Cabinet, Monday 12 January 2026 at 4.00pm

November Revenue Budget Monitor

Noted Executive 1 paper

AI summaryCabinet noted a forecast revenue underspend of (1,342) for 2025/26 at November, with schools 4,506 over budget and risk-based services 3,948 over. Cabinet approved an infrastructure virement and a new earmarked reserve.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSchools 4,506 over; risk areas 3,948 over
Money(1,342) overall, in £'000Schools 4,506 over; risk areas 3,948 over
What happens nextVirement and new reserve approvedInfrastructure virement and new earmarked reserve per 4.3
Who it affectsSchools and social servicesDemand pressures in adults, children and homelessness

What was decided

Cabinet noted the overall revenue budget forecast position and the current shortfall in delivery of 2025/26 revenue budget savings.

Cabinet noted the overall schools position and the risk of further individual school deficits by year end, alongside movements in reserves and other identified risks.

Cabinet approved the budget virement within the infrastructure service area and approved the allocation of funds to a new earmarked reserve for 2025/26 and on-going, subject to the Head of Finance raising no issues.

Why

Service areas (including schools) are forecast to spend 9,271 over budget in cash terms, with schools alone 4,506 over and risk-based demand areas 3,948 over. Report P1, P2, P9

After a 4,506 transfer from schools reserves, the net service overspend falls to 4,765, and after capital financing and contingency movements the overall position shows a (1,342) underspend. Report P3, P4, P6, P7, P8

Major pressures are in Adult Services community care (non-residential 1,586 over, supported living 812 over, residential income short by 979), Children Services out-of-area residential placements 2,566 over, ALN local provision development 842 over, and homelessness 918 over. Report P9

What happens next

A virement of existing infrastructure budgets between cost centres is to be actioned in line with financial regulations as set out at 2.7.

A new earmarked reserve is to be created with funding allocated for 2025/26 and on-going, conditional on no concerns from the Head of Finance on overall council finances, as set out at 4.3.

Schools balances are to be kept under review, with a forecast closing reserves total of 9,105,997 across all schools at 31 March 2026. Report P21

The money

  • (1,342) Overall revenue forecast variance in £'000 (under budget) Report P8
  • 4,506 Schools forecast overspend in £'000 Report P1
  • (4,506) Transfer from schools reserves in £'000 Report P3
  • 9,271 Service areas (inc schools) gross overspend in £'000 Report P2
  • 4,765 Service areas net of schools reserves in £'000 Report P4
  • 3,948 Risk-based demand areas overspend in £'000 Report P9
  • 428,726 Original revenue budget in £'000 Report P8
  • 427,384 Forecast revenue outturn in £'000 Report P8

Options considered

  • Chosen: Note the budget forecast, the savings shortfall, schools position, reserve movements and identified risks
  • Chosen: Approve the virement within the infrastructure service area. To transfer existing expenditure budgets to different cost centres in accordance with financial regulations, as set out in 2.7
  • Chosen: Approve allocation to a new earmarked reserve for 2025/26 and on-going. Subject to the Head of Finance raising no issues regarding council finances, as set out in 4.3

Implications

  • Financial: Service areas are forecasting a 9,271 overspend in £'000 before the 4,506 transfer from schools reserves, with the overall position showing a (1,342) underspend after capital financing and contingency. Report P1, P2, P3, P4, P6, P8
  • Financial: Total usable reserves are forecast to fall from a balance of 130,091 to 107,842 in £'000 by 31 March 2026, with movements across risk, enabling, smoothing and other earmarked reserves. Report P22, P23, P24, P25
  • Risk: Risk-based demand areas show a 3,948 overspend in £'000, driven by adult community care, children out-of-area residential placements, ALN provision and homelessness pressures. Report P9
  • Staffing: A new earmarked reserve is being established; the decision is subject to the Head of Finance raising no issues about overall council finances.
  • Legal: The infrastructure virement is to be carried out in accordance with the council's financial regulations.
  • Other: School balances show a forecast closing total of 9,105,997 at 31 March 2026, including individual deficits at Rogerstone Primary (28,302) and St Woolos Primary (2,199). Report P21

Who and where

  • Schools in Newport, with a forecast closing reserves total of 9,105,997 at 31 March 2026 Report P21
  • Adult Services users, with community care pressures of 1,586 in non-residential and 812 in supported living (in £'000) Report P9
  • Children Services users, with out-of-area residential placements 2,566 over budget (in £'000) Report P9
  • Homelessness service users, with a 918 overspend in £'000 Report P9
  • ALN pupils, with local provision development 842 over and out-of-county 680 under (in £'000) Report P9
  • Council taxpayers, funding the budget through council tax income of 99,404 and surplus of 1,062 (in £'000) Report P8

Timeline

  • November 2025 (month end): Revenue monitoring position reported (Appendix 2) Report P9, P20
  • Dated 5 January 2026: Background papers prepared Report P1
  • 12 January 2026: Cabinet decision taken
  • 31 March 2026 (forecast): Forecast year-end revenue outturn of 427,384 against budget of 428,726 (in £'000) Report P8
  • 31 March 2026 (forecast): Forecast closing school reserves balance of 9,105,997 Report P21
  • 31 March 2026 (forecast): Forecast total usable reserves balance of 107,842 in £'000 Report P25

Plain English for the jargon

  • Virement: Transfer of budget between cost centres within a service area without changing the overall total.
  • Earmarked reserve: Money set aside for a specific planned purpose rather than for general use.
  • ISB: Individual Schools Budget, the share of the education budget delegated to schools.
  • ALN: Additional Learning Needs, the Welsh term for special educational needs support.
  • RSG and NNDR: Revenue Support Grant and National Non-Domestic Rates, the main Welsh Government funding streams for the council.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

That Cabinet - · Noted the overall budget forecast position outlined within this report. · Noted the current overall shortfall in the delivery of the 2025/26 revenue budget savings. · Noted the overall position in relation to schools, acknowledging the risk that further individual deficit positions could emerge by the end of the financial year. · Noted the forecast movements in reserves. · Noted the risks identified throughout the report and in the Head of Finance comments, such as in relation to demand issues being faced. · Approved the budget virement to transfer existing expenditure budgets to different cost centres within the infrastructure service area in accordance with the financial regulations and as set out in 2.7. · Approved the recommendation to allocate funds to a new earmarked reserve, as set out in 4.3 for 2025/26 and on-going, subject to no issues raised by the Head of Finance as regards Council finances.
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Report Cabinet Part 1

Date: 12 January 2026

Subject November Revenue Budget Monitor Purpose To highlight the current forecast position on the Council’s revenue budget and the financial risks and opportunities that present themselves within the November position. This is the third Cabinet update of the 2025/26 financial year.

Author Service Manager Accountancy (Finance Business Partnering)

Ward All

Summary The November 2025 revenue monitoring position reflects a forecasted underspend of £2.404m taking into account the contingency budget. Service areas are collectively forecast to overspend by £4.7m, excluding schools. This significant service area overspending is offset by underspends in non-service areas, particularly the capital financing budget, producing a broadly balanced revenue budget forecast at this point.

The most significant areas of service area overspending are within: • Social Services due to the demand for non-residential care packages, supported living placements and out of area children’s placements, • Housing & Communities, due to the demand for temporary accommodation, • Education, due to increased costs of local Additional Learning Needs (ALN) provision.

Schools are separately projected to overspend on their revenue funding by £4.5m. This will be funded from schools’ own reserves. The overspending comes from both one-off as well as an element of recurring expenditure. Going forward, there is a risk that this level of recurring expenditure in excess of base budget funding will result in certain individual schools entering a deficit budget position i.e. negative reserve. Therefore, close monitoring will be required during the remainder of this year to ensure that schools are managing their finances as required and taking action to ensure that deficit positions are avoided wherever possible.

Whilst this report represents the third financial monitoring update to Cabinet for the current financial year, reflecting on performance up to the end of November, it should be noted that the position remains subject to change and may alter by the end of March. While a number of previously identified financial uncertainties have been clarified, significant variables persist. These include the potential for increased demand in people- based services and the possibility of additional in-year, specific grant allocations arising as the year-end approaches.

The appendices to the report are as follows: Appendix 1 Revenue Summary Monitor - November 2025 Appendix 2 Revenue Monitoring Dashboard - November 2025 Appendix 3 School Balances Position Appendix 4 2025/26 Forecast Reserve Movements Proposal That Cabinet:

• Note the overall budget forecast position outlined within this report. • Note the current overall shortfall in the delivery of the 2025/26 revenue budget savings. • Note the overall position in relation to schools, acknowledging the risk that further individual deficit positions could emerge by the end of the financial year. • Note the forecast movements in reserves. • Note the risks identified throughout the report and in the HoF comments, such as in relation to demand issues being faced. • Approve the budget virement to transfer existing expenditure budgets to different cost centres within the infrastructure service area in accordance with the financial regulations and as set out in 2.7. • Approve the recommendation to allocate funds to a new earmarked reserve, as set out in 4.3 for 2025/26 and on-going, subject to no issues raised by the HoF as regards Council finances.

Action by Cabinet Members / Head of Finance / Executive Board:

• All HoS implement actions to ensure that agreed 2025/26 and previous year budget savings are achieved as soon as practically possible, but by the end of the financial year at the latest. • Cabinet Members and HoS promote and ensure robust financial management and forecasting throughout all service areas.

Timetable Immediate This report was prepared after consultation with:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
November Revenue Budget MonitorReport 336 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
DB
Councillor Dimitri BatrouniChair, present
DD
Councillor Deb DaviesCommittee Member, present
MS
Councillor Mark SpencerCommittee Member, present
ES
Councillor Emma Stowell-CortenCommittee Member, present
LL
Councillor Laura LaceyCommittee Member, present
JH
Councillor Jason HughesCommittee Member, present
JC
Councillor James ClarkeCommittee Member, present
YF
Councillor Yvonne ForseyCommittee Member, present
SA
Councillor Saeed AdanCommittee Member, present
RH
Councillor Rhian HowellsCommittee Member, present

On this subject at Newport

Search all
  1. November Revenue Budget MonitorThis decision
  2. November Revenue Budget MonitorNoted

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies