London Borough of Newham
Mayoral Proceedings, Thursday 25 May 2017

Brampton Manor Academy School Pre procurement report for a construction project

Agreed Committee 1 paper

Mayoral Proceedings agreed this item on Thursday 25 May 2017. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Decision The Mayor agreed i) The commencement of a procurement exercise for a construction project at Brampton Manor Academy School; ii) To delegate authority to the Strategic Commissioning Director of Children’s Services, in consultation with the Cabinet Member for Children’s and Young Peoples to authorise the award of the preconstruction (first stage) agreement to progress the pre procurement and also where appropriate to enter into enabling works contract(s) in accordance with the Councils Procurement Code of Practice; and iii) To note that the contract award would be subject to planning consent and the school’s decision making process. Reason for Recommendation The scheme of Delegation and the Council’s Contract Standing Orders requires that mayoral approval is given to the commencement of a tendering exercise for the delivery of a works programme which is above £500,000.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Mayoral Proceedings

Reason for recommendation

The scheme of Delegation and the Council’s Contract Standing Orders requires that mayoral approval is given to the commencement of a tendering exercise for the delivery of a works programme which is above £500,000.

Name of lead Officer: James Thomas POSITION: Director of Commissioning, Children’s Services

Name of Lead Member consulted: Councillor Quintin Peppiatt Position: Lead Member Children and Young People (including Children's Safeguarding)

Originator of report: John Cochrane. Tel no: 020 3373 7820. E-mail address: [email removed] Local Government (Access to Information) Act 1985 Background papers used in preparing this report: N/A.

Pre-Procurement Report Template: Last revised December 2016 2 List of enclosures:  Scope of the construction project - Appendix A

Report – Part A

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Brampton Manor Academy School Pre procurement report for a construction projectAgenda 120 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 5 attended
TC
Tony ClementsOfficer, expected
DF
Daniel FenwickOfficer, expected
JM
James MartinSecretary, expected
SR
Sir Robin WalesChair, present
GA
Gemma AllenOfficer, expected

On this subject at Newham

Search all
  1. Brampton Manor Academy School Pre procurement report for a construction projectThis decision
  2. Brampton Manor Academy, Roman Road, East Ham, London, E6 3SQDeferred
  3. Expansion of Brampton Manor AcademyAgreed
  4. Brampton Manor Academy, Roman Road, East Ham, E6 3SQAgreed
  5. Brampton Manor Academy, Roman Road, E6Agreed

More from Newham Mayoral Proceedings

All decisions
MeetingDecisionOutcome
15 Oct 2018 Newham Scheme of Delegation to the Executive & OfficersDecision The Mayor agreed: i) To notify the Monitoring Officer of her delegation of executive powers under s.9E(2) of... Agreed Open
15 Oct 2018 Health & Care Space Newham - Agreement for Lease (Royal Wharf)Decision The Mayor agreed: i) That Health & Care Space Newham (HCSN) proceed with entry into the Agreement for Lease ... Agreed Open
15 Oct 2018 Award of Commercial Property Insurance ContractDecision The Mayor Agreed: i) The award of Lot 1 and Lot 2 of the Commercial Property Insurance Contract to Bidder 3,... Agreed Open
15 Oct 2018 Provision of non-life insurance - Award of Main Insurance Contract ExtensionDecision The Mayor agreed the extension of the main insurance contracts to the existing suppliers on the basis set ou... Agreed Open
15 Oct 2018 Cyclical Decoration and Repairs Programme Year 1Decision The Mayor agreed to: i) Award the contract in relation to the Cyclical Decorations and Repairs Programme Yea... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies