To note the current forecast position and the key risks within these at this early stage To wait until later in the Autumn before any firm decisions on use of any under-spend is made, when there will be greater confidence in the financial forecasts Cabinet Members, with Heads of Service maintain on-going strong financial management To note that current forecasts assume any under-spending on the school based redundancy budget is transferred to a specific reserve to manage future risks in this area and approve this for 2015/16. To note that current forecasts assume any school based over-spending are managed by a corresponding transfer from their specific school reserves to fund and to approve this for 2015/16. To approve the use of £120k of the ‘Landfill reserve’, currently at £163k, to fund a door knocking’ initiative to increase awareness of and encourage more recycling to meet the Council’s recycling targets
Word for word from the decision Newport published for this meeting.Source: democracy.newport.gov.uk
Subject July Revenue budget monitor Purpose This report details the current forecast position on the Council’s revenue budget and the key issues and risks being managed.
Author HoF
Ward All
Summary Based on the July financial monitoring, the Council is forecasted to underspend by £1.3m, excluding any impact of under-spending on the contingency budget. A number of key risks to this forecast, in particular Social Care forecasts and cross-cutting savings exist and it will be later in the Autumn when there should be more confidence in forecasts and therefore when any firm decisions on how to utilise this under-spending can be made.
In saying this, it is a good position at this early part of the financial year and provides a good foundation to move through the year. Given the risks in these forecasts and inherent in parts of the Councils budget, Cabinet Members should ensure their service responsibilities maintain on-going strong financial management
Proposal Cabinet are asked to
Note the current forecast position and the key risks within these at this early stage To wait until later in the Autumn before any firm decisions on use of any under- spend is made, when there will be greater confidence in the financial forecasts Cabinet Members, with Heads of Service maintain on-going strong financial management To note that current forecasts assume any under-spending on the school based redundancy budget is transferred to a specific reserve to manage future risks in this area and approve this for 2015/16. To note that current forecasts assume any school based over-spending are managed by a corresponding transfer from their specific school reserves to fund and to approve this for 2015/16. To approve the use of £120k of the ‘Landfill reserve’, currently at £163k, to fund a door knocking’ initiative to increase awareness of and encourage more recycling to meet the Council’s recycling targets
Action by -HoF / SLT – robust on-going forecasting -Cabinet/HoF/SLT – preliminary work on identifying key issues to which any under- spending confirmed later in the year could be earmarked for. Timetable On-going This report was prepared after consultation with:
Directors Head of Legal / HR & Business Change
Signed: Head of Finance Background July 2015 Revenue budget forecasts – overview and key assumptions
1. The revenue budget forecast for 2015/16 based on the July monitoring is shown in Appendix One.
2. This report highlights the current financial risks and the actions being taken to mitigate them (Paragraph 7). The Council operates a risk based budget monitoring process, identifying key risk areas to review in detail on a monthly basis. This report is a summary report of key issues that explains the current position and some of the key risks currently in place which impact on financial management. There are detailed, monthly, service based reports which HoS receive and which Cabinet Members have access to and these provide the next level of detail to understand the financial position with services, risks and actions being taken.
3. The forecast shows an overall underspend of c£1.3m. Key assumptions within this are:
No use of the contingency budget to deal with general overspending. Other approved costs to deliver planned 15/16 savings are funded from the Invest to Save Reserve
4. The key issue above is ‘no use of general contingency’, if the Council operates within its approved budget without using this; it will increase the under-spending to c£2.8m at year end.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.