For the reasons set out in the report, Cabinet RESOLVED to AGREE: To undertake all pre-construction activities for a revised scheme at the Plashet Road site (E13 0QB) that would provide around 66 x 100% Council owned, residential units at social rent levels and a nursery as part of the Affordable Homes for Newham programme agreed by Cabinet in July 2019. Alternatives Considered The consented scheme is built out at a significantly higher construction cost than the current budget thus generating governance, audit and reporting challenges, due to the complexities of the design, set out in section 4.2. The service and market need for a non-Council community centre in this location is not known The consented design will generate ongoing daylight/sunlight, maintenance and potentially building insurance issues due to the buildings proximity to the existing trees.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
3.1The development of a mixed-use scheme at Plashet Road (former site of the Upton Centre) has been subject to a number of Cabinet and Officer decisions over the period 2015 – 2019. They had resulted in a scheme to be developed within the General Fund which achieved resolution to grant planning consent (subject to entering a section 106 agreement within six months) for 55 homes (27 up to London Affordable Rent and 28 Shared Ownership Homes) a nursery and large community provision. The scheme was estimated to cost £16M and provide a marginal positive financial return to the Council. Because of the scale of the project, and the complex nature of the proposed design, an independent review was undertaken which was completed in September 2019. The scope of the review is included in Appendix 1.
4 Key Considerations & Proposals
4.1Timing and Grant: The scheme has been included in the grant allocation for the 19/20 financial year of the GLA ‘Building Council Homes for Londoners’ programme. The allocated GLA funding for this scheme is £3.8M. As the revised scheme will deliver more social rent units than the consented scheme, it may be eligible for extra funding subject to GLA agreement. Officers are in discussions with the GLA regarding funding conditions including start on site for the revised scheme. The GLA has indicated that there is flexibility in which schemes receive grant and that if the targets are exceeded, extra funding can be provided through recycled Right to Buy (RtB) receipts, available for this scheme, through the Building Council Homes for Londoners contractual framework. 4.2 Design: 4.2.1 Whilst visually striking, the consented scheme is complex and would cause some complications. These include: External curved façade (each curve is different from the other) would add cost; build complexity, risks related to tendering and timescales. As the homes do not ‘stack’, the structural, mechanical and electrical systems would be more complex, adding to the cost. Finally, a revised scheme would offer the opportunity to deliver an even more space efficient design.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.