ICT Investment

Agreed Committee 3 papers

Mayoral Proceedings agreed this item on Thursday 25 May 2017. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Decision The Mayor agreed: i) The allocation of £3M capital funding to fund ICT projects from unallocated capital in the Capital programme starting in 2017/18 over 3 years; ii) To note that the currently identified projects at Appendix 2 total £1.6M and would be allocated immediately and it was estimated that the remaining projects would cost £1.4M; and iii) That officers provide the Mayor with an accommodation strategy setting out what accommodation Newham has, which staff occupy the accommodation and the current IT provision within those buildings. Reasons for the Recommendations The investment identified in this report is critical for the council to improve its current infrastructure and maintain a robust, compliant and improved infrastructure.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Purpose of report

A review of ICT service was carried out to assess issues. The findings highlighted that the ICT service is significantly underfunded. The report identified that investment was required to deliver pace and innovation, remove customer dissatisfaction and enable transformed customer operations. A report was presented to SLT and it was agreed that ICT should develop a Business Case for short/medium and long term resources to:

 “Catch up and keep pace” with ICT investment to avoid further risks  invest in new “modern working”.  invest in resources to support the service delivery in delivering the council’s digital ambitions.

This report identifies the capital investment required to improve the current ICT infrastructure and systems in order to create a robust infrastructure that facilitates innovation and transformation.

This report therefore sets out a request for the capital funding required for the IT projects over the next three years.

Executive Summary of Outcomes

The approval of this proposal will enable the development of a fully costed, prioritised and phased plan for investment in ICT infrastructure over the next three years.

General Report Template: Ver: 005 Last revised: January 2016 The plan will deliver:

o an improved, secure and stable infrastructure that supports the council’s service delivery. o improved customer experience through better provision of technology in Libraries. o technology solutions that provide greater mobility and allow flexible working. o support for the council’s Small Business Programme through innovative technology solutions. o opportunity to reduce resources in future with a stable and secure infrastructure.

Recommendations

For the reasons set out in this report:

1. The Mayor is asked to agree the allocation of £3M capital funding to fund ICT projects from unallocated capital in the Capital programme starting in 2017/18 over 3 years.

2. The Mayor is asked to note that the currently identified projects at Appendix 2 total £1.6M and will be allocated immediately and it is estimated that the remaining projects will cost £1.4M

Reasons for the recommendations

The investment identified in this report is critical for the council to improve its current infrastructure and maintain a robust, compliant and improved infrastructure.

Name of lead Officer: Priya Javeri Position: Director of Innovation and Technology

Name of Lead Member consulted: Sir Robin Wales Position: Mayor of London Borough of Newham

Consulted on : 04 May 2017

Originator of report: Priya Javeri Tel no: 020 3373 3115 E-mail address: [email removed]

Copies of Background documents can be obtained from: Priya Javeri Tel no: 020 3373 3115 E-mail address: [email removed]

General Report Template: Ver: 005 Last revised: January 2016 List of enclosures / Appendices:  Appendix 1 Breakdown of ICT requirements, risks and benefits  Appendix 2 Project Financials

Background papers  ICT Service Review

Report - Part A 1. Introduction and Background

1.1The ICT service currently delivers and manages core infrastructure and application delivery platform for all services and locations. The basis of the provision is to provide a robust and highly available core infrastructure to support the needs of services in the delivery of services to communities, citizens and businesses. At present the shared oneSource platform supports around 900 different applications, holds 200TB of system and operational data, 800 servers and 8,000 staff across two authorities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Breakdown of ICT requirements risks benefitsAppendix 1 70 KB Download
PDF
Project FinancialsAppendix 2 47 KB Download
PDF
ICT InvestmentAgenda 89 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 5 attended
TC
Tony ClementsOfficer, expected
DF
Daniel FenwickOfficer, expected
JM
James MartinSecretary, expected
SR
Sir Robin WalesChair, present
GA
Gemma AllenOfficer, expected

On this subject at Newham

Search all
  1. ICT InvestmentThis decision
  2. Tobacco Investment RestrictionsAgreed

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies