Cabinet, Tuesday 1 April 2025

Financing the 2025/26 Capital Programme

Agreed Executive 4 papers

Cabinet agreed this item on Tuesday 1 April 2025. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

Decision For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree: i) To authorise the Corporate Director of Resources to enter into new long-term borrowing of up to £454m that will fund the estimated borrowing requirement in 2025/26. Alternatives Considered a) Not to agree a long-term borrowing mandate will mean reliance on temporary borrowing to finance the approved capital programme. As set out in the financial implications, the bank rate level, is currently higher than the loan rate for longer durations (up to 5 years) which have already discounted a falling bank rate. This would potentially increase the amount of interest payable in 2025/26. However, long-term borrowing spreads and hence reduces risk as placing too much reliance on temporary borrowing exposes the Council to market interest rate and liquidity volatility when there is no PWLB back stop available for temporary borrowing. It also imposes pressure on staff resources having to turnover large volumes of temporary debt.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report authorises officers to borrow to finance the 2025/26 capital programme which was approved by Full Council on 27 February 2025. Additionally, it authorises borrowing to replace existing internal and temporary borrowing that has been used to fund historic capital expenditure. This is funding that relates to prior year capital expenditure, which for effective cash management purposes, has to date been funded using internal reserves or short-term borrowing. To provide longer term interest rate stability, this internal and temporary borrowing may need to be replaced by longer term external borrowing during 2025/26. All proposals in this report support the capital programme and its contribution towards the Council’s investment plans, aligning with the priorities outlined in the Council’s Strategic Framework.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
. Current Treasury positionAppendix 1 292 KB Download
PDF
. Prudential IndicatorsAppendix 2 958 KB Download
PDF
. Borrowing Requirement DetailAppendix 3 453 KB Download
PDF
Financing the 2025/26 Capital ProgrammeReport 295 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
CM
Councillor Charlene McLeanMember, present
ZA
Councillor Zulfiqar AliMember, present
NW
Councillor Neil WilsonMember, present
SJ
Councillor Sarah Jane RuizMember, present
AV
Councillor Amar VirdeeMember, present
BY
Councillor Blossom YoungMember, present
DJ
Councillor Dr John WhitworthMember, present

On this subject at Newham

Search all
  1. Financing the 2025/26 Capital ProgrammeThis decision
  2. Financing the 2025-26 Capital ProgrammeNoted
  3. Financing the Capital ProgrammeAgreed
  4. Financing the 2023/24 Capital ProgrammeAgreed
  5. Financing the Capital ProgrammeAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies