What the committee will consider, in order, with every paper attached to its item. Submission of masterplan planning application for Carpenters Estate is the main business.
In accordance with the Members’ Code of Conduct this is the time for Members to declare any disclosable pecuniary interests or non-pecuniary interests they may have in any matter being considered at this meeting having regard to the guidance attached to the agenda.
Decisions of Cabinet made on 24 th February 2022 and 8 th March 2022
Decision: For the reasons set out in the report and its appendices Cabinet RESOLVED to AGREE: To approve the submission of the masterplan and a congruent Outline Planning Application by London Borough of Newham to the London Legacy Development Corporation (LLDC) for the Carpenters Estate masterplan in April 2022 in accordance with detail contained in the report. Alternatives Considered Not to progress to submit an Outline Planning Application: This would result in delaying the determination of the... Decision page
Decision: For the reasons set out in the report and appendices Cabinet RESOLVED to AGREE: i) The freehold sale of the land shown edged green on the Plan at Appendix 1 to the Purchaser, the Transport for London (TfL), on the sale price and terms as set out at exempt appendix 2; and ii) To delegate to the Director of Property authority to finalise the terms set out at exempt appendix 2 and to take all necessary actions to complete the freehold transfer, together with any necessary ancillary agreements.... Decision page
Decision: For the reasons set out in the report, Cabinet RESOLVED to AGREE: i ) To adopt the new 2022 Agreed Syllabus for Religious Education; ii) To note that Newham commenced its review of the Agreed Syllabus within 5 years of publishing the last syllabus in 2016 as the law required (there was one year where the syllabus development was put on hold due to Covid ); and iii) To note that changes made to the Agreed Syllabus were in line with directives from DfE (... Decision page
View the declarations of interest for item 9.
Decision: For the reasons set out in the report and its appendices, Cabinet RESOLVED to AGREE: i) To commence a procurement exercise to tender a two stage works contract through a restricted tender to commence in July 2023 at an estimate value of £2,415,584 to provide a new standalone classroom block, including a new PMLD resource provision at Colegrave Primary School; ii) To delegate the approval for the Pre Construction Services Agreement) for Colegrave primary school under delegated authority to the... Decision page
Decision: For the reasons set out in the report and its appendices, Cabinet RESOLVED to AGREE: i) To approve the award to lease 28 replacement vehicles utilising an existing framework. The replacement vehicles would be Euro 6 & operate on the councils gas to liquid fuel, in addition, the bin lifting equipment will be fully electric & produce zero emissions, ensuring they are all ULEZ compliant & have a positive impact on the council air quality; and. ii) To delegate to the Corporate Director of... Decision page
Decision: For the reasons set out in the report and its appendices, Cabinet RESOLVED to AGREE: i) To approve the proposed list of schemes planned for this year as set out in Appendix A; and ii) To approve the proposed methodology for the delivery of the planned patching programme as described in section 4.4 of the report and approve its inclusion as part of the overall maintenance strategy for 2022-23. Alternatives Considered An alternative considered, was to do no planned maintenance or very little, and... Decision page
Item 6 is where most of this meeting's papers sit: 4 papers, about 81 MB.
This is the first time this subject appears in the meetings we have read.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 19 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 8 March 2022. None of its items return this time; 7 items are new. Point at any item to follow a thread. Procedural items are left out.
Towards a Better Newham Q3 Performance Report, Newham Children and Young People's Plan 2022-27 and Young People's Charter, New Homes for Newham Programme - 2021-22 Contract Awards (Post December 2021 Cabinet Approval), Revised masterplan strategy for strategic site 28 at Custom House including early delivery of William Paton Gardens and 20-22 Freemasons Road and 6 more do not return this time.
See the 8 March meetingEvery Cabinet meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Newham, Cabinet
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.