Colegrave School Suitability works, Tender Award

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 7 May 2024. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree to: i) To award a contract to Thomas Sinden Ltd to provide a new standalone classroom block, including a new PMLD Resource Provision at Colegrave Primary School with associated demolition works at a value of £3,848,533 as set out in this report. Alternatives Considered a) Do Nothing - The mobile classrooms at Colegrave Primary School are “life expired” and will require replacement within the next 5 years. The school will need to continue to fund the considerable ongoing maintenance repairs whilst the demountable are in place. If the existing buildings are not replaced, they will fall into a further state of disrepair, which will lead to a reduction in teaching space and a shortfall in pupil spaces. There would also be no fundamental improvements to the PMLD resource provision if this issue were not addressed. b) Various configurations to the provision and classrooms were reviewed, including internal refurbishment and new build accommodation being added as an extension to the existing building in different locations of the school. However, these all impacted on how the various year groups and key stage groups can be clustered together. It was also more difficult to provide a complete holistic design to satisfy the requirement of an up to date Profound Multiple Learning Disabilities (PMLD) resource provision. c) The proposed stand alone new build has been designed in partnership with the school to ensure that all of the needs to the students in the mainstream setting and those in the PMLD provision are met. This building is purpose built, whilst maintaining the connection to the existing building therefore it was decided that this option was best suited to meet the school brief and fitted within the budget which also creates a new positive identity that the local community can celebrate and be proud off. In addition the construction works can be coordinated to ensure disruption to the operational continuity of the school is minimised during term time. For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree to: i) To award a contract to Thomas Sinden Ltd to provide a new standalone classroom block, including a new PMLD Resource Provision at Colegrave Primary School with associated demolition works at a value of £3,848,533 as set out in this report. Alternatives Considered a) Do Nothing - The mobile classrooms at Colegrave Primary School are “life expired” and will require replacement within the next 5 years. The school will need to continue to fund the considerable ongoing maintenance repairs whilst the demountable are in place. If the existing buildings are not replaced, they will fall into a further state of disrepair, which will lead to a reduction in teaching space and a shortfall in pupil spaces. There would also be no fundamental improvements to the PMLD resource provision if this issue were not addressed. b) Various configurations to the provision and classrooms were reviewed, including internal refurbishment and new build accommodation being added as an extension to the existing building in different locations of the school. However, these all impacted on how the various year groups and key stage groups can be clustered together. It was also more difficult to provide a complete holistic design to satisfy the requirement of an up to date Profound Multiple Learning Disabilities (PMLD) resource provision. c) The proposed stand-alone new build has been designed in partnership with the school to ensure that all of the needs to the students in the mainstream setting and those in the PMLD provision are met. This building is purpose built, whilst maintaining the connection to the existing building therefore it was decided that this option was best suited to meet the school brief and fitted within the budget which also creates a new positive identity that the local community can celebrate and be proud off. In addition, the construction works can be coordinated to ensure disruption to the operational continuity of the school is minimised during term time.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report seeks Cabinet approval to award a contract to Thomas Sinden Ltd for £3,848,533 to provide a new standalone classroom block, including a new (replacement) Profound and Multiple Learning Disabilities (PMLD) resource provision. The contract was procured as a two stage design and build contract process. Thomas Sinden Ltd. was the successful tenderer and was awarded the first stage PCSA agreement under delegated authority. Those services have now concluded and approval is now sought to award the second stage design and build contract to Thomas Sinden Ltd.

Recommendations

1 2.1 For the reasons set out in the report and its appendices, Cabinet is recommended to agree to award a contract to Thomas Sinden Ltd to provide a new standalone classroom block, including a new PMLD Resource Provision at Colegrave Primary School with associated demolition works at a value of £3,848,533 as set out in this report,

Background

3.1The Council has made a significant capital investment in its schools estate over the last 10 years, which has been driven by significant growth in pupil numbers, in order to meet its legal duties to provide sufficient school places. As with many London Boroughs and urban areas, LBN is now experiencing a reduction in demand for primary school places, mainly as a result of a slowing down of birth rates. Current capital investment projects to create new places are therefore focused on providing additional specialist provision, particularly for autism, where there has been a significant growth in need.

3.2The Council also has a responsibility to ensure that existing maintained school provision is suitable to enable the effective delivery of education.

3.3At the end of 2020 and early in 2021, a consultation exercise, in the form of a letter, was sent to all maintained schools across the borough. The purpose of this exercise was to establish whether there were any major suitability/maintenance issues across the schools estate, which need to be addressed.

3.4A number of responses were received and an evaluation exercise was carried out to assess the areas of greatest need. This exercise determined that there was specific need at Colegrave Primary School.

3.5A survey of the current six mobile classrooms on the Colegrave Primary School site determined that they are “life expired” and are beyond the point repair or refurbishment. It is therefore deemed necessary to replace these with a new purpose-built facility.

3.6In addition to this, there is an existing Profound and Multiple Learning Disabilities (PMLD) resource provision on site. The current provision is situated in the main school and accommodates fourteen students. This requires significant modification to accommodate the current needs of the children. An assessment has been made and it has been determined that the current location of this unit would make it both difficult and disproportionately expensive to bring the provision up to current standards.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App 1 EQIA-589404274Appendix 43 KB Download
PDF
Colegrave School Suitability works, Tender AwardReport 151 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
JA
Councillor James AsserMember, present
CM
Councillor Charlene McLeanMember, apologies
ZA
Councillor Zulfiqar AliMember, present
NW
Councillor Neil WilsonMember, present
SJ
Councillor Sarah Jane RuizMember, present
SM
Councillor Shaban MohammedMember, present
AV
Councillor Amar VirdeeMember, present

On this subject at Newham

Search all
  1. Colegrave School Suitability works, Tender AwardThis decision
  2. Colegrave and Winsor Primary Schools Proposed suitability worksAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies