For the reasons set out in the report, Cabinet RESOLVED to AGREE: To award the RMS building materials and stores management contract to Travis Perkins Trading Company Ltd via the OJEU compliant Pretium - Managed Stores Framework; Reference number: Pretium001 OJEU Award Notice (2016/S 150-270970) for a period of 12 months from 1 February 2020 at an estimated cost of £6m as set out in the report. Alternatives considered Do nothing This is not an option as, for the reasons set out above a reliable and cost quantifiable source is required for these supplies. Given the value of the contract, failure to procure an EU regulation compliant contract may place the Council in breach of EU regulations Procure via mini competition from an alternative framework or via an open EU complaint tender process This is not the preferred option. As set out above, there are financial and operational costs associated with change. Furthermore, an incoming supplier will have mobilisation costs which are likely to be factored into cost of a contract. It is not considered that a 1 year contract will be attractive to the market and tenders may be priced accordingly. There is not time to carry out either a mini competition or a full procurement before the current contract expires.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
1.1This report seeks approval for the award of a contract for a Repairs and Maintenance Services (RMS) building materials and stores management contract to Travis Perkins Trading Company Ltd (TP) for a period of one year from 1 February 2020 and introduces the strategy for a long-term contract.
Recommendations
2.1For the reasons set out in the report, Cabinet, is recommended to agree:
a. To award the RMS building materials and stores management contract to Travis Perkins Trading Company Ltd via the OJEU compliant Pretium - Managed Stores Framework; Reference number: Pretium001 OJEU Award Notice (2016/S 150-270970) for a period of 12 months from 1 February 2020 at an estimated cost of £6m as set out in the report.
1 3. Background
3.1RMS provide a wide range of planned and reactive works including Council property maintenance, highway repairs, street lighting, new builds, home adaptations and void refurbishment alongside other maintenance activity within the borough.
3.2In order to deliver an efficient and productive responsive repairs service, RMS needs an accessible supply of materials and equipment for its operatives.
3.3The Council’s current contract with Travis Perkins (TP) started in January 2019 and expires on 31 January 2020. This is a call-off via direct award from the Pretium Framework, a stores management framework set up by District Homes CIC, using Pretium Frameworks Ltd to manage the agreement, on which TP is the sole supplier.
3.4The Council had previously been in contract, also with TP, since 2011.
3.5The performance of the contract has been good and enhanced client management has led to a strong working relationship between the parties.
3.6An appendix on RMS‘s performance to date has been attached to this report. . 4. Key Considerations / Proposal
4.1In approving the award of a one year contract with TP in January 2019 Cabinet required that a report on procuring a new building materials and stores management contract for RMS should take into account the findings of the Internal Control Commission and be subject to pre-decision scrutiny challenge.
4.2Since January 2019 the Council has adopted a number of policies one of which is “Community Wealth Building” and as a consequence of this policy more time will be required to develop our long term materials supply strategy. This work is in progress and a business case is being developed to now include the objectives identified within this policy.
4.3It is anticipated that a further report will be brought to Cabinet in March 2020 upon completion of the business case. Whichever delivery mechanism is selected for the future stores service will take time to put in place. It is estimated that at least 12 months will be required for recommendation, decision and then implementation. An interim arrangement is needed to cover this period as the current contract expires at the end of January.
4.4There is insufficient time in which to undertake a full tender exercise for a new contract as this would require a full OJEU compliant procurement and associated
2 approval process as well as the need to manage TUPE and property transfer issues.
4.5Although there are a number of existing OJEU compliant frameworks for stores management the majority still require a mini competition to determine the successful supplier. There is insufficient time for this to take place in order to have a contract in place for 31 January 2020.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.