For the reasons set out in the report, Cabinet RESOLVED to AGREE: i) T h e use of £700,000 of Education Contribution Section 106 originally specified as being part of a wider Educational Contribution of £2.39 million to assist in the delivery of the Talent House for Urban Culture. Alternatives considered Provision of a loan - this would require the income from the organisation to be sufficient to repay the Council. The organisation does not have the income generating capacity to service a loan, so a loan was not a viable option. Not to agree the recommendations set out in the report – this would result in the Talent House for Urban Culture not being delivered and its benefits not being realised. Newham would lose a prospective £3.4 million investment, as well as an important cultural hub to further bolster East London’s strong offer. In addition, young people of Newham and neighbouring boroughs would potentially lose access routes to further their education and opportunities in both dance and music. The monies would otherwise contribute to supporting the Council as the Local Education Authority to deliver its pupil place expansion programme. In future the Talent House, for all it aligns to the principle of education, may impact on the Council’s ability to deliver school expansions (including Special Educational Needs and Disabilities and alternative provision) within available budgets in future years.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
1.1This Report relates to the use of monies provided as an Education Contribution, via the London Legacy Development Corporation, by means of an agreement under Section 106 of the Town and Council Planning Act 1990 as part of the development at Sugar House Lane. The total Education Contribution funding pertaining to the aforementioned S106 agreement is £2.39 million (to be index linked). These monies are stipulated through the Section 106 agreement as requiring the consent of the London Borough of Newham for expenditure as stipulated in the relevant clause of the agreement (see 3.7).
1.2This Report recommends that £700,000 from the wider £2.39 million Education Contribution for this scheme is utilised to support delivery of the Talent House facility. Talent House is to include the delivery of new dance and music based programmes linked to schools and youth programmes, as well as affordable workspace delivering educational outcomes. Talent House, within the Sugar House Island development, is scheduled to open in September 2021.
1 1.3 The Sugar House Lane development was granted planning permission in 2012 by the London Thames Gateway Development Corporation, and has subsequently been overseen by the London Legacy Development Corporation (LLDC) due to its inclusion within the LLDC Planning Authority boundary.
1.4The Talent House for Urban Culture will be located at Sugar House Lane, a development being bought forward by Vastint between Stratford High Street and Three Mills. Through the development branded ‘Sugar House Island’, Vastint is transforming 26 acres of land in order to deliver 58,000 m2 of office space, the first phase bringing forward 9,000 m2 of office space to creative businesses, 1,200 homes (with 40% three bed or more) and the enablement of a two-form entry primary school.
1.5East London Dance, a dance development organisation based in Newham and Urban Development, a music talent development charity, will occupy the Talent House. Proposed as the UK’s first Talent House for Urban Culture, it will offer a music and dance hub for the young people of East London. The organisations will deliver the fit out through their joint venture company 3 Sugar House Lane Limited and post-occupancy programmes will be delivered by the individual shareholder organisations.
Recommendations
2.1For the reasons set out in the Report, Cabinet is recommended to:
2.1.1 Approve the use of £700,000 of Education Contribution Section 106 originally specified as being part of a wider Educational Contribution of £2.39 million to assist in the delivery of the Talent House for Urban Culture.
Background
3.1The Sugar House Island development is a 26 acre mixed use development comprising of 1,200 homes, a two-form entry primary school and 58,000 m2 of office space being taken forward by Vastint. Construction has begun on site and the project is currently working its way through early phases to include residential and office floorspace. The school will be run by School 21, under the Big Education Trust and will be delivered as part of the scheme. Further commentary is provided on the school at 3.3.
Planning Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.