Item16
Resolved
For the reasons set out in the report, Cabinet RESOLVED to AGREE: i) To entering into a JCT Design & Build contract with Rooff Limited for the sum of £6,241,635 for the Bramall Close/ Idmiston schemes for 24 homes at London Affordable Rent; ii) To substitute sites as set out in Tables 3 and 4 within the Affordable Homes for Newham Programme approved by Cabinet in July 2019; and iii) To delegate authority to Corporate Director of Inclusive Economy & Housing in consultation with the Lead member for Regeneration, Planning and Strategic Housing Delivery and Lead Member for Housing Services to substitute Council-owned sites in the Affordable Housing Programme. Alternatives considered Site alternative uses would have been considered prior to the release of these sites for development as approved by the Cabinet (see reference above). The alternative of not delivering these schemes will impact upon the affordable homes programme. The proposed unit mix on these sites is considered the optimum to meet local needs and represent value for money.
Word for word from the decision Newham published for this meeting.
Source: mgov.newham.gov.uk