Decision The Mayor agreed:- 1. to note the position of the progress of works as set out in the report; 2. to note the circumstances in paragraphs 1.6 and 1.8 in terms of matters affecting the delivery of the project; 3. that approval of an increase in the value of the Stratford Town Centre Public Realm Contract from £6,008,301 to £7,271,000 is to be agreed in consultation with the Executive Member for Regeneration and Strategic Planning; and 4. in future, any delay to the start of large capital programmes will be brought to the attention of Members immediately. Reasons for the Decision To facilitate completion of the Stratford Town Centre Scheme and to comply with Contract Standing Orders. The report and decision have complied with Part 4.5, paragraph 16 of the Constitution. The decision is not subject to the Call-In process and may be implemented immediately.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
1.1.1 An Equalities Impact Assessment (EQIA) was undertaken for this project to ensure that it improves the town centre for all parts of the community, including disabled and older people. Advice from an access advisor was also incorporated into the design.
1.2Protecting Children
1.2.1 Not applicable
1.3Human Rights
1.3.1 Not applicable
1.4Climate Change implications and the effect on the Carbon footprint
1.4.1 The materials specified for the public realm works are durable, require little maintenance and have low embodied energy.
1.5Crime and Disorder
6.5.1 Improving public safety is one of the objectives of the project. The Stage D design was discussed with the Metropolitan Police and their comments were taken on board. The design will increase use and therefore natural surveillance of key spaces and reduce opportunities for crime in crowded areas. The lighting is being improved to provide adequate lighting levels and white light as recommended by the Police.
6.5.2 The design work was part funded by Home Office ‘Crowded Places’ grant as part of the Protect counter terrorism strategy. Hostile vehicle mitigation measures have been installed to improve security around Stratford Station.
1.6Economic Impact
1.6.1 A key objective of this project is to improve perceptions of Stratford town centre amongst residents, shoppers, visitors, businesses and investors. Improved perceptions will increase investment confidence and footfall, both of which support the viability of local businesses.
1.6.1 As part of its tender, Bardon Construction submitted a Community Benefits Plan, which included commitments to provide local job opportunities, create local training opportunities, recruit apprentices and sub-contract locally. 5. Consultation
5.1The Mayor was consulted at a meeting in December 2011.
5.2The Executive Member for Infrastructure & Environment and the Executive Member for Planning & Regeneration were consulted by circulation of the draft report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.