Cabinet, Thursday 7 September 2017

Leisure Centre 10 Year Capital Works Programme

Approved Executive 2 papers

Cabinet approved this item on Thursday 7 September 2017. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

Decision Approve spend against the provisional 10-year capital allocation of £9.9m (revised from the original £11.1m). This is funded from the £20.5m unallocated capital resources budget in the 2017/18 Budget Report approved at cabinet in February 2017. Approve the release of a £1.6m capital grant to activeNewham, from the overall budget of £9.9m, to enable the early delivery of two critical refresh programmes at Balaam Leisure Centre and Newham Leisure Centre and to delegate authority to the Chief Executive to enter into the grant agreement, after consultation with the Cabinet Member for Leisure & Sport and subject to completion of legal and financial due diligence. Reasons for the Recommendations The recommendations enable a long term capital programme to be implemented across the Council’s leisure centre portfolio, ensuring the provision of high quality, fit for purpose and commercially viable facilities for use by residents. The release of a proportion of the budget (up to £1.6m) to activeNewham in the form of a capital grant will enable essential and immediate refresh works to be carried out at Balaam and Newham Leisure Centres to ensure that a high quality service offer for residents is maintained.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Leisure Centre 10 Year Capital Works ProgrammeReport 112 KB Copy on its way
PDF
Leisure Centre Capital Programme Part BReport 44 KB Copy on its way

At this meeting

Whole meeting

On this subject at Newham

Search all
  1. Leisure Centre 10 Year Capital Works ProgrammeThis decision
  2. Atherton Leisure Centre RedevelopmentAgreed
  3. Atherton Leisure Centre - Appointment of OperatorAgreed
  4. Atherton Leisure Centre - Advance Works Building ContractAgreed
  5. Atherton Leisure Centre - Approval of Option for the Leisure Centre and Related Decision(s) Regarding Procurement(s)Agreed
  6. Newham Leisure Centre, Prince Regent Lane (Plaistow South Ward)Agreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies