultation with Cabinet agrees to accept a further report in May which will recommend to Cabinet whether or not to proceed with the establishment of the Newham development Vehicle and if so to ask that a partner be procured through tendering process throughout the EU.

Recommendations

The Mayor in consultation with Cabinet is asked to agree to receive a further report in May which will recommend whether or not to proceed with the establishment of a Newham Development Vehicle and if so recommended to procure a partner for the vehicle by tendering throughout the EU. Reasons for the Recommendations

Following the establishment of the Newham Development Vehicle project board and initial discussions with the Mayor, Members of Land Panel and the Executive Member for Housing, officers are requesting that the Mayor agrees that a further report should be received by Cabinet in May containing all relevant information and implications to enable the Mayor in consultation with Cabinet to decide whether or not to proceed with the establishment of a Newham Development Vehicle and if so to procure a partner through a tendering process throughout the EU.

Consultation

• The Mayor, Sir Robin Wales • Executive Member for Housing, Process and Business Efficiency, Councillor Andrew Baikie

NAME OF LEAD OFFICER: Jackie Belton POSITION: Head of Housing and Public Protection

Originator of report: Roberto Bruni Tel no: 0208 430 6262 E-mail address: [email protected]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report: None

List of enclosures / Appendices: • Outline Business Case (Exempt) • Draft Risk Matrix (Exempt) Report

1. Introduction and Background

1.1This report sets out the key issues that have been considered by the Project Board over the past two years. King Sturge Financial Services Ltd (KSFS) was appointed in September 2006 following a competitive tendering process. The basis of the appointment was to explore the establishment of a Development Vehicle based on the principles that the company’s focus would be on communities, achieving control and financial benefits for Newham while managing risk appropriately.

1.2The purpose of the company would be to secure sustainable developments across Newham and to deliver longer term financial returns for the benefit of borough. The Company would be run for a profit. Gateway Resources Board approved the funding of £220K in January 2007 for this appointment and other related work, which will be recovered from the partnership at the outset should it proceed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Newham Development Vehicle: Submission of Outline Business CaseReport 49 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 22 attended
SR
Sir Robin WalesChair, present
CB
Christine BowdenMember, present
UD
Councillor Unmesh Desai AMMember, present
LH
Councillor Lester HudsonMember, apologies
JL
Councillor Joy Laguda MBEMember, present
QP
Councillor Quintin PeppiattMember, present
AB
Councillor Andrew BaikieMayoral Adviser, present
PB
Councillor Paul BrickellMayoral Adviser, present
IC
Councillor Ian CorbettMayoral Adviser, present
RC
Councillor Richard CrawfordMayoral Adviser, present
JC
Councillor Jo CorbettMayoral Adviser, present
DG
Councillor David GriffinMayoral Adviser, absent

All 22 on the meeting page

On this subject at Newham

Search all
  1. Newham Development Vehicle - Submission of Outline Business CaseThis decision
  2. Pre-Procurement - Newham Tennis in Parks Management & Tennis Development ProgrammeAgreed
  3. Transfer of Town Planning Powers from the London Legacy Development Corporation to the London Borough of NewhamAgreed
  4. Ground Rents and Fairness for leaseholders in private developments built on Newham Council owned landAgreed
  5. Update on the Development of a Health & Wellbeing Strategy for Newham January 2020Agreed
  6. Newham's Local Plan: Gypsy and Traveller Accommodation Development Plan Document - AdoptionAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies