Cabinet, Tuesday 3 October 2023

Approval to Procure a Main Works Building Contract for Canning Town Old Library

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 3 October 2023. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree: i) To approve the commencement of the main building works procurement process for Canning Town Old Library refurbishment, with an estimated contract value of £6.9m. ii) To delegate authority to the Corporate Director of Inclusive Economy & Housing in consultation with the Lead Member for Inclusive Economy, Housing Delivery and Climate Emergency, Performance and Transformation to award and enter into a Main Works Construction Contract with the highest scoring contractor following a procurement process for the main building works. Alternatives Considered a) Not commencing this procurement exercise may leave LBN at risk of losing a considerable amount of LUF funding, given that the LUF grant funding is time limited and not proceeding would cause significant delays. b) LBN does not have the in-house construction capacity to deliver a refurbishment of this nature. As such an external procurement solution is required. For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree: i) To approve the commencement of the main building works procurement process for Canning Town Old Library refurbishment, with an estimated contract value of £6.9m. ii) To delegate authority to the Corporate Director of Inclusive Economy & Housing in consultation with the Lead Member for Inclusive Economy, Housing Delivery and Climate Emergency, Performance and Transformation to award and enter into a Main Works Construction Contract with the highest scoring contractor following a procurement process for the main building works. Alternatives Considered a) Not commencing this procurement exercise may leave LBN at risk of losing a considerable amount of LUF funding, given that the LUF grant funding is time limited and not proceeding would cause significant delays. b) LBN does not have the in-house construction capacity to deliver a refurbishment of this nature. As such an external procurement solution is required.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to Procure a Main Works Building Contract for Canning Town Old LibraryReport 500 KB Copy on its way

At this meeting

Whole meeting

On this subject at Newham

Search all
  1. Approval to Procure a Main Works Building Contract for Canning Town Old LibraryThis decision
  2. Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027Agreed
  3. Stratford Library HVAC Refurbishment Works - Pre-procurement ApprovalAgreed
  4. New Plaistow Library Fit Out - Pre Procurement ApprovalAgreed
  5. Pre-Procurement Approval for Pharmacy Public Health ServicesAgreed
  6. Pre-procurement approval for an HIV Prevention & Wellbeing Services Framework AgreementAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies