Gallions Primary School Procurement of Capital Project to Expand the Size of the School

Approved Committee 2 papers

Mayoral Proceedings approved this item on Thursday 23 February 2012. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision The Mayor granted approval for officers to commence a procurement exercise to construct the additional accommodation to expand Gallions Primary School. Reason for the decision The scheme of Delegation and the Council’s Contract Standing Orders requires that Mayoral Approval is given for the commencement of a tendering exercise for the delivery of a works programme which is above £500,000 . This decision is subject to the call-in process as the decision was based on part exempt information. The call-in period will expire at 5pm on Monday 5 March 2012.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Purpose of report

This pre-tender report requests approval to begin the procurement process to provide new accommodation to enable the expansion of the size of Gallions Primary School.

Reason for Urgency N/A.

Recommendations

The Mayor is asked to grant approval for officers to commence a procurement exercise to construct the additional accommodation to expand Gallions Primary School.

Reason for Recommendation The scheme of Delegation and the Council’s Contract Standing Orders requires that mayoral approval is given to the commencement of a tendering exercise for the delivery of a works programme which is above £500,000 NAME OF LEAD OFFICER: Chris Pope. POSITION: Director of Resources and Commercial Development

Originator of report: John P Cochrane. Tel no: 0203 3737820. E-mail address: [email protected]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report: N/A. List of enclosures: • Cost estimate. (Exempt information –Included in Appendix A) Report – Part A

Proposed EU procurement Early submission of broad outline information to the Mayor: Gallions Primary School. Procurement of Capital Project to expand the size of the school.

1. Introduction and Background

1.1As part of the Department for Education’s Schools Capital Allocation and Programmes 2011/12, Cabinet approved funding on 26 May 2011 to undertake initial design work at a number of potential projects including Gallions. It is proposed that the school be increased from 2 Form of Entry (420 pupils) to 3 Form of Entry (630 pupils)

1.2This report sets out the need to start the procurement process in order to commence construction work during the summer holiday 2012 period.

2. Key Considerations

2.1The enlargement of Gallions Primary School forms part of the strategy to provide additional primary numbers. This is due to the increasing numbers of pupils requiring primary school places.

2.2Pupil number projections show that there is now sufficient demand from families in the Beckon area to attend their local primary school to warrant the expansion of Gallions Primary School.

2.3The school is popular and the enlargement would support making the school of choice with local families. The last Ofsted inspection in October 2011, graded the school as 'Good'.

2.4Gallions Primary was designed as a 3 Form Entry School, (for 630 pupils), but constructed as a 2 Form entry School (420 pupils) in 1999. At that time there was not sufficient pupils to justify the capital costs to construct the school as 3 FE. However, it was always expected that there would be a future demand for places in the Beckton area which would require the school to be expanded to 3FE.

2.5The original building comprised 14 classrooms, practical, quiet rooms, hall and nursery teaching accommodation, as well as office and other non teaching accommodation.

2.6It is proposed to construct a new extension to the existing school to comprise of seven class bases, toilets and circulation areas, together with alterations to the existing school hall, toilets and services and external works including extending the car park and provision of additional storage.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gallions Primary School Procurement of Capital Project to Expand the Size of the SchoolReport 84 KB DownloadRead as text
PDF
Report Part BReport 63 KB Download

At this meeting

Whole meeting

Who was there

15 of 21 attended
SR
Sir Robin WalesChair, present
TS
Councillor Ted SparrowhawkMember, non-voting, in attendance
AB
Councillor Andrew BaikieMember, non-voting, present
SB
Councillor Stephen BrayshawMember, non-voting, in attendance
PB
Councillor Paul BrickellMember, non-voting, present
AC
Councillor Akbar ChaudharyMember, non-voting, in attendance
IC
Councillor Ian CorbettMember, non-voting, present
JC
Councillor Jo CorbettMember, non-voting, in attendance
RC
Councillor Richard CrawfordMember, non-voting, present
UD
Councillor Unmesh Desai AMMember, non-voting, present
CF
Councillor Clive Furness BEMMember, non-voting, present
LH
Councillor Lester HudsonMember, non-voting, present

All 21 on the meeting page

On this subject at Newham

Search all
  1. Gallions Primary School Procurement of Capital Project to Expand the Size of the SchoolThis decision
  2. Gallions Primary School. Proposal to Develop a Resourced Provision for up to 14 Children with Autism: Issuing of the Public NoticeAgreed
  3. Call-in: Gallions Primary SchoolAgreed

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies