For the reasons set out in the report, Cabinet RESOLVED to AGREE: i) To approve the Council entering into a financial assistance agreement with the Greater London Authority to release the next tranche of funding, as set out in the report; and ii) That once funding was secured from the Greater London Authority to approve use of the funding towards the costs of detailed scheme design, utility diversions, pre-construction costs and purchase of equipment for a number of signal sites, as set out in table 2 of the report. Alternatives considered To do nothing – the emerging residential and business communities in the Royal Docks have been pressing for change and to do nothing would not be acceptable to them. In addition, the Royal Docks Enterprise Zone is a development opportunity of world-wide significance, and to fail to address the existing quality of environment on the key access corridor to this Zone would not be acceptable for the Council in reputational terms. There is also a pressing road safety need for changes to the corridor to make the area safer for the increasing number of residents (particularly children) who now live in the area, and to urgently address previous safety issues, which have resulted in fatalities to both drivers and cyclists. Therefore, to do nothing is not a defensible position for the Council. As part of the design process, a minimum of two options for project are being developed. A preferred option following modelling approval by Transport for London will be consulted in spring next year with the stakeholders. The preferred scheme following consultation with stakeholders will be presented to Cabinet next year for approval.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
EqIA: Royal Docks Corridor Project Assessing impact on equality is a process which develops along with your policy. You must complete the table below to ensure that the EqIA process can be tracked.
Version number 001 Date Created 18/11/2019 Date last reviewed: 14/12/2020 Approved by: Murray Woodburn (Project Director) Date approved: Murray still to approve Next review date: 30/03/2020 Saved as: EqiA
1. Management of the EqIA
Paul Gannon & Rex Vaheesan (Project Managers), Murray Woodburn (Project Director)
2. Identification of policy aims, objectives and purpose
A Royal Docks corridor improvement masterplan that forms part of the Royal Docks Enterprise Zone initiative was agreed with the Newham delegated powers in early 2016. This corridor comprises primarily of Silvertown Way, North Woolwich Road, leading up to Connaught Bridge. There have been several developments along the Silvertown Way and North Woolwich Road Corridor in recent years. New applications were being considered by Newham Planners along the length of the corridor. The masterplan considered accommodating all development accesses in progressing the highway improvement proposals.
The developments along Silvertown Way and North Woolwich Road Corridor, in recent years, show these to be extended along the length of the road on both sides. More recently Barrier Point has been completed and Royal Wharf is currently under construction. With these developments and the proposed regeneration at Silvertown Quays, North Woolwich Road and Silvertown Way will see a complete change to their environment in the foreseeable future.
The Council has received several Section 106 Agreement contributions from the developments mentioned above, for carrying out highway and transport improvement measures. The Council has utilised some of this funding to develop a masterplan and some initial measures on the improvements.
The Royal Docks corridor is now driven as a highway and public realm improvement project where all development accesses will be accommodated and measures will be introduced to enhance conditions for the vulnerable road users such as pedestrians and cyclists. This is a joint initiative between Royal Docks Enterprise and Newham Council. Newham have to date secured S106 monies to progress various work. A report is due to be presented at the March cabinet to approve £ 748,159, this is in addition to the S106 already secured for £490k. Further details on how this money will be spent can be found within scheme details. As this is a joint venture the Royal Dock
London Borough of Newham 1 Enterprise have funding of £46.2m which is expected for detail design, consultation and implementation for the whole scheme. The Royal Docks Team have already secured £460k for initial design work and joint commissioning for a place making design. To secure the remaining £46.2m approval is required from Royal Docks Enterprise Zone Board, GLA and appropriate delegated governance and/or London Mayor’s decision.
3. Scope / focus of the EqIA Consider how relevant the policy is to equality and which group(s) it is likely to affect most. This is where you make a judgement on where to concentrate your efforts and lay the ground for a proportionate approach. a. Could it affect some groups differently? b. Could it advance equality? c. Could it foster good relations?
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies