CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Newham
Cabinet, Friday 17 April 2020

Expansion of Little Ilford School: Pre Procurement Report

Agreed Executive 2 papers

Cabinet agreed this item on Friday 17 April 2020. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

For the reasons set out in the report, Cabinet RESOLVED to AGREE: i) The proposed procurement strategy to undertake a tender exercise, for a new-build construction project at Little Ilford School by using the LHC Modular Framework, (Ref. CN 2017-OJS108-216569) , at an estimated contract sum of £7.9m, for a period of 40 weeks, with an estimated start date in March 2021, for the expansion project at Little Ilford School. The proposed form of contract to be the JCT Design & Building Contract (DB) 2011 with the Council’s Supplemental Amendments. ii) The proposed procurement strategy to undertake a tender exercise, for a remodelling construction project at Little Ilford School by using the Council’s Constructionline approved list of contractors, at an estimated contract sum of £3.5m for a period of 40 weeks, with an estimated start date in March 2021, for the expansion project at Little Ilford School. The proposed form of contract to be the JCT Design & Building Contract (DB) 2011 with the Council’s Supplemental Amendments. iii) To waive Contract Standing Orders (CSO’s) 22.4 and 22.4.1 in respect of recommendations 2.1.1 and 2.1.2 above for the reasons set out at paragraph 4.3 and 4.5 of this report. iv) To note that, following the activities set out at paragraph 4.2 of this report, the main contract award(s) will be subject to a further decision by Cabinet and subject to planning consent and the outcome of statutory consultation on the proposed expansion. Alternatives Considered Alternative Option: Comment: Do not provide additional places. The Council has a statutory duty to provide sufficient places and forecasts indicate that these places are required. Provide additional places at another school. Little Ilford School was selected following invitation of expressions of interest from all Newham Secondary Schools. Three schools expressed an interest, including Little Ilford School and proposals are in development to expand two of these schools. The proposal is now well advanced and pursuing an alternative site would result in considerable delay. However, further expansions will be required to meet forecast demand and these will be considered at other school sites. Provide places at a new school. Land availability to build a new school is limited and would need to be identified. All new schools must be Free School Academies. A sponsor would need to be identified. Different space configuration to achieve expansion. Different options have been considered however these were considered not viable for the following reasons: 1. Standalone 2 storey block located to the side of the proposed playing field and relocation of 3G pitch. This was not accepted as it significantly reduced he playing field area for both school and community use. 2. Three storey extension linked to the existing school. This used valuable play space, disrupted the school during the construction period and split the main playing field/MUGA areas from the school. 3. Three storey new build on car park area plus relocation of the car park on part of the playing field area. This was unacceptable as there was a considerable loss ...
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

LONDON BOROUGH OF NEWHAM

CABINET

Report title Expansion of Little Ilford School: Pre Procurement Report Date of Meeting 17th April 2020 Lead Officer and Name: Treena Lyons / Zoe Power contact details Job Title: Capital Programme Manager (Basic Need) Head of Projects and Programmes External Telephone Number: 0203 3739567 / 37263 Email address : [email removed] [email removed]

Director Name: Mark Butler

Job Title: Director of Asset Management External Telephone Number: 01708 432947 E-mail Address: [email removed]

Name: Tim Aldridge

Job Title: Director of Children’s Services External Telephone Number: 020 3373 6799 E-mail Address: [email protected]

Lead Member Cllr Julianne Marriott, Cabinet Member, Education Key Decision? Yes Reason: Involves expenditure or savings of £500,000 or more. Exempt No N/A information & Grounds Wards Affected Little Ilford School is in Little Ilford Ward. Whilst most students are local to the school, some students, including students with Special Educational Needs and Disabilities (SEND), who attend the school may live across the Borough and the need to provide additional Secondary School places affects the whole Borough and therefore all wards are affected. Appendices 1.Equalities Impact Assessment (if any)

1 1 Executive Summary 1.1 Following consideration of a School Place Planning Update by Cabinet on 21st January 2019, which allocated Basic Need funding towards secondary school expansion projects to meet forecast demand for places, this report seeks approval, (subject to the outcome of the formal consultation process outlined below), to invite tenders for an expansion project at Little Ilford School.

1.2The expansion works are proposed to be undertaken via two or more two stage design and build contracts:

1.2.1 Construction project using the LHC modular framework, including design development and securing planning approval for the expansion works. 1.2.2 Construction project(s) using the JCT Design and Build Contract 2011 and/or using Minor Works contract(s) to undertake works within the existing school premises.

This report relates to procurement of the LHC modular framework contract and the JCT Design and Build Contract refurbishment works above.

1.3The procurement route and evaluation criteria (including price / quality split) have been discussed and agreed with the Head of Procurement, in line with the new guidelines agreed by Cabinet on 4th September 2019.

2 Recommendations 2.1 For the reasons set out in the report and its appendices Cabinet is requested to:

2.1.1 Approve the proposed procurement strategy to undertake a tender exercise, for a new-build construction project at Little Ilford School by using the LHC Modular Framework, (Ref. CN 2017-OJS108-216569) , at an estimated contract sum of £7.9m, for a period of 40 weeks, with an estimated start date in March 2021, for the expansion project at Little Ilford School. The proposed form of contract to be the JCT Design & Building Contract (DB) 2011 with the Council’s Supplemental Amendments.

2.1.2 Approve the proposed procurement strategy to undertake a tender exercise, for a remodelling construction project at Little Ilford School by using the Council’s Constructionline approved list of contractors, at an estimated contract sum of £3.5m for a period of 40 weeks, with an estimated start date in March 2021, for the expansion project at Little Ilford School. The proposed form of contract to be the JCT Design & Building Contract (DB) 2011 with the Council’s Supplemental Amendments.

2 2.1.3 Agree to waive Contract Standing Orders (CSO’s) 22.4 and 22.4.1 in respect of recommendations 2.1.1 and 2.1.2 above for the reasons set out at paragraph 4.3 and 4.5 of this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Expansion of Little Ilford School: Pre Procurement ReportReport 189 KB DownloadRead as text
PDF
Little Ilford Expansion Pre Procurement Cabinet Report App 1 FinalAppendix 295 KB Download

At this meeting

Whole meeting
3MinutesOn the agenda
4Expansion of Little Ilford School: Pre Procurement ReportThis decision

Who was there

9 of 13 attended
AM
Adrian MaySecretary, expected
JF
Jayne FisherCouncil Staff, expected
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
JG
Councillor John GrayMember, present
CM
Councillor Charlene McLeanMember, present
ZA
Councillor Zulfiqar AliMember, present
JM
Councillor Julianne MarriottMember, present
JB
Councillor James BecklesMember, present
TP
Councillor Terence PaulMember, present
SJ
Councillor Sarah Jane RuizMember, present
JA
Councillor James AsserMember, present
DF
Daniel FenwickOfficer, expected

All 13 on the meeting page

On this subject at Newham

Search all
  1. Expansion of Little Ilford School: Pre Procurement ReportThis decision
  2. Expansion of Little Ilford School: Additional Funding Allocation and Procurement Report - New Classroom BlockAgreed
  3. Expansion of Little Ilford School: Procurement Report (Constructionline) and Allocation of Additional Basic Need Capital FundingAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies