Decision For the reasons set out in the report Cabinet RESOLVED to AGREE i) A change in sequencing of RDV’s initial ‘Wave 1’ sites, previously approved by cabinet in October 2018, for the reasons set out in this report. The Didsbury Package of developments now including the former Didsbury Centre and Town Hall Annex along with six small sites shall proceed to start on site by end of March 2019 with the Brickyard and Grange Road schemes to be delivered as a separate package, subject to cabinet approval in due course; ii) To delegate to the Director of Regeneration and Planning in consultation with the Mayor, the Interim Executive Director of Financial Sustainability and the Director of Legal and Governance authority to agree the draft RDV business plan as attached as Appendix 1 subject to the items set out in Para 8.1.8 being monitored and mitigated to their satisfaction. Any material changes would be reported back to cabinet; iii) To fund the Didsbury Package of developments encompassing eight sites namely The Didsbury Centre, Town Hall Annex, Doherty Road, Wordsworth Avenue, Stracey Road, High Street South, Romford Road and Old Fire Station sites with GLA grant of up to £11,304,000 and Newham equity and loan funding up to £54,933,986 for the Development Phase and £58,816,013 for the Investment Phase and scheme specific working capital of £ 361,435 iv) To delegate to the Interim Executive Director of Financial Sustainability in consultation with the Mayor, the Director of ... view the full minutes text for item 6.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
Report title Red Door Ventures – Updated Request for Funding Date of Meeting 5th March 2019 Lead Officer and Michael Holland, Lead for Red Door Ventures contact details Email: [email protected] Director, Job title Elaine Elkington, Interim Director of Regeneration and Planning Lead Member Rokhsana Fiaz (Mayor) Key Decision? Reasons: Over £500,000; and, affects two or Yes more wards. Exempt Grounds: Appendices 1-6 and 8-10 are exempt information & by virtue of Category 3 of Rule 11 of the Access Grounds Yes to Information Procedure Rules set out in the Constitution pursuant to Schedule 12A Local Government Act 1972, as amended. Wards Affected Forest Gate North, East Ham North, East Ham Central, Manor Park, Canning Town North Appendices Exempt Appendix 1 – Draft Red Door Ventures Business Plan 2019 (if any) Exempt Appendix 2 - Due Diligence report on RDV business plan January 2019 Exempt Appendix 3 – Scheme Specific Financial Implications Exempt Appendix 4 - Viability Assessment Appraisal Report (VAAR) – Didsbury Centre, Town Hall Annex and associated smaller sites. Exempt Appendix 5 – Heads of Terms for Lease to RDV Exempt Appendix 6 – Required Due Diligence Pre Funding Appendix 7 – Equalities Impact Assessment Exempt Appendix 8 – Procurement Advice Exempt Appendix 9 - Legal commentary on Heads of Terms Exempt Appendix 10 – Statement from RDV on Package 1 impact on 2019 draft RDV Business Plan
1 Executive Summary 1.1 The Council approved a cabinet report on 15th October 2018 which set out how Red Door Ventures, the council’s wholly-owned development company, was to be re-purposed towards the council’s aims of delivering increased levels of genuinely affordable homes for our residents. The same report also provided approval for Development and Investment funding for RDV’s initial packages of development sites. Following unfortunate delays
1 to two of the RDV sites, it is now necessary to revert to cabinet for revised funding approval in order to avoid a delay to the overall RDV programme.
1.2Following the October cabinet decision, RDV, instigated senior leadership change within the company by appointing a new interim CEO and an additional Board member. The council has also increased its shareholder oversight of the company and put in place further governance and oversight processes. This is part of the strategy agreed by cabinet to re-purpose RDV and improve shareholder governance.
1.3Red Door Ventures informed the council in December that the Brickyard and Grange projects would be subject to delay.
1.4The Brickyard development is delayed as a result of changes to Building Regulations that restrict the use of Cross Laminated Timber (CLT) which forms the primary structural material for the proposed development.
1.5The Grange Road development is delayed as it was found following review by the interim CEO, that the project had not been competitively tendered.
1.6Due to the impact of these delays on both packages, RDV, in consultation with the council, has restructured the initial funding packages that were approved by the cabinet on 15th October 2018.
1.7RDV is now requesting development funding for a single Didsbury Package (Package 1) including the following sites: The Didsbury Centre; Town Hall Annex; Romford Road; Stracey Road; Doherty Road; Wordsworth Avenue; Old Fire Station; and High Street South.
1.8RDV has stated its intention to request funding for the Brickyard and Grange sites as a separate funding package later in 2019
1.9This report also recommends the council approves RDV’s draft business plan subject to ongoing monitoring and mitigation of issues set out to the satisfaction of the shareholder board.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.