Item6

Resolved

Decision The Deputy Mayor agreed to a pprove the acceptance of the tender submitted by Neilcott Construction in the sum of £2,100,000 for construction works at Sir John Heron Primary . Reasons for the Recommendations The scheme of Delegation and the Council’s Contract Standing Orders requires that Mayoral approval is given for the award of a contract which is above £500,000 .
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Purpose of report

This report requests approval to accept the tender submitted by Neilcott Construction in the sum of £2,100,000 for construction works at Sir John Heron Primary School. This is in accordance with the decision secured at Mayoral Proceedings on Thursday 11 December 2014 to begin the procurement process.

Executive Summary of Outcomes

 The construction project will address suitability issues with the building not having sufficient facilities to support the delivery of the curriculum for all pupils with PMLD, as well as to ensure it is maintained to a safe and acceptable standard that can contribute to improved educational performance. Four classrooms enables the internal improvements of spaces to support pupils, as well as removing a temporary classroom, currently used to accommodate bulge classes.

 The construction project forms part of the strategy to help ensure that Newham will continue to meet its legal requirement to ensure that there are sufficient pupil places within the Borough, as the design enables the school to accommodate additional bulge years if required.(A bulge year is a temporary class of thirty pupils).

Recommendations

The Mayor is asked to approve the award of acceptance of the tender submitted by Neilcott Construction in the sum of £2,100,000 for construction works at Sir John Heron Primary.

Reasons for the recommendations

The scheme of Delegation and the Council’s Contract Standing Orders requires that Mayoral approval is given for the award of a contract which is above £500,000.

Name of lead Officer: James Thomas POSITION: Director of Commissioning, Children’s Services

Name of Lead Member consulted: Councillor Quintin Peppiatt Position: Lead Member Children and Young People (including Children's Safeguarding)

Originator of report: John Cochrane. Tel no: 020 3373 7820. E-mail address: [email removed]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report: N/A

List of enclosures:

 Scope of the construction project - Appendix A  Equality Impact Assessment - Appendix B. Report - Part A

1. Introduction and Background

1.1This report requests approval to the award of a contract to Neilcott Construction for the main construction stages of a two stage tender at Sir John Heron Primary School. This is in accordance with the decision secured at Mayoral Proceedings on Thursday 11 December 2014 to begin the procurement process.

1.2The costs of the project will be funded via the schools capital programme (approved by Cabinet on 18 February 2016).

2. Key Considerations

2.1The Director of Commissioning (Children’s Services) in consultation with the Director of Legal and Governance agreed as an Officer Key Decision on 21 May 2015 to enter into a pre-construction agreement with Neilcott Construction Limited in the sum of £54,959.79 to carry out the pre construction duties to for the development of the proposals to deliver a construction project at Sir John Heron Primary School. This amount has now been subsumed into the contract sum. The cost includes the contractor’s preconstruction duties, including contractors design fees, management and prelims costs.

2.2The scope of the project is to provide 4 additional classrooms to accommodate bulge class (temporary class of thirty pupils) and increase PMLD resources. Together with improvement works to the school’s internal courtyard hall and the provision of an enhanced MUGA.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of Construction contracts at Sir John Heron Primary SchoolReport 108 KB DownloadRead as text
PDF
Draft SJH 29 April 2016.Report 104 KB Download
PDF
Sir John Herron School Tender award Appendix AAppendix 42 KB Download
PDF
Sir John Herron School Tender award Part BReport 56 KB Download

At this meeting

Whole meeting

Who was there

1 of 5 attended
DF
Daniel FenwickOfficer, expected
JM
James MartinSecretary, expected
SR
Sir Robin WalesChair, apologies
LH
Councillor Lester HudsonChair, present
GA
Gemma AllenOfficer, expected

On this subject at Newham

Search all
  1. Award of Construction contracts at Sir John Heron Primary SchoolThis decision
  2. Will Thorne Pavilion and Queen's Market Creative Wellbeing Space Main Works Construction Contract Procurement and Award StrategyAgreed
  3. Award of Construction contracts at St. Bonaventure's SchoolAgreed
  4. Award of Construction contracts at Edith Kerrison, and Rosetta SchoolsAgreed
  5. Award of Construction contract at Cleves Primary School.Agreed
  6. Award of Construction contract at St. Angela’s SchoolAgreed

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies