Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 7 September 2021. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

For the reasons set out in the report, Cabinet RESOLVED to AGREE: I. To allocate additional Basic Need capital funding of £701,316 to the project, as set out at paragraph 8.1.3 of the report; and II. To award a contract in the sum of £8,368,878 to Module-AR Ltd (M-AR) to provide a new two / three-storey classroom building at Little Ilford School, as set out at paragraph 4.2 of the report. Alternatives Considered Not to provide additional places – the Council had a statutory duty to provide sufficient places. There continued to be significant additional pressure on secondary school places; since September 2019 an additional 11 forms of entry had been provided to meet demand. To meet demand for September 2021 onwards, four further forms of permanent entry were planned at Little Ilford (two forms) and Lister Schools (two forms). Data from school applications for pupils applying for Year 7 places for 2021 confirmed that the additional provision was needed in order to ensure every child could be offered a place. Provide additional places at another school - In 2018/19 all Newham secondary schools were invited to express interest in expanding to meet forecast demand for 2021. Three schools expressed interest. A number of secondary schools had already been expanded and there was little scope to expand them further, which limited the response from other schools. Two of the three schools were selected (Little Ilford and Lister) on the basis that they were popular and at least good performing schools with the capacity to expand. The proposal was now well advanced and pursuing an alternative site would result in considerable delay. Provide places at a new school - land availability to build a new school was limited and would need to be identified. It had not been possible to identify a site for a new secondary school, particularly in the east of the borough where secondary school places were in shorter supply. The difficulty in identifying suitable site(s) was evidenced by the prolonged search by the LocatED to identify a site for 2 x new all-through Free School Academies in the borough. All new schools must be Free School Academies. A Free School Academy sponsor would need to be identified. Different space configuration to achieve expansion - Different options had been considered for the overall expansion; however these were considered not viable for the following reasons: · Standalone two-storey block located to the side of the proposed playing field and relocation of 3G pitch. This was not accepted as it significantly reduced the playing field area for both school and community use. · Three-storey extension linked to the existing school. This used valuable play space, disrupted the school during the construction period and split the main playing field/MUGA areas from the school. · Three-storey new build on car park area plus relocation of the car park on part of the playing field area. This was unacceptable as there was a considerable loss of the playing field. The chosen option of building the new ...
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Expansion of Little Ilford School: Additional Funding Allocation and Procurement Report: New Classroom BlockReport 205 KB Copy on its way

At this meeting

Whole meeting

On this subject at Newham

Search all
  1. Expansion of Little Ilford School: Additional Funding Allocation and Procurement Report - New Classroom BlockThis decision
  2. Expansion of Little Ilford School: Procurement Report (Constructionline) and Allocation of Additional Basic Need Capital FundingAgreed
  3. Expansion of Little Ilford School: Pre Procurement ReportAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies