Vacant Land Adjacent St Margaret's Convent, Chargeable Lane, Plaistow, E13

Agreed Planning 1 paper

Development Control Committee agreed this item on Wednesday 14 January 2009. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Decision The Committee agreed: (i) the reasons for approval as outlined in this report and granted planning permission, subject to conditions and the completion of a legal agreement under s106 of the Town and Country Planning Act 1990; and (ii) that the application should be reconsidered and represented at Committee should agreement on the legal agreement under s106 of the Town and Country Planning Act 1990 not be reached. Conditions: 1. The development to which this permission relates must be commenced not later than the expiration of THREE YEARS from the date of this permission. Reasons: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990. 2. All works are to be completed in accordance with the following drawing numbers: 206039/001; 206039/010; 206039/020; 206039/021; 206039/022; 206039/023; 206039/110/RevA; 206039/120/RevA; 206039/121/RevA; 206039/122/RevA; 206039/123/RevA; 206039/130/RevA; 206039/131/RevA; 206039/132; 206039/133/RevA and 206039/134/RevA. No further drawings apply, unless otherwise approved in writing by the Local Planning Authority. Reasons: To ensure that the development is undertaken in accordance with the approved drawings and to protect the local amenity with regard to Policy EQ19 of the London Borough of Newham Unitary Development Plan (adopted June 2001, saved from the 27th of September 2007 in accordance with the direction from the Secretary of State), and Policy 4B.1 of the adopted London Plan consolidated with alteration since 2004 (February 2008). The development is acceptable on the basis of the particulars contained within the application and this condition seeks to ensure the development is undertaken in strict accordance with those details as approved. 3. a) Prior to the commencement of works, full details, samples and specifications of the materials to be used on the external surfaces of all buildings and enclosures (fences/walls/gates) shall be submitted to and approved in writing by the Local Planning Authority. b) The approved materials shall be constructed and permanently maintained thereafter to the satisfaction of the Local ... view the full minutes text for item 7.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Development Control Committee

Recommendations

The Committee is asked to:

a) agree the reasons for approval as outlined in this report; and

b) agree that they are minded to GRANT planning permission, subject to conditions and the completion of a legal agreement under s106 of the Town and Country Planning Act 1990; and

c) agree that the application should be reconsidered and represented at Committee should agreement on the legal agreement under s106 of the Town and Country Planning Act 1990 not be reached. Conditions:

1. The development to which this permission relates must be commenced not later than the expiration of THREE YEARS from the date of this permission.

Reasons: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990.

2. All works are to be completed in accordance with the following drawing numbers: 206039/001; 206039/010; 206039/020; 206039/021; 206039/022; 206039/023; 206039/110/RevA; 206039/120/RevA; 206039/121/RevA; 206039/122/RevA; 206039/123/RevA; 206039/130/RevA; 206039/131/RevA; 206039/132; 206039/133/RevA and 206039/134/RevA. No further drawings apply, unless otherwise approved in writing by the Local Planning Authority.

Reasons: To ensure that the development is undertaken in accordance with the approved drawings and to protect the local amenity with regard to Policy EQ19 of the London Borough of Newham Unitary Development Plan (adopted June 2001, saved from the 27th of September 2007 in accordance with the direction from the Secretary of State), and Policy 4B.1 of the adopted London Plan consolidated with alteration since 2004 (February 2008). The development is acceptable on the basis of the particulars contained within the application and this condition seeks to ensure the development is undertaken in strict accordance with those details as approved.

3. a) Prior to the commencement of works, full details, samples and specifications of the materials to be used on the external surfaces of all buildings and enclosures (fences/walls/gates) shall be submitted to and approved in writing by the Local Planning Authority.

b) The approved materials shall be constructed and permanently maintained thereafter to the satisfaction of the Local Planning Authority.

Reasons: To ensure a satisfactory standard of external appearance and to protect local amenity and with regard to Policy EQ19 of the London Borough of Newham Unitary Development Plan (adopted June 2001, saved from the 27th of September 2007 in accordance with the direction from the Secretary of State and Policy 4B.1 of the London Plan consolidated with alterations since 2004 (February 2008).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Vacant Land Adjacent St Margaret's Convent, Chargeable Lane, Plaistow, E13Report 2.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 11 attended
RM
Councillor Ron ManleyChair, present
PM
Councillor Patrick MurphyDeputy Chair, present
MC
Councillor Marie CollierMember, present
PH
Councillor Patricia HollandMember, present
MJ
Councillor Maureen JonesMember, present
KK
Councillor Khalil Kazi OBEMember, present
RA
Councillor Riaz Ahmed MirzaMember, present
LS
Councillor Lakmini ShahMember, present
AK
Councillor Abdul Karim Sheikh BEMMember, present
AS
Councillor Amarjit SinghMember, present
MS
Councillor Mary SkyersMember, present

On this subject at Newham

Search all
  1. Vacant Land Adjacent St Margaret's Convent, Chargeable Lane, Plaistow, E13This decision
  2. Vacant Land At 26 To 34, Tidal Basin Road, Silvertown, London, E16 1ADAgreed

More from Newham Development Control Committee

All decisions
MeetingDecisionOutcome
3 Mar 2010 370 Romford Road, Forest Gate, London E7 8BSDecision The Committee agreed the reasons for approval as outlined in the report and granted planning permission subj... Agreed Open
3 Mar 2010 120 High Street, E6Decision The Committee agreed to defer consideration to a later meeting. Agreed Open
3 Mar 2010 Dersingham Infant School, Lawrence Avenue, Manor Park E12Decision The Committee agreed the reasons for approval as outlined in the report and granted outline planning permiss... Agreed Open
3 Mar 2010 Eastlea Community Comprehensive School, Exing Road E16Decision The Committee agreed the reasons for approval as outlined in the report and granted full planning permission... Agreed Open
3 Mar 2010 44 The Broadway, E15Decision The Committee agreed the reasons for approval as outlined in the report and granted planning permission subj... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies