Levelling Up Fund (LUF) programme update: Approval to re-profile LUF Grant Funding

Agreed Executive 3 papers

Cabinet agreed this item on Tuesday 2 April 2024. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree to: i) The transfer of £1.45m LUF grant funding from the Lochnagar Bridge project to Canning Town Old Library and £234k to the Will Thorne Pavilion project to enable delivery by the Memorandum of Understanding (MOU) deadline of end of March 2025. ii) Note progress to date on the two LUF programmes, as detailed in Appendix 1 Alternatives Considered a) The LUF grant funding could be reallocated to other projects within the same bid (0195). However, the CTOL project represents a higher priority to deliver the agreed outputs and outcomes on time. b) The remaining LUF grant funding could be handed back to central government, but this option is not recommended as this proposed way forward means Newham can continue to benefit from the full grant awarded. For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree to: i) The transfer of £1.45m LUF grant funding from the Lochnagar Bridge project to Canning Town Old Library and £234k to the Will Thorne Pavilion project to enable delivery by the Memorandum of Understanding (MOU) deadline of end of March 2025. ii) Note progress to date on the two LUF programmes, as detailed in Appendix Alternatives Considered a) The LUF grant funding could be reallocated to other projects within the same bid (0195). However, the CTOL project represents a higher priority to deliver the agreed outputs and outcomes on time. b) The remaining LUF grant funding could be handed back to central government, but this option is not recommended as this proposed way forward means Newham can continue to benefit from the full grant awarded.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1For the reasons set out in the report and its appendices, Cabinet is recommended to:

2.1.1 Agree to the transfer of £1.45m LUF grant funding from the Lochnagar Bridge project to Canning Town Old Library and £234k to the Will Thorne Pavilion project to enable delivery by the Memorandum of Understanding (MOU) deadline of end of March 2025.

2.1.2 Note progress to date on the two LUF programmes, as detailed in Appendix 1.

Background

3.1Further to a decision by Cabinet on 1 st June 2021, the Council submitted and successfully secured two bids (LUF) from Central Government, receiving grant funding of £39,777,273.

3.2At Cabinet on the 11th January 2022, the Council approved the acceptance of the grant funding of £39,777,273 from the Department of Levelling Up, Housing and Communities (DLUHC), and delegated the authority to the Corporate Director of Inclusive Economy and Housing to enter into the relevant grant agreement, following the advice provided by the Council’s legal services.

3.3The Memorandums of Understanding were signed in February 2022 and all projects are now in delivery.

3.4The aims of these projects are to:  Create new, accessible spaces where people from all backgrounds can work, come together and enjoy shared culture.  Better connect neighbourhoods to make it easier to move around in a green, safe and healthy way.  Improve our neighbourhood environments to make them places that our communities are proud of and want to spend time.

4. Progress on delivery and movement of grant funding

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2.1. Programme delivery progress update_Appendix 1Appendix 2.5 MB Download
PDF
2.2. Programme delivery financial summary_Appendix 2 (1)Appendix 487 KB Download
PDF
Levelling Up Fund (LUF) programme update: Approval to re-profile LUF Grant FundingReport 378 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
JA
Councillor James AsserMember, present
CM
Councillor Charlene McLeanMember, apologies
ZA
Councillor Zulfiqar AliMember, present
NW
Councillor Neil WilsonMember, present
SJ
Councillor Sarah Jane RuizMember, present
SM
Councillor Shaban MohammedMember, present
AV
Councillor Amar VirdeeMember, present

On this subject at Newham

Search all
  1. Levelling Up Fund (LUF) programme update: Approval to re-profile LUF Grant FundingThis decision
  2. Levelling Up Fund: Compressor House Project Funding and DeliveryAgreed
  3. Levelling Up Fund: Proposals for Future DeliveryAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies