I. To note the current forecast position and the key risks within these at this stage II. To delay making firm decisions on use of any under-spends until January, when there will be further confidence in the financial forecasts III. To ensure that Directors & Heads of Service maintain on-going strong financial management IV. To note the current use of the Invest to Save reserve and its significantly reduced balance, and that following review of the Pay Reserve, any surplus balances there be transferred to the Invest to Save reserve to fund future Change/Efficiency programmes. V. To note the use of Christmas Lights reserve
Word for word from the decision Newport published for this meeting.Source: democracy.newport.gov.uk
Subject September Revenue budget monitor Purpose This report details the current forecast position on the Council’s revenue budget and the key issues and risks being managed.
Author HoF
Ward All
Summary Based on the September financial monitoring, the Council is forecasted to underspend by £1.4m, excluding any impact of under-spending on the contingency budget. A number of key risks to this forecast, in particular Social Care forecasts and cross-cutting savings continue to exist, therefore the January report will give further confidence as to the use of the underspends.
In saying this, it is a good position at this part of the financial year and provides a good foundation to move into the second half of the financial year. Given the on-going risks in these forecasts and inherent in parts of the Councils budget, Cabinet Members should ensure their service responsibilities maintain on-going strong financial management
Proposal Cabinet are asked to
Note the current forecast position and the key risks within these at this stage To delay making firm decisions on use of any under-spends until January, when there will be further confidence in the financial forecasts Directors & Heads of Service maintain on-going strong financial management Note the current use of the Invest to Save reserve and its significantly reduced balance, and that following review of the Pay Reserve, any surplus balances there be transferred to the Invest to Save reserve to fund future Change/Efficiency programmes. Note the use of Christmas Lights reserve
Action by -HoF / SLT – robust on-going forecasting -Cabinet/HoF/SLT – preliminary work on identifying key issues to which any under- spending confirmed later in the year could be earmarked for.
Timetable On-going This report was prepared after consultation with: Background September 2015 Revenue budget forecasts – overview and key assumptions
1. The revenue budget forecast for 2015/16 based on the September monitoring is shown in Appendix One.
2. This report highlights the current financial risks and the actions being taken to mitigate them (Paragraph 7). The Council operates a risk based budget monitoring process, identifying key risk areas to review in detail on a monthly basis. This report is a summary report of key issues that explains the current position and some of the key risks currently in place which impact on financial management. There are detailed, monthly, service based reports which HoS receive and which Cabinet Members have access to and these provide the next level of detail to understand the financial position with services, risks and actions being taken.
3. The forecast shows an overall underspend of c£1.4m. Key assumptions within this are:
No use of the contingency budget to deal with general overspending. Other approved costs to deliver planned 15/16 savings are funded from the Invest to Save Reserve, which are further detailed in Appendix Two.
4. The key issue above is ‘no use of general contingency’, if the Council operates within its approved budget without using this; it will increase the under-spending to c£2.8m at year end.
5. The overall Council financial position is very good at this point. It mainly comes from ‘non-service’ budgets, in particular capital financing/PFI at c£1.3m. The saving from ‘capital financing/PFI’ was expected as this was a significant saving in 2014/15 as well. Service areas are overall slightly underspent by c£100k after taking into account reserves transfers directly related to some specific under-spending / overspending within services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.