Approval of funding for replacement of Air Conditioning Units at Building 1000, Dockside

Agreed Executive 3 papers

Cabinet agreed this item on Thursday 16 February 2017. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Decision The Mayor in consultation with Cabinet agreed to approve capital expenditure up to £520,000 from within the Asset Management capital allocation, subject to pre procurement approval at Mayoral Proceedings and receipt of acceptable tenders. Reasons for the Recommendations Two of the four existing air conditioning units serving the building have already failed and a third has been recommissioned following a recent repair, with no guarantee of the unit remaining operational in the medium to longer term. Air conditioning is required throughout the year to prevent overheating and to maintain a suitable environment for building occupants.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report seeks approval to spend capital on the replacement of the air conditioning units serving Building 1000 Dockside to sustain a suitable working environment for both Council operations and commercial tenants within the building.

The Medium Term Budget Strategy agreed by Cabinet in February 2016 included a number of new capital schemes, including a substantial capital allocation for addressing more significant expenditure requirements within the Council’s property portfolio. The Budget Strategy noted that funding for this, and other similar projects, would need to be determined as part of a separate business case.

Approval is now sought to incur capital spend on this project as set out in section 2 of this report.

Executive Summary of Outcomes

Agreement to incur the capital expenditure will support the continued operation of Council functions within an acceptable working environment for staff, visitors and the other commercial tenants within the building.

General Report Template: Ver: 006 Last revised: April 2015 Recommendations

The Mayor in consultation with Cabinet is asked to:

Approve capital expenditure up to £520,000 from within the Asset Management capital allocation, subject to pre procurement approval at Mayoral Proceedings and receipt of acceptable tenders.

Reasons for the recommendations

Two of the four existing air conditioning units serving the building have already failed and a third has been recommissioned following a recent repair, with no guarantee of the unit remaining operational in the medium to longer term.

Air conditioning is required throughout the year to prevent overheating and to maintain a suitable environment for building occupants. Further information is set out within Part B of this report

Name of Lead Officer: Mark Butler Position: Director of Asset Management

Name of Lead Member consulted: Councillor Lester Hudson Position: Deputy Mayor and Cabinet Member for Finance, oneSource, Project Delivery and Commercial Opportunities

Originator of report: Ron Bateman Tel no: 0203 373 0528 E-mail address: [email removed]

Local Government (Access to Information) Act 1985 Background papers used in preparing this report:

 Specialist report from KJ Tait Facilities

Copies of Background documents can be obtained from: Ron Bateman Tel no: 0203 373 0528 E-mail address: [email protected]

List of enclosures / Appendices:

Appendix A – Summary of Procurement Options

General Report Template: Ver: 006 Last revised: April 2015 Report - Part A

1. Introduction and Background

1.1The purpose of this report is to seek approval to fund the replacement of the four chiller units at Newham Dockside offices due to recent critical failures of large components including 3 condenser coils and 2 compressors. A separate pre-procurement report is being submitted to Mayoral Proceedings on the same date (16th February 2017) dealing with permissions to undertake a procurement exercise.

1.2The existing chiller units were installed in pairs in 2003, providing air conditioning to the East and West wings of the building, separated by the central atrium area. The specific reason for failure of coils is not known but is assumed to be vibration on long unsupported sections of coils. On the basis of current failures it is considered likely that further coils could fail within the remaining chiller units.

1.3The building is currently operating with 2 of the 4 units functioning which is not sustainable. The air conditioning system is in use throughout the year and due to the thermal efficiency of the building there remains a need to cool the ambient air within each wing, even during winter months.

2. Key Considerations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Replacement of air conditioningAppendix 1 62 KB Download
PDF
Approval of funding for replacement of Air Conditioning Units at Building 1000, DocksideReport 88 KB DownloadRead as text
PDF
Funding replacement of air conditioning units: Part BReport 50 KB Download

At this meeting

Whole meeting

Who was there

6 of 11 attended
TC
Tony ClementsOfficer, expected
DF
Daniel FenwickOfficer, expected
JM
James MartinSecretary, expected
SR
Sir Robin WalesChair, present
FC
Councillor Frances ClarkeMember, absent
CM
Cabinet Member - Councillor Lester Hudson (Deputy Mayor)Member, present
CM
Cabinet Member - Councillor Ken ClarkMember, present
CM
Cabinet Member - Clr Lakmini ShahMember, absent
CM
Cabinet Member - Councillor Rev. Quintin PeppiattMember, present
CM
Cabinet Member - Councillor Forhad HussainMember, present
RT
Councillor Rachel TrippMember, present

On this subject at Newham

Search all
  1. Approval of funding for replacement of Air Conditioning Units at Building 1000, DocksideThis decision
  2. Levelling Up Fund (LUF) programme update: Approval to re-profile LUF Grant FundingAgreed
  3. Royal Docks Corridor - Funding Changes ApprovalAgreed
  4. Demolition of Tower Blocks - Approval of Delegated Authority to Enter into a Funding Agreement with the London Thames Gateway Development CorporationAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies