London Borough of Newham
Cabinet, Tuesday 20 January 2026

Local (Transport) Implementation Plan (LIP) 26/27

Agreed Executive 5 papers

AI summaryNewham Cabinet approves extra 2026/27 transport schemes worth £1.6m, plus £6.7m for Royal Docks Corridor Phase 6, delegating scheme delivery to officers.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedAdditional LIP schemes and RDC Phase 6 funding
MoneyNot stated
What happens nextPublic consultationOn each scheme, plus GLA deed of variation
Who it affectsBorough roads and public realmNewham residents, road and transport users

What was decided

Cabinet approved an additional Local Implementation Plan programme of schemes for 2026/27, totalling £1.6m, on top of the programme approved in December 2024. Report 2.1, 4.1

Cabinet allocated £6.7m for Phase 6 of the Royal Docks Corridor project, made up of up to £5m underspend from earlier phases, £1.3m from a TfL phasedown contribution via the GLA, and £0.4m from developers and statutory bodies. Report 2.2, 4.10, 4.11, 4.13

Cabinet delegated authority to the Corporate Director of Environment and Sustainable Transport, in consultation with the Lead Member, to run consultation, vary the GLA funding deed, use the Council's Term Highway Frameworks Contract, and make supporting traffic orders. Report 2.3, 2.4, 2.6, P9, 2.10, 2.11

Why

The funding is external, does not require match funding from the Council, and the schemes deliver the Mayor of London's Transport Strategy and the Council's Building a Fairer Newham priorities, including health, climate and safer streets. Report 3.1, 5.1, 5.4, 5.6, 8.1, 8.22

Not submitting a spending plan to TfL would risk losing a substantial element of highways and sustainable transport funding and would put the Council in breach of the GLA Act. Report 3.1, 6.1, 8.8

What happens next

Each scheme listed in section 4 of the report will go through its own public consultation and engagement, with co-design on several schemes, before implementation. Report 2.4, 7.1, 7.2

Officers will enter into a deed of variation to the 19 January 2023 GLA funding agreement so underspend and £1.3m of additional GLA money can be used on Phase 6, and the GLA grant will be claimed in arrears against milestones. Report 2.6, 2.7, 4.12, 8.5, 8.13

Statutory consultation on supporting Traffic Regulation Orders will be carried out, with orders made if no material objections are received, and works delivered via the Council's existing Term Highway Frameworks Contract. Report 2.10, 2.11, P9, 8.21

The money

  • £6.7m Total allocation for Royal Docks Corridor Phase 6 Report 2.2
  • £5m Underspend from previous RDC project phases (up to) Report 2.2, 3.14
  • £1.3m TfL phasedown contribution via GLA for RDC Phase 6 Report 2.2, 4.11
  • £0.4m Funding from developers and statutory bodies (s106 etc.) for RDC Phase 6 Report 2.2, 4.13, 8.6
  • £1.6m Total of additional LIP programme schemes for 2026/27 Report 4.1
  • £0.2m Leytonstone Road design Report P33
  • £0.2m RDC Phase 8 Connaught Bridge Node Report 4.4
  • £0.25m RDC Phase 9 Cycleway 3 Crossing Report 4.4
  • £0.15m RDC Phase 10 Silvertown to Woolwich Crossings Report 4.4
  • £0.25m East Village Connections detailed design Report 4.5, P38
  • £0.3m Prince Regent Lane Bus Priority Phase 2 delivery Report 4.6, P40
  • £0.2m Siding Street Bus Priority delivery Report 4.7, P42
  • £0.1m Borough-wide Bus Priority Feasibility (Twelvetrees, Green Street, SL2) Report 4.8, P44, P45

Options considered

  • Rejected: Do not submit an LIP spending plan to TfL. Would lose substantial highways and sustainable transport funding and would breach the GLA Act Report 6.1, 8.8
  • Rejected: Submit a different LIP programme. Risk of not meeting TfL scheme eligibility guidance or not delivering the Council's own priorities Report 6.2
  • Rejected: Do not proceed with RDC Phase 6. Reallocated underspend and additional GLA funding can only be used for this purpose, so not proceeding would sacrifice external investment in the public realm Report 6.3, 4.10, 4.11

Implications

  • Financial: No Council match funding is required, as all funding is external from TfL, the GLA, and developer and statutory contributions; the GLA £1.3m will be claimed in arrears against milestones and rigorous monitoring is needed to keep within budget. Report 8.1, 8.4, 8.5
  • Legal: Under the GLA Act, the Council must submit an annual LIP spending submission and implement it; the Mayor of London can direct non-compliant boroughs and recover costs as a civil debt. A deed of variation to the 19 January 2023 GLA funding agreement (clause 11 allows variation) is needed for Phase 6. Report 3.1, 8.8, 8.9, 8.11, 8.12, 8.13
  • Equalities: The LIP Equalities Impact Assessment concludes the programmes have primarily positive or neutral impacts on equality groups with no significant negative impacts that cannot be addressed; many schemes include accessibility upgrades such as dropped kerbs, audible signals, and bus stop accessibility improvements, and the Council now works with Transport for All on equalities evaluation. Report 8.15, 8.17, 8.18, 8.19
  • Climate: The programme supports the Council's Just Transition Plan by prioritising non-motorised and active travel to cut carbon emissions and air pollution, and contractors are being required to give carbon commitments and use recycled and lower-embodied-carbon materials where possible. Report 8.22, 8.23
  • Risk: Without an agreed programme the Council could breach the GLA Act and lose TfL funding; new TROs can only be made if no material objections are received; the GLA grant is claimed in arrears so delivery milestones must be met. Report 2.11, 6.1, 8.4, 8.5, 8.8
  • Staffing: TfL funding includes an element to cover design, consultation, and management fees and associated staffing costs, and further legal resources may be needed as the programme progresses after consultation. Report 8.3, 8.10

Who and where

  • Residents and road, walking, cycling and public transport users across the borough, including those near the Royal Docks, East Village, Stratford, Leytonstone, Prince Regent Lane, Siding Street, and school streets schemes Report 4.4, 4.5, 4.6, 4.7, 5.4, 5.6
  • Developers and statutory bodies contributing around £0.4m in s106 and other payments towards the Royal Docks Corridor Phase 6 Report 4.13, 8.6
  • Neighbouring landowners and GLA and TfL partners in the Royal Docks area, who were consulted on Phase 6 Report 7.4
  • The Council's Highways and Sustainable Transport team and its term highways contractors, who will deliver the additional design and construction work Report P9, 2.1, 8.3, 8.21

Timeline

  • 22 September 2022: Cabinet approved the Royal Docks Corridor project and entry into a £21m GLA grant funding agreement Report 3.13, 9.1
  • 19 January 2023: GLA grant funding agreement for the Royal Docks Corridor signed Report 3.13, 8.12
  • 3 December 2024: Cabinet approved the draft LIP programme for 2025/26 to 2027/28 and the Sustainable Transport Strategy Report 3.4, 9.2, 9.3
  • 23 October 2025: Cabinet members consulted on the proposed delivery plan Report 7.3
  • 2026/27: Delivery year for the additional LIP schemes and RDC Phase 6 Report 2.1, 2.2, 4.1

Plain English for the jargon

  • LIP: Local Implementation Plan, the document by which London boroughs set out how they will deliver the Mayor of London's Transport Strategy
  • TfL: Transport for London, the regional transport authority
  • GLA: Greater London Authority
  • MTS: Mayor of London's Transport Strategy
  • RDC: Royal Docks Corridor, a major transport and public realm scheme
  • AST: Active and Sustainable Travel, the Council's own capital programme
  • JTP: Just Transition Plan, the Council's plan for a fair move to a low-carbon borough
  • BaFN: Building a Fairer Newham, the Council's corporate plan
  • EqIA: Equalities Impact Assessment
  • s106: Section 106 planning obligation payments from developers
  • TRO: Traffic Regulation Order, the legal order needed to enforce many traffic and parking restrictions
  • MD: Mayoral Decision, a formal decision by the Mayor of London
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to Agree: i) The additional Local Implementation Plan (LIP) programme of schemes and interventions to be delivered by the Highways and Sustainable Transport team with Transport for London (TfL) funding in 2026/27, over and above those approved by Cabinet in December 2024, as set out in section 4 of the report. ii) The allocation of £6.7m for Phase 6 of the RDC project, comprising of up to £5m underspend of the previous RDC project phases, £1.3m from TfL phasedown contribution (via GLA), and £0.4m from the additional funding secured from developers and statutory bodies. iii) To delegate authority to the Corporate Director of Environment and Sustainable Transport, in consultation with the Lead Member for Environment and Sustainable Transport to: a) commence public consultation on the individual schemes listed in section 4, and consider any consultation responses arising out of consultation on the schemes; b) make such amendments to the schemes as are considered necessary, taking account of the results of the public consultation (where undertaken ); c) enter into a deed to vary the funding agreement made with the GLA on 19 January 2023 (attached at Appendix 1) enabling the Council to access and utilise underspend and receive additional monies from GLA for use on Phase 6 of the Royal Docks Corridor Project; d) receive and spend £1.3m additional funding from the GLA on Phase 6 of the Royal Docks Corridor Project; e) approve use of the Council’s Term Highway Frameworks Contract to implement and complete works; f) implement the schemes with the inclusion of such amendments as are considered necessary; g) undertake the necessary statutory consultation processes regarding the supporting traffic regulation orders for the implementation of the scheme; and h) make the supporting traffic orders as required, subject to no material objections being received. Alternatives Considered 1) With regards to the LIP, the alternative would be to not submit a spending plan to TfL and to lose a substantial element of the Council’s funding for highways and sustainable transport interventions. We would also be in breach of the terms of the GLA Act 2000 if spending submissions were not done. 2) An alternative programme could have been devised and submitted but would run the two-fold risk of either not meeting TfL guidelines for scheme submissions or not delivering on the Council’s own priorities. As noted above, the guidance from TfL includes a prescriptive list of what schemes are eligible for funding. 3) In relation to RDC Phase 6, reallocation of the underspend and receiving the additional GLA funding can only be used for this purpose, hence the alternative would be not proceeding with the scheme and sacrificing this external investment in the public realm of the borough.
Word for word from the decision Newham published for this meeting. Source: mgov.newham.gov.uk

Follow this further

Built from Newham's papers

What the report saysPro

Report to Cabinet

Recommendations

For the reasons set out in the report and its appendices, Cabinet is recommended to agree:

2.1The additional Local Implementation Plan (LIP) programme of schemes and interventions to be delivered by the Highways and Sustainable Transport team with Transport for London (TfL) funding in 2026/27, over and above those approved by Cabinet in December 2024, as set out in section 4 of this report.

2.2The allocation of £6.7m for Phase 6 of the RDC project, comprising of up to £5m underspend of the previous RDC project phases, £1.3m from TfL phasedown contribution (via GLA), and £0.4m from the additional funding secured from developers and statutory bodies.

2.3To delegate authority to the Corporate Director of Environment and Sustainable Transport, in consultation with the Lead Member for Environment and Sustainable Transport to:

2.4commence public consultation on the individual schemes listed in section 4, and consider any consultation responses arising out of consultation on the schemes;

2.5make such amendments to the schemes as are considered necessary, taking account of the results of the public consultation (where undertaken);

2.6enter into a deed to vary the funding agreement made with the GLA on 19 January 2023 (attached at Appendix 1) enabling the Council to access and utilise underspend and receive additional monies from GLA for use on Phase 6 of the Royal Docks Corridor Project;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SIGNED RDC Funding Agreement £21m: Jan 2023Appendix 1 5.1 MB Download
PDF
RDC Phase 6 DrawingAppendix 2 6 MB Download
PDF
GLA Mayoral Decision SIGNEDAppendix 3 852 KB Download
PDF
RDC Additional Contributions (LBN)Appendix 4 28 KB Download
PDF
Local (Transport) Implementation Plan (LIP) 26/27Report 279 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
RF
Rokhsana Fiaz OBE, Mayor of NewhamChair, present
CM
Councillor Charlene McLeanMember, present
ZA
Councillor Zulfiqar AliMember, present
SJ
Councillor Sarah Jane RuizMember, present
AV
Councillor Amar VirdeeMember, present
BY
Councillor Blossom YoungMember, present
DJ
Councillor Dr John WhitworthMember, present
RC
Councillor Rita ChadhaMember, apologies

On this subject at Newham

Search all
  1. Local (Transport) Implementation Plan (LIP) 26/27This decision
  2. Sustainable Transport Strategy (STS) and Local Implementation Plan (LIP) 2025/26 to 2027/28Agreed
  3. Local Implementation Plan (LIP) 3 Draft Submission To Transport for LondonAgreed

More from Newham Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Quarter 2 2026/27 Budget Monitoring ReportDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i ) Note the General Fund Re... Noted Open
17 Nov 2026 Draft Budget Proposals for 2027/28 and the MTFPDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To agree, for the purpose... Agreed Open
17 Nov 2026 Newham Lane Rental SchemeDecision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Approve the roads the Cou... Approved Open
17 Nov 2026 Holiday Activities and Food (HAF) Programme Grant Funding Approach 2027 and 2028Decision For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) To officers allocating HA... Decided Open
17 Nov 2026 Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027For the reasons set out in this report and its appendices, Cabinet RESOLVED to: i) Accept £ 4,021,591 of grant fundin... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies