Highways Planned Maintenance Plan

Agreed Executive 5 papers

Cabinet agreed this item on Tuesday 2 April 2024. Below is the council's own wording, with the papers it was decided on.

Item17

Resolved

For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree to: i) Approve the proposed list of schemes planned for this year as set out in Appendix A. ii) Approve the replacement of the circa 800 Lamp Columns. iii) Grant delegated authority to the Corporate Director of Environment & Sustainable Transport, in consultation with the Cabinet Member for Environment, Highways and Sustainable Transport, to make alterations to the programme to facilitate other works, as required to maintain the highways to an acceptable standard. Alternatives Considered a) An alternative considered, is to do no planned maintenance or very little, and to only manage the condition of the network by reactive maintenance. This would mean the reactive maintenance budget, would over time, need to be increased year on year, to cater for the ongoing deterioration of the network. As the condition of the network deteriorates, the work required to reactively maintain it would become more intrusive and costly. This would lead to longer reactive maintenance programmes and an overall delay to the users of the network, as well as the network becoming unsafe. The number of complaints received about the condition of the network would also increase, with more time required by officers to handle these complaints. Due to the legal requirements to maintain the highways and footways in a safe condition and the level of deterioration in the highway network, this alternative was discounted. Therefore, it is felt that the planned maintenance programme as proposed is an essential component of the highway authority’s delivery plan, as it assists the Council in meeting its statutory obligations to ensure safety for all highway and footway users. Another consideration is not to undertake any resurfacing of the footway and carriageway network, and only undertake the structures and lighting works. However it is felt that it would be best if the remaining budget left within the KNM programme is used to serve the maintenance of the wider network. For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree to: i) Approve the proposed list of schemes planned for this year as set out in Appendix A. ii) Approve the replacement of the circa 800 Lamp Columns. iii) Grant delegated authority to the Corporate Director of Environment & Sustainable Transport, in consultation with the Cabinet Member for Environment, Highways and Sustainable Transport, to make alterations to the programme to facilitate other works, as required to maintain the highways to an acceptable standard. Alternatives Considered a) An alternative considered, is to do no planned maintenance or very little, and to only manage the condition of the network by reactive maintenance. This would mean the reactive maintenance budget, would over time, need to be increased year on year, to cater for the ongoing deterioration of the network. As the condition of the network deteriorates, the work required to reactively maintain it would become more intrusive and costly. This would lead to longer reactive maintenance programmes and an overall delay to the users of the network, as well as the network becoming unsafe. The number of complaints received about the condition of the network would also increase, with more time required by officers to handle these complaints. Due to the legal requirements to maintain the ... view the full minutes text for item 17.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report seeks approval for the funding of the Planned Highway Maintenance programme for year 2024-25. Our highway network is a universal and high profile asset that all of our residents and visitors to the borough use. The Planned Highway Maintenance Programme is the borough’s long-term programme to maintain the highway network. It is essential to ensure the safety of the highway and enables all forms of travel including walking, cycling and driving. Having a well maintained highway also supports the borough’s inclusive economic growth, education, employment opportunities and access to healthcare. Finally, planned maintenance interventions prolong the life of the highway asset and over time can reduce the requirement for reactive maintenance, to rectify defects.

Recommendations

2.1For the reasons set out in the report and its appendices, Cabinet is recommended to:

2.1.1 Approve the proposed list of schemes planned for this year as set out in Appendix A. 2.1.2 Approve the replacement of the circa 800 Lamp Columns. 2.1.3 Grant delegated authority to the Corporate Director of Environment & Sustainable Transport, in consultation with the Cabinet Member for Environment, Highways and Sustainable Transport, to make alterations to the programme to facilitate other works, as required to maintain the highways to an acceptable standard.

2 3. Background

3.1As part of the existing Keep Newham Moving programme, £100 million of capital funds was allocated to be invested into the borough’s footways, roads, street lighting, and residents’ priority parking zones. The resurfacing programme was allocated a total budget of £81.45million, with £75.45million forecast spend to date (including 23/24 forecast) and £6.0m budget remaining.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1.1. Appendix A: Proposed resurfacing list 2024-25Appendix 36 KB Download
PDF
2.3.2. Appendix B Planned Maintenance Strategy 01 DraftAppendix 571 KB Download
PDF
2.3.3. Appendix C Scheme Prioritisation Strategy 01 DraftAppendix 633 KB Download
PDF
2.3.4. Appendix D: Planned Maintenance Works Overview map DRAFTAppendix 1.8 MB Download
PDF
Highways Planned Maintenance PlanReport 433 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
JA
Councillor James AsserMember, present
CM
Councillor Charlene McLeanMember, apologies
ZA
Councillor Zulfiqar AliMember, present
NW
Councillor Neil WilsonMember, present
SJ
Councillor Sarah Jane RuizMember, present
SM
Councillor Shaban MohammedMember, present
AV
Councillor Amar VirdeeMember, present

On this subject at Newham

Search all
  1. Highways Planned Maintenance PlanThis decision
  2. Highways Planned Maintenance Plan ReportAgreed
  3. Highways Planned Maintenance Plan ReportAgreed
  4. Highways Planned Maintenance PlanAgreed
  5. Highways Planned Maintenance Plan ReportAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies