Sunborn London Yacht, Western Gateway, Canning Town, London E16 1AA
NotedCommittee1 paper
AI summaryNewham Strategic Development Committee approves replacement of Sunborn Yacht Hotel with a new 223-cabin vessel in Royal Victoria Dock, subject to a legal agreement within six months.
Written from the decision and the officer reportPDF Pro
OutcomeNotedDelegated to Director of Place Making once s106 is completed
Money£71,167.50S106 local employment contribution, already paid under previous consent and carried forward
What happens nextSign s106 within 6 monthsOtherwise the Director can refuse planning permission
Who it affectsSetting of Grade II listed assetsStothert and Pitt Cranes, Warehouse W, Warehouse K at Royal Victoria Dock
What was decided
The Committee agreed the reasons for approval as set out in the officer report. Report P2
Authority was delegated to the Director of Place Making to grant planning permission once a Section 106 legal agreement is completed and the 17 listed conditions are imposed. Report P3, P7
If the Section 106 agreement is not completed within six months of the resolution, the Director of Place Making may refuse planning permission. Report P4
Why
Officers found that a hotel on this mooring is a well established use, accords with Royal Docks tourism and employment policies, and is identical in design to a previously approved scheme with no material policy change since. Report P49, P55, P133, P137, P229
The angled mooring position was judged not to cause undue harm to nearby Grade II listed heritage assets, including the Stothert and Pitt Cranes, and conditions would secure acceptable amenity, transport, biodiversity and airport safeguarding outcomes. Report P150, P164, P171, P226
What happens next
The applicant and Council must complete the Section 106 legal agreement based on the three agreed heads of terms covering administration, local labour via Our Newham, and CCTV. Report P9, P10
A series of pre-commencement and pre-occupation submissions are required by condition, including a Construction and Logistics Plan, External Details, Glint and Glare Assessment, Servicing and Management Plan, Bird Hazard Management Plan and a Secured by Design package. Report P7, P239, P241, P243, P257, P258, P268
The money
£71,167.50 Section 106 contribution towards local employment, previously paid under the unimplemented 2020/21 consent and carried forward to this application Report P59, P60, P146, P147
Options considered
Chosen: Approve the replacement yacht hotel, subject to a Section 106 agreement and conditions. Use is established, design matches a previously approved scheme, and impacts on heritage, amenity, transport and airport safeguarding can be controlled by condition Report P1, P3, P55, P133, P137, P229
Chosen: Delegate refusal power if the Section 106 agreement is not completed within six months. Standard fallback to ensure the legal agreement is progressed Report P4
Implications
Legal: Planning permission can only be granted once a Section 106 agreement under the Town and Country Planning Act 1990 is signed, otherwise the Director is delegated to refuse. Report P3, P4
Financial: No further Section 106 payment is required because the £71,167.50 local employment contribution paid under the previous consent is being carried forward. Report P59, P60, P146, P147
Equalities: Officers concluded there are no adverse equalities issues and that 23 of 223 cabins (10%) would be wheelchair accessible, in line with Policy E10 and Draft Policy HS8. Report P16, P17, P114, P115, P210
Climate: A condition requires a final Urban Greening Factor of 0.2; mains electricity must be installed to the dock edge, and a BREEAM rating is not required because the proposal is a vessel, not a building. Report P102, P122, P217, P218, P248, P271
Risk: Conditions address London City Airport safeguarding: a glint and glare assessment, full cut off lighting, a Bird Hazard Management Plan, and notification of solar panels. Report P226, P243, P266, P268
Other: The site lies in Flood Risk Zones 2 and 3 but the vessel rises and falls with water levels and no dock edge changes are proposed, so the Environment Agency and Lead Local Flood Authority raised no objection. Report P25, P86, P95, P128
Who and where
The applicant, Sunborn International (UK) Limited Report P25, P42
Neighbouring occupiers of Royal Victoria Square, Warehouse W and Warehouse K Report P38, P39, P71, P150
Hotel guests, future staff and visitors to the ExCeL London conference centre Report P27, P28, P37
London City Airport, given safeguarded aerodrome and bird strike considerations Report P86, P226, P268
Local job seekers, through the Our Newham local labour Section 106 obligation Report P10, P143, P144
Timeline
2nd March 2026: 904 consultation letters sent to neighbouring properties Report P64, P66
11th March 2026: Site notice and press notice in the Newham Recorder erected and published Report P61, P62
4th April 2026: Public consultation period expired (recorded in the report as 04.04.026) Report P32, P61, P62, P64
23rd June 2026: Strategic Development Committee resolved to approve, subject to Section 106 and conditions
Within six months of the resolution: Deadline for completing the Section 106 legal agreement, otherwise the Director of Place Making may refuse Report P4
Plain English for the jargon
Section 106 (s106): A legal agreement under section 106 of the Town and Country Planning Act 1990 used to secure planning obligations from a developer
PTAL: Public Transport Accessibility Level, a 1 to 6 score used in London to rate access to public transport (here 3, moderate)
UGF (Urban Greening Factor): A scoring system for the amount of green cover provided by a development, including planting on buildings and in the public realm
CIL: Community Infrastructure Levy, a charge that local authorities in England can levy on new development to fund infrastructure
APA / SINC: Archaeological Priority Area and Site of Important Nature Conservation, planning designations shown on local policy maps
BREEAM: Building Research Establishment Environmental Assessment Method, a sustainability rating used for buildings (not applied to vessels in this case)
Listed Building setting: The surroundings of a statutory listed building, in which a development must avoid causing harm to the asset's special interest
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
Decision The Strategic Development Committee NOTED the Officer Update Report and RESOLVED to AGREE: 1. agree the reasons for approval as set out in the report; 2. delegate authority to the Director of Place Making to grant planning permission subject to the completion of a legal agreement under s106 of the Town and Country Planning Act 1990 (as amended) based on the Heads of Terms identified at Appendix 2 of the report and the Conditions listed in Appendix 1 of the report; and 3. if within six months of the resolution the legal agreement has not been completed , the Director of Place Making is delegated power to refuse planning permission.
Word for word from the decision Newham published for this meeting.Source: mgov.newham.gov.uk
The Strategic Development Committee is asked to resolve to:
1. agree the reasons for approval as set out in this report;
2. delegate authority to the Director of Place Making to grant planning permission subject to the completion of a legal agreement under s106 of the Town and Country Planning Act 1990 (as amended) based on the Heads of Terms identified at Appendix 2 of this report and the Conditions listed in Appendix 1 of this report and summarised below; and
London Borough of Newham Sunborn Yacht 3. if within six months of the resolution the legal agreement has not been completed, the Director of Place Making is delegated power to refuse planning permission.
Conditions – Summary
A summary of the proposed condition is set out below. Please refer to Appendix 1 for the proposed conditions in full.
1. Time Limit 2. Approved Documents 3. Construction and Logistics Plan 4. External Details 5. Photovoltaic cells (Glint & Glare) 6. Fixed Plant Machinery 7. Mains Power. 8. Delivery and Servicing Management Plan 9. Blue Badge Parking Bays 10. Landscaping 11. Designing Out Crime 12. Servicing and Management Plan 13. Café/Restaurant/Hot food takeaway/public house/ drinking establishments 14. Control of Dust, Emissions and Noise from Construction and Demolition 15. Control of Lighting on the Proposed Development 16. Submission of a Bird Hazard Management Plan 17. Urban Greening Factor
S106 –Heads of Terms
The Section 106 Legal Agreement Heads of Terms agreed between the Council and the Applicant are set out below:
1. Administrative 2. Local Labour via Our Newham 3. CCTV
NAME OF LEAD OFFICER: Darren Mackin POSITION: Director of Place Making
Originator of report: Liam McFadden Tel no: 020 337 34749 E-mail address: [email protected]
Human Rights Act
The provisions of the Human Rights Act 1998 have been taken into account in the processing of the application and the preparation of this report.
London Borough of Newham Sunborn Yacht Equalities
In determining this planning application the Council has regard to its equalities obligations including its obligations under section 149 of the Equality Act 2010.
For the purposes of this application there are no adverse equalities issues.
Environmental Impact Assessment
For the purposes of this application, this proposal has been screened and assessed under the Town and Country Planning (Environmental Impact Assessment) Regulations 2017 and considered not to warrant the need for Environmental Impact Assessment.
Local Government (Access to Information) Act 1985 Background papers used in preparing this report: Planning Application Statutory Register of Planning Decisions Correspondence with Adjoining Occupiers Correspondence with Statutory Bodies Correspondence with other Council Departments National Planning Policy Framework London Plan Local Plan Other relevant guidance
London Borough of Newham Sunborn Yacht
Contents PLANNING APPLICATION FACT SHEET SITE & SURROUNDINGS PROPOSAL RELEVANT HISTORY CONSULTATION PLANNING POLICIES AND GUIDANCE THE COMMUNITY INFRASTRUCTURE LEVY (CIL) REGULATIONS 2010 (AS AMENDED) ASSESSMENT APPENDIX 1: CONDITIONS AND INFORMATIVES APPENDIX 2: HEADS OF TERMS APPENDIX 3: PROPOSED PLANS AND IMAGES
London Borough of Newham Sunborn Yacht
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
1 Stansfeld Road. Beckton, London E6 5LUDecision The Strategic Development Committee RESOLVED to DEFER the application to a future meeting. The reasons for d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.