Decision The Mayor agreed to: 1. Interim proposal: a tender exercise is undertaken for the provision of home adaptations for disabled people (such as wet rooms) with suitable contractors who are registered and approved on Constructionline. This is expected to start in Q4 2013/14 and run as an interim arrangement for approximately 6-8 months whilst the full tender EU process is undertaken to participate in a pan-London framework for home adaptations for disabled people; and to delegate authority to the Executive Director of Strategic Commissioning and Community to award the interim framework to the most ecconomically advantagous contractors following legal and financal approval. 2. Longer term proposal: To join a pan-London framework for the provision of home adaptations for disabled people with the London Borough of Haringey who are leading the procurement process. Based on a scheduled tender programme it is anticipated that this framework will be available from Q3 2014/15 and is likely to run for a period of 4 years. Reason for the Decision The council does not currently have a disabled adaptations contract in place; this puts us at risk in terms of EU compliance, slows down the adaptations process by having to obtain three quotes and does not demonstrate value for money. Strategic Procurement Unit has advised that there are no East London Solutions (ELS) or contracting opportunities with neighbouring boroughs for home adaptations. The report and decision have complied with Part 4.5, paragraph 16 of the Constitution. The decision is not subject to the Call-In process and may be implemented immediately.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
Subject: Procurement for Home Adaptations via Disabled Facilities Grants (DFGs)
Source: Strategic Commissioning and Community
Wards affected: All
Outline of Proposed Procurement
The purpose of the report is to seek authority to commence a procurement exercise to: • Undertake a tender exercise for the provision of home adaptations (such as wet rooms) for disabled people with suitable contractors who are registered and approved with Constructionline. This is expected to start in Q4 2013/14 and run as an interim arrangement for approximately 6-8 months whilst the full tender EU process is undertaken to participate in a pan-London framework for home adaptations for disabled people.
• Long term: Join a pan-London framework for the provision of home adaptations for disabled people with the London Borough of Haringey who are leading the procurement process. Based on a scheduled tender programme it is anticipated that this framework will be available from Q3 2014/15 and is likely to run for a period of 4 years
The adaptation service transferred to Adult Social Care in April 2013. The department inherited all existing processes and there is no current framework in place. Historically three quotes have been obtained for each adaptation from an approved list of providers. Requesting and reviewing quotes requires significant resource, delays delivery and does not demonstrate best value. Whilst national evidence shows that the process of providing home adaptations for disabled people can be complex Newham, is continuing to reduce the time taken to deliver home adaptations which historically has taken many months and in sometimes even years. Improved pathways will reduce the time taken to deliver adaptations will further increase the throughput and reduce any remaining backlog. The aim is to make the process shorter and more efficient.
Pre-Procurement Report Template: Ver: 003 Last revised 27112013 Successful contractors on the future frameworks will be managed and tracked by the Home Adaptations for Independent Living (HAIL) team in Adult Social Care and issued with adaptations work on a rotational basis. Prior to implementation of the framework Adult Social Care will establish bench mark unit costs for each element of an adaptation.
Executive Summary of Outcomes
Financial improvement There are no cashable savings for the remainder of 2013/14 and for 2014/15. We anticipate that the average cost of adaptations will decrease in both the interim and longer term procurement solutions. This will enable further adaptations to be processed with the annual DFG allocation and additional one-off capital funding allocated in September 2013.
Cost avoidance: providing home adaptations can be categorised in terms of reduction and prevention required for Adult Social Care. In some cases the existing care support can be reduced, or the required number of carers (per visit) reduced which may in turn improve dignity and well-being for individuals. Also the adaptation can support carers by avoiding injuries that may be sustained by assisting and moving individuals.
Less time will be spent by the surveyors creating individual specifications and reviewing tenders which will allow them to concentrate on delivery of the complex adaptations. Overall administration will be reduced. The impact of the framework will be reviewed in quarter two 2014/15.
Customer benefit Home adaptations enable individuals and family members who may be carers, to live more safely, confidently and independently in their home – key outcomes in the Resilience performance framework. It is recognised that housing is critical to supporting the outcomes of independent living, dignity, improved health and well- being, and increased choice and control which underpin the Adult Social Care Outcomes framework (NASCOF).
Procurement: Governance and Regulatory
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.