Resolved

Decision The Mayor agreed that officers seek tenders to construct the build of a Children Centre at Altmore Infant school. Reason for Decision To provide a Children Centre at Altmore Infant school. The scheme of Delegation and the Council’s Contract Standing Orders requires that Mayoral approval is given to the commencement of a tendering exercise for the delivery of a works programme which is above £500,000. This decision is subject to the call-in process as the decision was based on part exempt information. The call-in period will expire at 5pm on 29 March 2010.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Purpose of report

This pre-tender report requests approval to begin the procurement process to provide a Children Centre at Altmore Infant school.

Recommendations

The Mayor is asked to grant approval for officers to seek tenders to construct the build of a Children Centre at Altmore Infant school. Reason for Recommendation

The scheme of Delegation and the Council’s Contract Standing Orders requires that mayoral approval is given to the commencement of a tendering exercise for the delivery of a works programme which is above £500,000

Consultation

Councillor Rev. Quintin Peppiatt, as Lead Member for Children and Young People’s Services has been consulted.

Ward members Councillor Omana Gangadharan, Councillor Lester Hudson and Councillor Ted Sparrowhawk were consulted through the influential councillor scheme on: 22nd January 2010.

NAME OF LEAD OFFICER: Kim Bromley-Derry POSITION: Executive Director Children and Young People’s Services

Originator of report: Treena Lyons Tel no: 39567 E-mail address: [email protected]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report: None

List of enclosures:

Exempt Appendix 1 Proposed EU procurement

Early submission of broad outline information to the Mayor: Altmore Children Centre

1. Introduction and Background

1.1Altmore Infant school was selected to become a Phase 3 Children Centre. The new build will be a new stand alone building on the school site. This provision will enhance the existing delivery of services for the children and families of the local community. This will include the provision of Daycare, family support services, health services and training and employment development in accordance with the Children Centre core offer requirements.

2. Key Considerations

It was decided after careful consideration that a Children’s Centre at Altmore Infant school would be beneficial to deliver a range of services for the local community. This would include the Children’s Centres core offer of family support, training and employment and health services. The Children’s Centres will be resourced by Children Centre revenue and income by private providers.

2.1Reasons for outsourcing

2.1.1 We do not have a suitable internal contractor to deliver this programme of works.

2.2Potential use of proposed contract over life of contract

2.2.1 If awarded the construction contract will be solely for the delivery of this project.

2.3Estimated value of the proposed procurement over the life of the proposed contract

2.3.1 Details of the projected construction costs are set out in the budget plan (Exempt information –Included in Appendix A)

2.4Duration of proposed contract

2.4.1 It is anticipated that the contract period will be in the region of 33 weeks

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Altmore Children's CentreReport 83 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 19 attended
SR
Sir Robin WalesChair, present
JL
Councillor Joy Laguda MBEMember, present
AB
Councillor Andrew BaikieMember, present
CB
Christine BowdenMember, present
PB
Councillor Paul BrickellMember, present
IC
Councillor Ian CorbettMember, present
JC
Councillor Jo CorbettMember, present
RC
Councillor Richard CrawfordMember, present
UD
Councillor Unmesh Desai AMMember, present
CF
Councillor Clive Furness BEMMember, present
LH
Councillor Lester HudsonMember, present
AK
Councillor Alec KellawayMember, present

All 19 on the meeting page

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies