Canning Town Estates Regeneration Programme -Vincent Street Main Works Contract Award

Agreed Executive 1 paper

Cabinet agreed this item on Thursday 9 November 2023. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree: i) To entering into the 2 nd stage JCT Design & Build contract with Hill Partnerships Limited. ii) To approve a budget of up to the maximum capital value of £73m, subject to a final satisfactory cost submission being received within the agreed capital envelope. iii) To exercise value engineering of the final cost submission to ensure the appropriate balance of quality and value is achieved. iv) To deliver a further report on the final cost submission of Vincent Street to the Corporate Director of Inclusive Economy and Housing prior to entering into contract. v) To delegate authority to Corporate Director of Inclusive Economy & Housing in consultation with the Lead Member for Inclusive Economy and Strategic Housing Delivery and Lead Member for Housing Services to enter into the JCT Design & Build contract. Alternatives Considered a) Not to progress the award of the main works contract. A new procurement exercise could be undertaken using the RIBA stage 4 design information developed under the PCSA contract. This would cause a delay of at least six months and would further frustrate the regeneration of the Canning Town estate, which has been ongoing since 2005. The council would incur additional cost associated with running and reviewing a new tender and there is no guarantee a new tender would result in a lower price submission. With current cost inflation, there is a risk the construction cost increases. If the scheme is not progressed expediently, the GLA could also request the council returns the £14.7m grant funding under the grant funding agreement. b) To do nothing – the land has been vacant since 2016. Not delivering the scheme means that the council fails to deliver the much needed affordable housing. For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree: i) Entering into the 2 nd stage JCT Design & Build contract with Hill Partnerships Limited. ii) To approve a budget of up to the maximum capital value of £73m, subject to a final satisfactory cost submission being received within the agreed capital envelope. iii) To exercise value engineering of the final cost submission to ensure the appropriate balance of quality and value is achieved. iv) To deliver a further report on the final cost submission of Vincent Street to the Corporate Director of Inclusive Economy and Housing prior to entering into contract. v) Delegate authority to Corporate Director of Inclusive Economy & Housing in consultation with the Lead Member for Regeneration, Planning and Strategic Housing Delivery and Lead Member for Housing Services to enter into the JCT Design & Build contract. Alternatives Considered a) Not to progress the award of the main works contract. A new procurement exercise could be undertaken using the RIBA stage 4 design information developed under the PCSA contract. This would cause a delay of at least six months and would further frustrate the regeneration of the Canning Town estate, which has been ongoing since 2005. The council would incur additional cost associated with running and reviewing a new tender and there is no guarantee a new tender would result in a lower price submission. With current cost inflation, there is a risk the construction cost increases. If the scheme is not progressed expediently, the GLA could also request the council returns the £14.7m grant funding under the grant funding agreement. b) To do nothing – the land has been vacant since 2016. Not delivering the scheme means that the council fails to deliver the much needed affordable housing.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Canning Town Estates Regeneration Programme -Vincent Street Main Works Contract AwardReport 460 KB Copy on its way

At this meeting

Whole meeting

On this subject at Newham

Search all
  1. Canning Town Estates Regeneration Programme -Vincent Street Main Works Contract AwardThis decision
  2. New Premises Licence Application - Cafe Marina, Unit 4a Excel Marina, Canning Town, E16 1ATAgreed
  3. Variation of a Premises Licence Application - Butchers Road Newsagents, 83 Butchers Road, Canning Town, E16 1NEAgreed
  4. Sunborn London Yacht, Western Gateway, Canning Town, London E16 1AANoted
  5. Land At 10 To 11 Brunel Street And 36 To 48 Shirley Street, Canning Town, London E16 1HUAgreed
  6. Holiday Inn Express 1 - 3 Silvertown Way, Canning Town, London E16 1EAAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies