London Borough of Newham
Mayoral Proceedings, Thursday 21 March 2013

LB Newham Affordable Homes New Build Project Pre-Procurement Report

Agreed Committee 2 papers

Mayoral Proceedings agreed this item on Thursday 21 March 2013. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

The Mayor agreed to: 1. note that a grant has been secured from the Homes and Communities Agency (HCA), which is administered through the Greater London Authority (GLA), of up to £9m for the construction of affordable homes in the borough; 2. delegate to the Executive Director – Operations in consultation with the Head of Procurement to determine the best procurement approach, either through an OJEU compliant framework or a number of packages tendered in accordance with EU procurement rules and treaty principles and the Council’s Contract Standing Orders (CSO) through Construction Line; and 3. grant approval for officers to commence the procurement of a building constructor and, or, multiple building constructors to deliver the construction phase of the Council’s affordable homes building programme. Reason for Decision To appoint a building contractor or multiple building contractors to deliver the construction phase of the Council’s Affordable Homes new build programme. The Scheme of Delegation and the Council’s Standing Orders requires that Mayoral approval is given prior to the commencement of a tendering exercise for the delivery of works programmes that exceed £500,000. The report and decision have complied with Part 4.5, paragraph 16 of the Constitution. The decision is not subject to the Call-In process and may be implemented immediately.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Purpose of report

The Mayor is asked to consider this report requesting approval to begin the procurement process to appoint a building constructor or multiple constructors to carry out the construction phase of the Council’s new build housing project where it is intended 104 dwellings are built as part of the affordable homes programme.

The appointment of the constructor(s) will be through an Official Journal of the European Union (OJEU) compliant Framework or a competitive tender process from a selection of suitable companies through Construction Line.

1 of 6 Recommendations:

The Mayor is asked to agree to

1. Note that a grant has been secured from the Homes and Communities Agency (HCA), which is administered through the Greater London Authority (GLA), of up to £9M for the construction of affordable homes in the borough 2. Agree to delegate to the Executive Director – Operations in consultation with the Head of Procurement to determine the best procurement approach, either through an OJEU compliant framework or a number of packages tendered in accordance with EU procurement rules and treaty principles and the Council’s Contract Standing Orders (CSO) through Construction Line. 3. The Mayor is asked to agree to grant approval for officers to commence the procurement of a building constructor and, or, multiple building constructors to deliver the construction phase of the Council’s affordable homes building programme.

Reason for recommendation

To appoint a building contractor or multiple building contractors to deliver the construction phase of the Council’s Affordable Homes new build programme. The Scheme of Delegation and the Council’s Standing Orders requires that Mayoral approval is given prior to the commencement of a tendering exercise for the delivery of works programmes that exceed £500,000.

NAME OF LEAD OFFICER: Jackie Belton POSITION: Executive Director Operations

Originator of report: Roberto Bruni / John McCollin Tel no: 020 3373 0475 / 020 3373 0378 E-mail address: [email protected] [email protected]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report:

Cabinet Report 23 February 2012 – Budget Framework 2012/13

Background papers can be obtained by contacting:

Roberto Bruni / John McCollin Tel no: 020 3373 0475 / 020 3373 0378 E-mail address: [email protected] [email protected]

List of enclosures: None

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LB Newham Affordable Homes New Build Project Pre-Procurement ReportReport 94 KB DownloadRead as text
PDF
Report Part BReport 40 KB Download

At this meeting

Whole meeting

Who was there

14 of 17 attended
SR
Sir Robin WalesChair, present
AB
Councillor Andrew BaikieMember, non-voting, apologies
TS
Councillor Ted SparrowhawkMember, non-voting, present
AS
Councillor Amarjit SinghMember, non-voting, apologies
NW
Councillor Neil WilsonMember, non-voting, apologies
PB
Councillor Paul BrickellMember, non-voting, present
IC
Councillor Ian CorbettMember, non-voting, present
RC
Councillor Richard CrawfordMember, non-voting, present
UD
Councillor Unmesh Desai AMMember, non-voting, present
CF
Councillor Clive Furness BEMMember, non-voting, present
LH
Councillor Lester HudsonMember, non-voting, present
AK
Councillor Alec KellawayMember, non-voting, present

All 17 on the meeting page

On this subject at Newham

Search all
  1. LB Newham Affordable Homes New Build Project Pre-Procurement ReportThis decision
  2. Increasing Affordable Temporary Accommodation Supply and Tackling Homelessness in NewhamAgreed
  3. Affordable Homes for Newham, contract variationsAgreed
  4. 2021-2026 GLA Funding Contract and Future Affordable Homes for Newham ProgrammeAgreed
  5. Affordable Homes for Newham, Plashet Road Award of Main Works Contracts for 65 New DwellingsAgreed
  6. Affordable Homes for Newham Greater London Authority (GLA) Bid 2021-26Agreed

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies