Decision The Mayor agreed: 1. to note the options available in respect of the works carried out through the existing Partnering contract for Engineering Services; 2. to approve a one year extension to this contract until 30 October 2014 for the reasons set out in this report; and 3. that the Mayor and the Executive Member for Infrastructure and Environment must be consulted by officers as part of the strategic review and options appraisal set out in paragraph 1.3 of the report. Reasons for the Decision To update the Mayor regarding options for the delivery of work currently carried out using the Partnering Contract and to recommend a one year extension in the light of considerations discussed in the body of the report The report and decision have complied with Part 4.5, paragraph 16 of the Constitution. The decision is not subject to the Call-In process and may be implemented immediately.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
This report discusses the proposed extension of the current Partnering Contract for Engineering Services having regard for alternative options and longer term procurement strategies.
Recommendations
The Mayor is asked to
1. note the options available in respect of the works carried out through the existing Partnering contract for Engineering Services; and
2. approve a one year extension to this contract until 30 October 2014 for the reasons set out in this report
Reasons for the recommendations
To update the Mayor regarding options for the delivery of work currently carried out using the Partnering Contract and to recommend a one year extension in the light of considerations discussed in the body of the report
NAME OF LEAD OFFICER: Steve Moore POSITION: Divisional Director Environmental Services
Originator of report: Tony.Smedley Tel no: 020 3373 8284 E-mail address: [email protected] Local Government (Access to Information) Act 1985 Background papers used in preparing this report:
• Report to Mayoral Proceedings 22 February 2007 (Proposed Partnering Contract for Engineering Services in Public Realm) • Report to Mayoral Proceedings 13 December 2007 (Proposed Partnering Contract for Engineering Services in Public Realm) • Report to Mayoral Proceedings 5 September 2008 (Partnering Contract for Engineering Services in Public Realm – Acceptance of Tender)
Background papers can be obtained by contacting:
Tony.Smedley – Interim Support Manager Tel no: 020 3373 8284 E-mail address: [email protected]
List of enclosures / Appendices:
None Report - Part A
1. Introduction and Background
1.1This contract which commenced in October, 2008 was awarded to Ringway- Jacobs and comprises of the following range of works and services:
• Programmed highway maintenance works • Capital highway works arising from the 2012 Olympics and development • Traffic management schemes • Specialist design services • Provision of technical staff to address workload variations • Responsive highway maintenance • Construction services • Signs and lighting maintenance • Bridge maintenance
The contract was for an initial period of 5 years with a provision to extend by one further year. The contract now covers the Council’s signs and lighting term maintenance service following the expiry of the previous contract for this work in October, 2010.
In line with government recommendations on collaborative working and smarter partnering to achieve efficiency savings through economies of scale, the contract can be used by other London authorities and currently Hackney, Tower Hamlets and Waltham Forest have been given access to this contract through a Partnership Agreement.
The services commissioned via this contract have primarily been those relating to specialist design, technical support and the signs and lighting works particularly for major projects and programmes including Highways Renewal, Canning Town, Stratford Town Centre and the 2012 Games.
Besides the specialist services discussed above, there is a continuing demand for the other services resulting from Legacy and other developments and the LIP programme.
While alternative options are discussed in section 1.2 below, to avoid the need to procure a short-term contract for specialist services and to offer the opportunity to conduct a strategic review with a common expiry date on or around October 2014, it is recommended that the option of extending this contract by one year be approved.
1.2Options for delivery of the works and services currently provided through this contract
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.