CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Newham
Cabinet, Tuesday 1 April 2025

Highways Planned Maintenance Plan Report

Agreed Executive 5 papers

Cabinet agreed this item on Tuesday 1 April 2025. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision For the reasons set out in the report and its appendices Cabinet RESOLVED to Agree to: i) Approve the proposed list of schemes planned for 2025/26 as set out in Appendix A, making use of funding approved at Cabinet on 18 February 2025; ii) Accept Department of Transport (DfT) funding of £692,000.00, making use of it on the renewal of sections of the Principal and Classified Road Network, as outlined in Appendix A, in line with the guidance set by the DfT on its use; and iii) Grant delegated authority to the Corporate Director of Environment & Sustainable Transport, in consultation with the Cabinet Member for Environment, Highways and Sustainable Transport, to make alterations to the programme set out in Appendix A to facilitate other works, as required to maintain the highways to an acceptable standard. Alternatives Considered a) An alternative considered, is to do no planned maintenance or very little, and to only manage the condition of the network by reactive maintenance. This would mean the reactive maintenance budget, would over time, need to be increased year on year, to cater for the ongoing deterioration of the network. As the condition of the network deteriorates, the work required to reactively maintain it would become more intrusive and costly. This would lead to longer reactive maintenance programmes and an overall delay to the users of the network, as well as the network becoming unsafe. The number of complaints received about the condition of the network would also increase, with more time required by officers to handle these complaints. Due to the legal requirements to maintain the highways and footways in a safe condition and the level of deterioration in the highway network, this alternative was discounted. Therefore, it is felt that the planned maintenance programme as proposed is an essential component of the highway authority’s delivery plan, as it assists the Council in meeting its statutory obligations to ensure safety for all highway and footway users. b) Another consideration is not to undertake any resurfacing of the footway and carriageway network, and only undertake the essential structures works. However, it is felt that it would be best if the remaining budget left within the KNM programme is used to serve the maintenance of the wider network, in line with its original governance.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Executive summary

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed programme and scheme list for 2025-26Appendix A 60 KB Download
PDF
HIAMF– Planned Maintenance StrategyAppendix B 534 KB Download
PDF
HIAMF: Scheme Prioritisation StrategyAppendix C 599 KB Download
PDF
Map illustrating next year’s planned maintenance programme including completed works to date as part of Keep Newham Moving (2016-current)Appendix D 1.7 MB Download
PDF
Highways Planned Maintenance Plan ReportReport 445 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
CM
Councillor Charlene McLeanMember, present
ZA
Councillor Zulfiqar AliMember, present
NW
Councillor Neil WilsonMember, present
SJ
Councillor Sarah Jane RuizMember, present
AV
Councillor Amar VirdeeMember, present
BY
Councillor Blossom YoungMember, present
DJ
Councillor Dr John WhitworthMember, present

On this subject at Newham

Search all
  1. Highways Planned Maintenance Plan ReportThis decision
  2. Highways Planned Maintenance Plan ReportAgreed
  3. Highways Planned Maintenance PlanAgreed
  4. Highways Planned Maintenance PlanAgreed
  5. Highways Planned Maintenance Plan ReportAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies