Item5

Resolved

Decision The Deputy Mayor agreed to a pprove the acceptance of the tender submitted by Frencon Construction in the sum of £2,349,089 for construction works at Rosetta Primary School and Edith Kerrison Nursery School. Reasons for the Recommendations The scheme of Delegation and the Council’s Contract Standing Orders requires that Mayoral approval is given for the award of a contract which is above £500,000.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Purpose of report

This report requests approval to accept the tender submitted by Frencon Construction in the sum of £2,349,089 for construction works at Rosetta Primary School and Edith Kerrison Nursery School. This is in accordance with the decision secured at Mayoral Proceedings on Thursday 11 December 2014 to begin the procurement process at Edith Kerrison, Rosetta and Kay Rowe Schools.

Executive Summary of Outcomes

 Improved access and facilities for both Rosetta Primary School and Edith Kerrison Nursery School.  Improved kitchen and dining facilities at Rosetta Primary School to help deliver the Department for Education (DfE) universal infant free school meals (UIFSM), enhance the pupils dining experience to align with the Mayor’s commitment to providing free school meals and help to support educational attainment, activity and achievement of children attending the school.  Potential to expand Rosetta Primary School at a future time if required.  The new accommodation at Edith Kerrison will be used by training Providers from the other schools, private, voluntary, independent sector and Childminders to deliver the Early Years Free Entitlement [EYFE] for two year olds.  The new facilities construction works will increase capacity enable the school to provide an additional 24 two year old pupil places.  The construction works will support the Council resilience agenda particularly the themes Young People get the Best start in Life and Residents Achieve their Potential.

Recommendations

The Mayor is asked to approve the award of acceptance of the tender submitted by Frencon Construction in the sum of £2,349,089 for construction works at Rosetta Primary School and Edith Kerrison Nursery School.

Reasons for the recommendations

The scheme of Delegation and the Council’s Contract Standing Orders requires that Mayoral approval is given for the award of a contract which is above £500,000.

Name of lead Officer: James Thomas POSITION: Director of Commissioning, Children’s Services

Name of Lead Member consulted: Councillor Quintin Peppiatt Position: Lead Member Children and Young People (including Children's Safeguarding)

Originator of report: John Cochrane. Tel no: 020 3373 7820. E-mail address: [email removed]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report: N/A.

List of enclosures:

 Appendix A. Scope of the construction project -  Appendix B. Equality Impact Assessment – Rosetta Primary School.  Appendix C Equality Impact Assessment – Edith Kerrison Nursery School. Primary School Report - Part A

1. Introduction and Background

1.1This report requests approval to the award of a contract to Frencon Construction for the main construction stage of a two stage tender at Edith Kerrison Nursery School and Rosetta Primary School which shares the same campus

1.2The costs of the project will be funded via the schools capital programme (approved by Cabinet on 18 February 2016).

1.3On 11 December 2014, the Mayor agreed to commence procurement of construction projects at Edith Kerrison, Rosetta and Kay Rowe School via Construction Line. This report updated on the procurement process to date.

1.4The Mayor authorised officers to enter into a preconstruction agreement and on 20 May 2015 the Director of Commissioning (Children’s Services) in consultation with the Director Legal and Governance, approved entering into a preconstruction (first stage) agreement with Frencon Construction on Wednesday 20th May 2015, in the sum of £130,374

2 Key Considerations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of Construction contracts at Edith Kerrison, and Rosetta SchoolsReport 94 KB DownloadRead as text
PDF
Edith Kerrison and Rosetta award of contract: Appendix AAppendix 70 KB Download
PDF
Edith Kerrison and Rosetta award of contract: Part BReport 55 KB Download
PDF
EqIA Edith Kerrison version 2Report 186 KB Download
PDF
EqIA Rosetta primary version 2Report 185 KB Download

At this meeting

Whole meeting

Who was there

1 of 5 attended
DF
Daniel FenwickOfficer, expected
JM
James MartinSecretary, expected
SR
Sir Robin WalesChair, apologies
LH
Councillor Lester HudsonChair, present
GA
Gemma AllenOfficer, expected

On this subject at Newham

Search all
  1. Award of Construction contracts at Edith Kerrison, and Rosetta SchoolsThis decision
  2. Will Thorne Pavilion and Queen's Market Creative Wellbeing Space Main Works Construction Contract Procurement and Award StrategyAgreed
  3. Award of Construction contracts at St. Bonaventure's SchoolAgreed
  4. Award of Construction contracts at Sir John Heron Primary SchoolAgreed
  5. Award of Construction contract at Cleves Primary School.Agreed
  6. Award of Construction contract at St. Angela’s SchoolAgreed

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies